Supreme Court of India (Full Bench (FB)- Three Judge)

Appeal (Civil), 1247 of 2012, Judgment Date: Jul 12, 2016


                                                                  Reportable

                        IN THE SUPREME COURT OF INDIA
                        CIVIL APPELLATE JURISDICTION

                        CIVIL APPEAL NO.1247 OF 2012

Talaulicar & Sons P. Ltd.                                      …Appellant
                                   VERSUS

Union of India & Anr.                                        …Respondents

                                    WITH

                       CIVIL APPEAL NO. 6174  OF 2016
          [arising out of SLP(C). 17731/2016 @ CC No.20925 of 2012]

                                    WITH

                           T.P.(C) NO.1843 OF 2013

                         J   U  D  G   M   E   N   T

Fakkir Mohamed Ibrahim Kalifulla, J.

Delay condoned.

Leave granted in SLP(C)……../2016 @ CC No.20925 of 2012.
These  appeals  are  directed  against  a  Division  Bench  judgment   dated
12.08.2011 of the High Court of Bombay at Goa in Public Interest  Litigation
Writ Petition No.6 of  2011.  The  said  writ  petition  was  moved  at  the
instance of the second respondent herein with a prayer  that  the  appellant
was originally granted environmental clearance for the expansion  of  Saniem
Sacorda Iron Ore Mine on 25.11.2005 for two  years,  that  by  a  subsequent
letter dated 18.10.2007 of the first respondent, the  two  years  period  to
conduct a higher geological  study  was  deleted,  that  by  virtue  of  the
conditions stipulated in the Notification dated 27.01.1994 read  along  with
the Notification dated 04.05.1994 such environmental  clearance  granted  in
favour of the appellant expired on 25.11.2010 and  that  in  spite  of  such
expiry, the appellant  continued  to  indulge  in  mining  operations.   The
second respondent therefore contended that such illegal mining  activity  of
the appellant was not controlled by the  first  respondent  even  after  the
second respondent’s communication dated 30.11.2010.  It  was  on  the  above
said basis, the second respondent prayed for the issuance  of  the  mandamus
directing the first respondent to stop the operation of Saniem Sacorda  Iron
Ore Mine of the appellant and also direct for payment  of  compensation  for
having caused environmental damage.


The Division Bench of the High Court having made a detailed analysis of  the
grievance of the  second  respondent  as  a  local  resident,  the  relevant
provisions of the Statute as  well  as  the  Environment  Impact  Assessment
(EIA) Notification dated  27.01.1994,  took  the  view  that  the  clearance
granted in favour of the appellant in the order  dated  25.11.2005  for  the
expansion of Saniem Sacorda Iron Ore Mine was initially for a period of  two
years as per the EIA Notification of 1994 and that  such  clearance  can  be
valid only for  a  period  of  five  years  as  is  stipulated  in  the  EIA
Notifications and the relevant Rules. The  Division  Bench  ultimately  held
that the appellant was carrying on the mining  operations  without  a  valid
subsisting  environmental  clearance  and  while  granting  liberty  to  the
appellant to seek an extension/renewal of the environmental clearance for  a
further period, in accordance with law, within  a  period  of  three  months
also directed that in the event  of  non-grant  of  any  such  environmental
clearance,  the  appellant  should  discontinue  mining  operations  of  the
concerned mine, till such time environmental  clearance  is  granted.  While
holding so, the Division Bench made  it  clear  that  the  validity  of  the
environmental clearance granted in favour of the appellant was  only  for  a
period of five years from the date of commencement of the operation  of  the
mining projects / expansion of the project carried  out  by  the  appellant.
Aggrieved by the said judgment of  the  Division  Bench,  the  appellant  is
before us.


