Supreme Court of India (Full Bench (FB)- Three Judge)

SPECIAL APPEAL DEFECTIVE, 461-462 of 2016, Judgment Date: Jan 20, 2016

                                                                  REPORTABLE

                        IN THE SUPREME COURT OF INDIA
                        CIVIL APPELLATE JURISDICTION

             CIVIL APPEAL NOS.       461-462            OF  2016
              (Arising out of SLP (C) Nos.29680-29681 of 2010)


VENKATESH CONSTRUCTION COMPANY                                   ….Appellant

                                   Versus

KARNATAKA VIDYUTH KARKHANE
LIMITED (KAVIKA)                                               ...Respondent



                               J U D G M E N T



R. BANUMATHI, J.


      Leave granted.

2.    These appeals assail the judgment dated 15.06.2010 in R.F.A.  Nos.1051
of 2003 and 1076 of 2003, by which the High  Court  of  Karnataka  vide  the
common impugned judgment reversed  the  judgment  of  the  trial  court  and
allowed the appeal of respondent-defendant.  While doing so, the High  Court
dismissed the cross-appeal preferred by the appellant-plaintiff.
3.           Briefly  stated  case  of  the  appellant-plaintiff   is   that
appellant-company is engaged in construction of dams and other  civil  works
and registered as  a  civil  contractor  for  the  Government  of  Karnataka
amongst others. The respondent-defendant invited tender on  17.08.1991  “for
constructing a compound wall along the boundary line of Kavika and also  for
constructing underground sump, shed to store  useful  laminations  and  also
core assembly shop for these works”.  The appellant responded  to  the  said
tender  and  appellant’s  tender  was  accepted  by   the   respondent.   On
12.02.1992,  a  contract  was  executed  between  the  appellant   and   the
respondent incorporating the terms and conditions and the cost of  work  was
estimated at Rs.10,86,200/-.  The appellant had  quoted  the  rates  on  the
premise that the earth work for the foundation  was  to  the  depth  of  1.5
metres and average width of 4.25 metres. However, after the work  commenced,
even while digging earth to one foot depth, it was  noticed  that  soil  was
caving in and there was seepage of  water  from  Vrushabhavathi  river.  The
appellant was instructed by the respondent’s engineers to dig  earth  up  to
four metres depth until hard soil bed is reached.  Accordingly, in order  to
make a trench  of  four  metres  depth,  appellant  had  to  excavate  earth
commencing from width of six metres at  the  ground  level  and  the  entire
nature of work changed and appellant had to  incur  additional  expenses  on
account of the changed plan. The changed measurements were verified  by  the
engineers nominated by the respondent and a  payment  of  Rs.4,50,000/-  was
made in two running bills. The respondent then asked the appellant  to  stop
the work till the new designs are given by  the  respondent  which  was  not
forthcoming.   Vide  several  letters  appellant   sought   permission   for
continuation of the work, but, there was no response  from  the  respondent.
Finally, after issuing legal notice dated 15.03.1993,  for  which  no  reply
was given by the  respondent.   The  appellant  filed  a  civil  suit  being
Original Suit No.11037 of 1993 in the court of Additional City Civil  Judge,
Bangalore, making a claim  of  rupees  thirty  lakhs  under  various  heads,
interalia, on the work already completed,  towards  the  extra  earth  work,
stocking of materials and also liquidated damages and others.
4.     Admitting  the  execution  of  the  contract  dated  12.02.1992,  the
respondent filed a written statement contending  that  the  construction  of
the compound wall was in accordance with the estimate and  the  question  of
the respondent’s directing the appellant to stop the ongoing work  for  want
of fresh design did  not  arise.   Respondent  averred  that  the  appellant
unilaterally stopped the work and there is no question of  defendant  making
further payment.  It was  averred  that  no  extra  work  was  done  by  the
appellant and the respondent  was  not  liable  to  pay  any  amount  either
towards the damages or towards the alleged loss sustained by the  appellant.

5.     On  the  above  pleadings,  trial  court  framed  seven  issues.   To
substantiate the claim,  appellant-plaintiff  examined  four  witnesses  and
produced thirty three documents.  On behalf of  respondent-defendant,  DW-1-
Jagadeesh  Kumar-Deputy  Manager  was  examined  and  five  documents   were
produced. Upon consideration of evidence adduced by the parties,  the  first
three issues were answered in favour of the  appellant-plaintiff  viz.:  (i)
appellant’s claim as to extra work;    (ii) respondent’s direction  to  stop
the running work for want of revised design and (iii)  due  to  stoppage  of
work side embankment began to fall in the  trench  due  to  the  seepage  of
water and involving double work for the appellant-plaintiff  to  remove  the
fallen loose earth.  Taking note of the fact that the  respondent  had  paid
only a sum of Rs.4,36,575/- to the appellant out of the  assessed  value  of
Rs.5,82,100/-, trial court calculated the balance of  Rs.1,45,525/-  as  the
balance amount payable in respect of completed portion of the work.  On  the
value of building material  stock,  trial  court  awarded  Rs.1,00,000/-  as
against the appellant’s claim of Rs.6,00,000/-.   Trial  court  decreed  the
suit in respect of extra earth work, embankment work  and  other  heads  and
directed the defendant  to  pay  in  all  a  sum  of  Rs.3,23,000/-  to  the
appellant with proportionate cost and interest on the  said  amount  at  12%
per annum from the date of the suit till the date of realization.
6.    Being  aggrieved,  respondent  as  well  as  the  appellant  preferred
appeals before the High Court and both the appeals were heard  together  and
disposed of by the impugned judgment.  Referring to the contract,  the  High
Court held that the written contract governs the terms between  the  parties
and any variation thereof ought to be in terms of the provisions  of  clause
11 of the contract and the appellant having not gone through  the  procedure
envisaged under clause 11, the appellant  cannot  putforth  a  claim  for  a
higher payment on the premise that it has executed some extra work over  and
above the stipulated quantity of the  work.  The  High  Court  reversed  the
judgment of the trial court observing that the trial court acted  more  like
an arbitrator in examining the suit claim and that the trial court erred  in
passing the decree in  favour  of  the  appellant-plaintiff  for  a  sum  of
Rs.3,23,000/- with interest and proportionate cost.
7.          Learned counsel for the appellant Mr. Partha Sil  has  contended
that the High Court failed to appreciate  that  the  change  in  work  which
materially changed the nature of  intended  work  mentioned  in  the  tender
document which was admitted by DW-1-Jagadeesh Kumar during  trial.   It  was
further submitted that  the  High  Court  erred  in  ignoring  the  evidence
adduced by  the  appellant  which  clearly  establish  that  the  respondent
directed the appellant to stop the work resulting  in  double  work  due  to
soil caving in trenches causing severe financial loss and  hardship  to  the
appellant. It was submitted that upon  appreciation  of  evidence  when  the
trial court recorded findings of fact, the  High  Court  was  not  right  in
reversing the same.
8.    Per contra, learned  Senior  Counsel  for  the  respondent     Mr.  P.
Vishwanatha Shetty submitted that appellant was appointed  to  complete  the
given work as per the terms of the contract and  it  was  the  duty  of  the
appellant to collect the relevant information before  making  an  offer  and
the appellant was not justified in making an  exaggerated  claim  of  rupees
thirty lakhs which is  thrice  the  estimated  cost  of  the  work.  It  was
submitted that the appellant failed to prove that he had purchased  material
and they were brought to the site and there is  no  acceptable  evidence  to
show that the appellant had stored  large  quantities  of  material  in  the
site.  It was submitted that the plea of the appellant that  he  was  orally
asked to stop the work and to await revised design is totally  baseless  and
the High Court rightly reversed the judgment of the trial court.
9.    We have carefully considered the  rival  contention  and  perused  the
impugned judgment and also  the  judgment  of  the  trial  court  and  other
material on record.
10.   PW-1-Venkatesh, who is the proprietor of the appellant-company  stated
that the alignment of compound wall to be constructed is in  line  with  the
existing flow of water from the river and that excavation for  the  compound
wall was done in the  river  itself  and  when  the  work  commenced,  water
started collecting in the trenches and the  plaintiff  had  to  dewater  the
same simultaneously. PW-1 further stated that the  appellant  requested  the
respondent to consider the  matter  and  accord  sanction  for  extra  items