It will be worthwhile to note certain observations  of  the  Division  Bench
before  passing  final  orders  in  these  appeals.  While  considering  the
question whether the validity of  the  environmental  clearance  granted  in
favour of the appellant would be limited for  a  period  of  five  years  or
more, the Division Bench made a reference  to  Para  2(III)(c)  of  the  EIA
Notification of 1994 wherein it was stipulated that clearance granted  would
be  valid  for  a  period  of  five  years  from  the  commencement  of  the
construction or operation of the projects, that  such  prescription  of  the
period has got a nexus to the environment protection.  In that context,  the
Division  Bench  further  observed  that  the  purpose  and  object  of  the
Environment Protection Act and the Rules framed there under  must  be  given
its full effect, that if there is no check on the environment hazard at  the
time of carrying out the mining activities, it could lead to degradation  of
the environment, that carrying out impact assessment within specific  period
would assist in ascertaining the adverse  effect  of  the  project  activity
which is sought to be pursued by the project proponent,  that  any  activity
carried out in  respect  of  specific  projects  such  as  mining,  requires
environmental clearance in order to  see  that  such  activities  would  not
result in further degradation of the environment affecting the life  of  the
residents in the locality and therefore the prescription of  limited  period
had a nexus to the grant of  environmental  clearance.  The  Division  Bench
also rejected the  claim  of  the  appellant  that  once  the  environmental
clearance was granted, the same would be valid for  thirty  years  based  on
the subsequent Notification of 2006  in  supersession  of  the  Notification
dated 27.01.1994.


Having thus noted the above observations of the  Division  Bench,  we  heard
Mr. Shyam Divan, learned  senior  counsel  for  the  appellant,  Mr.  A.N.S.
Nadkarni, learned Advocate General for Goa,  Mr.  Colin  Gonsalves,  learned
senior counsel for the  second  respondent  and  Ms.  Pinky  Anand,  learned
Additional Solicitor General for the first respondent.



We  find  that  the  appellant  applied  for  environmental  clearance   for
expansion of Saniem Sacorda Iron Ore Mine falling  within  Tehsil  Sariguem,
District South Goa in the Union Territory of Goa, in its  application  dated
15.03.2005, followed by subsequent letters dated 28.04.2005 and  16.08.2005.
 The first respondent passed orders on 25.11.2005.  In paragraph 2.0 it  was
stipulated that the Ministry of  Environment  and  Forest  (MoEF  in  short)
accord environmental clearance for a period of  two  years  only  to  Saniem
Sacorda Iron Ore Mine of the appellant  involving  a  lease  area  of  50.30
hectares for production of iron ore  under  the  provisions  of  Environment
Impact Assessment Notification, 1994, subject to specific  conditions  under
caption ‘A’.  In sub-para (ii) of Para ‘A’, it  was  specifically  noted  as
under:

“A(ii).  The  proponent  shall   within   2   years   conduct   a   detailed
hydrogeological  study  (quality  and  quantity)  on  impact  of  mining  on
hydrogeology (pre-monsoon, monsoon and post-monsoon) and furnish a  detailed
report on the same to the Ministry. Based on the same, a decision  regarding
continuation of mining beyond 2 years or otherwise will be taken.”


After the said order dated  25.11.2005,  the  first  respondent  passed  its
subsequent order dated 18.10.2007, wherein, it was stated that in  pursuance
of its order dated  25.11.2005,  the  appellant  had  filed  the  report  of
hydrogeological study on impact of mining on hydrogeology of the mine  lease
area, that on examination of the said report, it was found  that  radius  of
influence due to mine pit  dewatering  would  extend  to  about  235  meters
around the mine pit, that the stage of ground  water  development  is  about
4.53% which according to the first  respondent  was  well  within  the  safe
limits as per Central Groundwater Board Norms.  It was also noted  that  the
results of chemical quality data of both surface water  and  groundwater  as
well as mine pit water indicated no contamination due to mining  operations.
 In paragraph 3 of the said order, the first respondent  ultimately  deleted
the  prescription  of  two  years  period  stipulated  in  the  order  dated
25.11.2005.

It was in the above stated background, that the second respondent moved  the
High Court as a local resident  alleging  that  having  regard  to  the  EIA
Notification dated 27.01.1994 as amended by  subsequent  Notification  dated
04.05.1994, the environmental clearance granted in favour of  the  appellant
was valid only for a period of five years from the date of commencement  and
consequently the five years period having  expired  on  25.11.2010,  further
mining operations of the appellant in the above referred to mine by  way  of
expansion was in violation of the provisions of the  Environment  Protection
Act, the EIA Notifications and the relevant Rules.


In so far as the right of a local resident is  concerned,  when  we  make  a
reference  to  the  initial  Notification  dated  27.01.1994,  in  paragraph
2(III)(c) it is specifically provided as under:

“2.(III)(c).  The  Impact  Assessment  Agency  shall  prepare   a   set   of
recommendations  based  on  technical  assessment  of  documents  and  data,
furnished by the project authorities, supplemented by data collected  during
visits to sites or factories, if undertaken, and interaction  with  affected
population and environmental groups, if necessary. Summary of  the  reports,
the recommendation  and  the  conditions,  subject  to  which  environmental
clearance is given, shall be made available subject to the  public  interest
to the concerned parties or environmental groups on  request.   Comments  of
the public may be solicited, if so  decided  by  Impact  Assessment  Agency,
within thirty days of receipt of proposal, in public hearings  arranged  for
the purpose after giving thirty days notice of such  hearings  in  at  least
two newspapers. Public shall be  provided  access,  subject  to  the  public
interest, to the summary of the reports/Environmental  Management  Plans  at
the Headquarters of the Impact Assessment Agency.


The assessment shall be completed  within  a  period  of  ninety  days  from
receipt of the requisite documents and data  from  the  project  authorities
and completion of public hearing,  where  required,  and  decision  conveyed
within thirty days thereafter.


The clearance granted shall  be  valid  for  a  period  of  five  years  for
commencement of the construction or operation.


No construction work, preliminary or otherwise, relating to the  setting  up
of the  project  may  be  undertaken  till  the  environmental  and/or  site
clearance is obtained.”

                                                            (Emphasis added)


Again  when  we  make  reference  to  the  subsequent   Notification   dated
14.09.2006, there is a specific provision  therein  also  in  paragraph  III
Stage III clause (i) & (ii) which contains as many sub-paragraph (a) to  (f)
in clause (i), (a) and (b) in Clause (ii) apart from Clause (iii) to  (vii).
 The specifications contained in the Notification dated  14.09.2006,  states
that the same came to be issued in supersession of  the  Notification  dated
27.01.1994.  It also stipulates the Constitution of State Level  Environment
Impact Assessment Authority,  categorization  of  projects  and  activities,
screening, scoping and appraisal  committees,  different  Stages  for  prior
environmental  clearance  (EC-process  for  new   projects),   process   for
expansion or modernization or change of product  mix  in  existing  projects
and at the end in paragraph 8, grant or  rejection  of  prior  environmental
clearance and in paragraph 9 validity  of  environmental  clearance  and  in
paragraph 10  post  environmental  clearance  monitoring,  in  paragraph  11
transferability of environmental clearance is also provided.


Keeping the above relevant factors in mind,  we  heard  the  learned  senior
counsel for the appellant, learned  Additional  Solicitor  General  and  the
learned  Advocate  General,  the  learned  senior  counsel  for  the  second
respondent.  In order to examine the scope, ambit  and  correctness  of  the
orders dated 25.11.2005 and 18.10.2007,  the  learned  Additional  Solicitor
General was directed to call upon MoEF to produce the records of  the  case.
Thereafter, it was felt that after grant of the environmental clearance  for
a period of two years in the order dated 25.11.2005, subject  to  submission
of hydro geological study of the  area,  when  the  subsequent  order  dated
18.10.2007  was  passed,  we  found  that  very  many  requirements  of  the
Environment Protection Act, the relevant Rules framed there  under  and  the
various factors to be taken into account and a detailed  public  hearing  to
be  effected  as  stipulated  in  the  last  of  the   Notifications   dated
14.09.2006, were not specifically addressed by the  first  respondent  while
passing the order  dated  18.10.2007.   In  other  words,  the  order  dated
18.10.2007 was a cryptic one  without  giving  due  regard  to  the  various
salient features concerning the environment protection and the  interest  of
the public  at  large,  while  granting  such  clearance  and  allowing  the
clearance granted earlier to be valid  beyond  the  initial  period  of  two
years and also without specifying as to the other terms  and  conditions  to
be complied with.