namely, making temporary drain, dewatering work and that the  appellant  had
to do extra work for removal of loose earth and this caused double work  for
the  appellant.   PW-3-Hanumegowda,  working  as  a  supervisor  under   the
appellant corroborated the version of PW-1 and stated that while  doing  the
foundation work, seepage water  from  river  flooded  in  and  collected  in
trenches and the appellant had to do extra work in  dewatering  and  removal
of loose earth. PW-3 further stated that as per the estimate, depth  of  the
earth excavation for the foundation  work  was  only  four  feet  and  while
digging the trenches it was found that the  soil  was  loose  and  that  the
engineers of the respondent told  the  appellant  to  dig  the  earth  to  a
further depth till hard soil bed is reached and  on  this  score  also,  the
appellant had to do extra work.  The version of PWs 1 and 3 is fortified  by
letter dated 06.05.1992 (Ex. P4) sent by the  appellant  to  the  respondent
stating that there was seepage of water in the trench  and  that  embankment
had fallen in the trench and that the appellant has  to  do  extra  work  in
dewatering and removing the loose soil.  Inspite of repeated  letters  (Exs.
P4 and P5), there was no response from the respondent.
11.   DW-1-Jagadeesh Kumar working as Deputy  Manager  with  the  respondent
had stated that the parties were not aware of the soil strength at the  time
of  entrustment  of  the  work  to  the  appellant.  However  during  cross-
examination, DW-1 admitted that before commencement of  work,  both  parties
were unaware of nature of different strata of soil.  He also stated that  in
case soil testing  had  been  done  before,  the  records  would  have  been
available with the respondent.  But no  such  record  was  produced  by  the
respondent. Be it noted that the defendant has not adduced any  evidence  to
discredit the testimony of PWs 1 and 3 that extra work was  required  to  be
done on account of seepage of water and soil  caving  in  and  widening  and
deepening the trench.  On appreciation of evidence of PWs 1 and 3 and  other
documentary evidence, the trial court recorded the  findings  of  fact  that
the appellant had to do extra work incurring additional expenditure.
12.         In so far as the direction of the respondent to stop  the  work,
PW-1 stated that during the first week  of  April,  1992  officials  of  the
respondent had asked the appellant to stop the work for getting  the  design
from the architect on account of seepage  of  water.   PW-2-Raghavendra  Rao
working as Civil Engineer in the appellant company,  has  also  corroborated
the version of PW-1 and stated that the respondent asked  the  appellant  to
stop the work and that the work could be resumed later.  Though DW-1  stated
that the defendant did not issue any letter  to  the  plaintiff  complaining
against the stopping of work, he also stated that the plaintiff  was  orally
told about the same.  By  perusal  of  various  letters,  it  is  seen  that
inspite of  number  of  letters  by  the  appellant  seeking  permission  to
continue the work, there was no response from  the  respondent.  Absence  of
any response on  the  part  of  the  respondent,  only  indicates  that  the
respondent was aware of the change of nature of work.
13.   PW4-Naresh Kumar-architect had stated about  his  visit  to  the  work
site at the request of the respondent for preparing  the  design  after  the
masonry wall for the length of hundred metres was over and that he gave  the
revised design and PW-4 estimated the cost of the work as  per  the  revised
design at rupees twenty lakhs.  PW-4  was  engaged  to  prepare  the  design
suitable to the soil strength only because of the change in  the  nature  of
the work.  Otherwise the need for engaging PW-4  for  preparing  new  design
would not have arisen if the earlier design would  have  been  suitable.  On
appreciation of evidence, trial court rightly answered issue No.2 in  favour
of the appellant that  the  respondent  asked  the  appellant  to  stop  the
running work for want of revised design.
14.   The  High  Court  took  note  of  clause  11  of  the  contract  dated
12.02.1992 which states that the contractor is  not  authorized  to  do  any
extra work or make any alteration without the previous  consent  in  writing
of the respondent.  High Court set aside the findings recorded by the  trial
court holding that the parties are governed by  the  terms  of  the  written
contract and any variation with the terms of the agreement was  required  to
be done strictly adhering to clause 11 of the contract.   While  saying  so,
the High Court brushed aside the admission by DW-1 that extra work was  done
by the appellant and the High Court was not right in ignoring  the  same  to
hold that the admission of DW-1 cannot have the effect  on  the  contractual
obligation of the parties.  It is to be pointed out that the respondent  has