In such circumstances, while on the one hand, appreciating the  observations
made by the Division Bench in the impugned order which we  have  highlighted
in the earlier part of this order, we feel that the first respondent  should
be directed to take a fresh look for the continuation or  otherwise  of  the
environmental clearance granted by it in the order dated  25.11.2005,  after
scrupulously following the various relevant factors, such as  notifying  the
State level Authority and  other  Authorities  concerned,  effective  public
hearing after due paper  publication  even  while  referring  to  the  hydro
geological report submitted by the appellant and  then  pass  final  orders.
In that perspective we are convinced that  the  order  dated  18.10.2007  is
liable to be set aside with necessary direction to the first  respondent  to
look into the application of the appellant afresh after  the  submission  of
the hydro geological report and after giving an opportunity  of  hearing  to
the appellant as well as the second respondent or such other bodies to  whom
such hearing is to be offered  as  per  the  subsequent  Notification  dated
14.09.2006, permit them to file the required material documents  in  support
of their respective stand and pass a reasoned order in accordance  with  the
procedure prescribed under the said Notification.


With that view, we set aside the order dated  18.10.2007,  and  consequently
the impugned order cannot  also  stand.   We  therefore,  direct  the  first
respondent MoEF to  proceed  afresh,  issue  a  notice  of  hearing  to  the
appellant, the second respondent, as well as, hold the consultative  process
with the State Level Authorities and call for the required reports from  the
concerned experts of its choice and  after  due  hearing,  pass  appropriate
orders, in accordance with law. Such exercise shall be carried  out  by  the
first respondent MoEF expeditiously, preferably, within a  period  of  three
months from the date of production of a copy of this order.  It is  needless
to state that any order that may be passed pursuant to  this  judgment  will
always be subject to the decisions  in  Goa  Foundation  cases  reported  in
(2014) 6 SCC 590 and (2014) 6 SCC 738 respectively. We make  it  clear  that
we have not gone into the  merits  of  the  respective  contentions  of  the
appellant or the respondents. The appeals stand disposed of with  the  above
directions. No costs.


Transfer Petition(C)  No.1843/2013  has  been  filed  by  Respondent-Shankar
Raghunath Jog in the above appeals. He has  approached  the  National  Green
Tribunal in O.A. No.22/2012 as against  the  MoEF  State  Pollution  Control
Board and the Department of Mines and Geology with the following prayer:

“1. Order or direction ordering the Respondent to close down  the  mines  in
the State of Goa which do not  have  valid  EC  following  the  Judgment  in
Shankar Jog versus M/s Talaulicar and Sons Private Limited,  with  immediate
effect.

2. Order or direction ordering the  Respondent  to  pay  compensation  under
section 15 of the National Green Tribunal  Act  2010  to  the  Environmental
Relief Fund for its failure to take  timely  action  closing  the  violating
mines in the State of Goa which has lead to environmental degradation.

3. Costs.”


In the body of the application, the  Respondent-Shankar  Raghunath  Jog  has
made reference  to  the  environmental  clearance  relating  to  the  mining
project of the appellant dated 25.11.2005 and  the  subsequent  order  dated
18.10.2007 by which the conditional grant of EC for two  years  came  to  be
deleted. He also made reference to the expiry  of  the  EC  itself  and  the
grant which occurred on 25.11.2010 while praying for the above directions.

It is relevant to note that the appellant was not impleaded as  a  party  in
the said O.A. No.22/2012. In the grounds of the said application  there  was
a general allegation against the official respondents  including  MoEF  that
inspite of the judgment impugned in the civil appeal (viz)  Public  Interest
Litigation  Writ  Petition   No.6/2011   dated   12.08.2011   the   official
respondents failed to take any  steps  for  closing  down  the  mines  which
violated the statutory provisions. In the light of the present judgment  and
the directions which we have issued, we  are  of  the  view  that  the  O.A.
No.22/2012 pending on the file  of  the  Green  Tribunal  will  not  survive
inasmuch as Respondent-Shankar Raghunath Jog mainly placed his prayer  based
on the impugned judgment when he filed the O.A. before the  Green  Tribunal.
Since we have set aside the impugned judgment in these  Appeals,  the  whole
basis of Respondent-Shankar Raghunath Jog’s  grievance  in  the  O.A.  filed
before  the  Tribunal  does  not  survive.  Therefore,  while  allowing  the
Transfer Petition and direct the O.A. No.22/2012 to be transferred  to  this
Court, the O.A. shall stand dismissed as having become infructuous.

                                                   .….………………………………………..C.J.I
                                                             [T.S. Thakur]

                                                   …..….………………………………………...J.
                                        [Fakkir Mohamed Ibrahim Kalifulla]


                                                   …..….………………………………………...J.
                                                       [Uday Umesh Lalit]

New Delhi;
July 12, 2016