not raised the plea relying upon clause 11 of  the  contract.   Further,  by
perusal of Ex.P2 dated 20.12.1991, a letter addressed by  the  appellant  to
the respondent informing the respondent about the extra work which needs  to
be done and the fact that PW-4 was engaged by the respondent to prepare  the
new design for the work, it is evident that the respondent was aware of  the
fact of the change in the nature of work and that  there  is  alteration  in
the work done by the appellant.  When  the  evidence  and  material  clearly
depict the change of nature of work involved and when the extra work  to  be
done was also admitted by DW-1, parties cannot  be  expected  to  go  for  a
revised agreement/contract.  Moreover, having regard to the  fact  that  the
work was to be completed within a specified time-frame, the  parties  cannot
be expected to go for a second round of negotiation and  reframe  the  terms
and conditions of the work.  While so, the  High  Court  was  not  right  in
placing reliance upon clause 11 of the contract to reverse the  findings  of
fact recorded by the trial court.
15.   So far as the claim of the appellant that  it  suffered  loss  due  to
loss of stock of material, PWs 1 and 3 have stated that  they  have  stocked
the material of worth  about  rupees  six  lakhs  at  the  work  site.   The
appellant also produced several letters (Exs. P5, P6 and P7)  by  which  the
appellant has informed the respondent that there  was  no  progress  in  the
work and that the building material  are  lying  waste.   Apart  from  these
letters, the appellant has also produced photographs (Exs. P18  to  P28)  to
substantiate their claim  that  the  building  material  like  bricks,  size
stones and other materials were stocked at the work site.  Even  though  the
appellant has claimed rupees six lakhs on account of loss  of  the  material
stocked, as the appellant had not produced any bill relating to purchase  of
material nor  produced   authentic  trip  sheet,  the  trial  court  rightly
awarded rupees one lakh only on account of loss  of  building  material.  As
noticed earlier, based on the evidence of PWs 1 and 3 and  other  documents,
the trial court has awarded amount on various other heads viz.,  the  amount
payable in respect of:- (i) extra earth work; (ii)  embankment  work;  (iii)
extra soiling work; (iv)  extra  bed  concrete  work  and  (v)  extra  stone
masonry work.  The amount so awarded by the trial court under various  heads
is based on evidence and material on record.
16.   The Appellate Court may not interfere with the finding  of  the  trial
court unless the finding recorded by the trial court  is  erroneous  or  the
trial court ignored the evidence on record.  The  High  Court  reversed  the
decree passed by the trial court without  discussing  oral  and  documentary
evidence and several grounds raised before the trial court.  The High  Court
veered away from the main issue and went on  to  elaborate  on  the  law  of
arbitration and the mode of setting aside the arbitral award  under  Section
34 of the Arbitration Act, which in our view, was  not  warranted.   Without
considering the oral and documentary  evidence,  the  High  Court  erred  in
interfering with the factual findings recorded by the trial  court  and  the
impugned judgment is liable to be set aside.
17.   Trial court directed the respondent to pay a sum of Rs.3,23,000/-   to
the appellant with interest at the rate of 12% per annum from  the  date  of
suit till the date of realization. To award interest from the date  of  suit
to date of decree and from the date of decree till the date  of  realization
is entirely discretionary.  The terms of the contract  do  not  specify  any
rate of interest.  In the facts and circumstances of  the  case  and  having
regard to the fact that the matter is pending for over two  decades  and  in
the interest of justice, it is appropriate that  the  interest  of  12%  per
annum awarded by the trial court is reduced to 6% per annum.
18.   In the result, the impugned judgment is set aside and the appeals  are
allowed.  The judgment and decree passed by  the  trial  court  is  restored
with the modification of reduction of interest at  6%  per  annum  from  the
date  of  the  suit  till  the  date  of  realization.  In  the  facts   and
circumstances of the present case, no order as to costs in these appeals.


                                                              …………………….…CJI.
                                                               (T.S. THAKUR)


                                                               ………………………….J.
                                                                (A.K. SIKRI)



                                                             ..………………………..J.

                                                              (R. BANUMATHI)
New Delhi;
January 20, 2016