Supreme Court of India

CIVIL APPEAL NO. 10784 OF 2014 @ SPECIAL LEAVE PETITION (CIVIL) NO.24652 OF 2013 Judgment Date: Dec 04, 2014

                                                                  Reportable

                        IN THE SUPREME COURT OF INDIA

                        CIVIL APPELLATE JURISDICTION

                      CIVIL APPEAL NO. 10784  OF 2014 @
               SPECIAL LEAVE PETITION (CIVIL) NO.24652 OF 2013


NEW INDIA ASSURANCE COMPANY LTD              .... Appellant

                                   Versus

GENUS POWER INFRASTRUCTURE LTD.             .... Respondent

                               J U D G M E N T

Uday U. Lalit, J.

1.    Leave granted. This  appeal  challenges  the  order  dated  30.05.2013
passed by the High Court of Delhi in Arbitration  Petition  No.212  of  2011
appointing an arbitrator to adjudicate  the  disputes  between  the  present
parties.

The respondent has a  manufacturing  unit  for  which  it  had  purchased  a
Standard Fire and Special  Perils  Policy  ('policy'  for  short)  from  the
appellant on 17.04.2009, which policy was for a period of one year  and  the
total sum assured was Rs.91 crores and 10 lacs only.   On  29.10.2009  there
was a fire explosion  in  the  adjoining  Indian  Oil  Corporation  Terminal
causing extensive damage to the manufacturing unit  of  the  respondent.  On
being notified, the appellant appointed a  category  "A"  Licensed  Surveyor
and Loss Assessor in compliance of Section 64 UM of the Insurance Act,  1938
to assess the damage. In the assessment of the respondent  and  as  per  the
claim lodged by it, the loss caused to its plant  and  machinery,  buildings
fixtures and furnitures and stocks was to the tune of Rs.28.79  crores.   It
appears that the Surveyor submitted  his  final  report  on  27.07.2010  and
assessed the loss at Rs.6,09,77,406/-.   It is contended  by  the  appellant
but denied  by  the  respondent  that  the  final  survey  report  was  duly
communicated to the respondent on 01.11.2010.

 On 11.03.2011 the respondent signed a detailed letter of subrogation  which
was  on  a  stamp  paper,  accepting  Rs.5,96,08,179/-  in  full  and  final
settlement of its claim under the policy and the relevant  portion  of  said
letter dated 11.03.2011 was to the following effect:
To,
New India Assurance Co. Ltd.
Regional Office
Nehru Place, Tonk Road,
Jaipur

Dear Sir,

      That in consideration of claim amount of Rs.5,96,08,179  (Rupees  Five
Crores Nintey Six Lakhs  Eight  Thousand  One  Hundred  Seventy  Nine  only)
(herein after referred as "Claim  amount")  as  full  and  final  settlement
amount  of  our  claim  No.330203/11/10/01/00100001  arising  under   policy
No.330203/11/09/11/00000018 (herein after  referred  as  "Policy")  covering
fire loss  of  my/our  factory  situated  on  Plot  No.SPL  3,  Sitapura,  -
Industrial area Jaipur (herein after referred as "Factory Premises") due  to
fire that took place in IOC Terminal on 29-10-2009, we hereby subrogate  our
rights on behalf of M/S Genus Power Infrastructures Limited  Jaipur  (herein
after referred as "Insured") in favour  of  New  India  Assurance  Co.  Ltd.
(herein after referred as "Insurer") as under:-

That we the Insured hereby subrogate all the rights  and  remedies  (to  the
extent provided by aforesaid contract of Insurance  and  under  the  General
law and further any other Law enforceable consequence  to  the  above  loss)
against the  RIICO,  Indian  Oil  Corporation,  Govt.  of  Rajasthan,  other
insurance company or any other agency/authority of Govt. of Rajasthan,  semi
Govt. etc. whom so ever is liable  in  respect  whereof  in  favour  of  the
Insurer regarding Fire accident taken place on 29-10-2009  in  IOC  terminal
in  Sitapura  Industrial  Area,  Jaipur  and  claim  arises  under  "Policy"
covering fire loss of Insured factory in "Factory  Premises"  in  favour  of
the "Insurer".
That we the Insured further assign and transfer all  rights  to  Insurer  to
recover the claim  amount  or  any  part  thereof  from  RIICO,  Indian  Oil
Corporation, Govt. of  Rajasthan,  other  insurance  company  or  any  other
agency/authority of Govt. of Rajasthan, semi  Govt.  etc.  who  so  ever  is
liable.
That we the Insured further assign and transfer all rights  to  agitate  the
Claim before the RIICO, Indian Oil Corporation, Govt.  of  Rajasthan,  other
insurance company or any other agency/authority of Govt. of Rajasthan,  semi
Govt. etc. who so  ever  is  liable  to  pay  the  compensation/claim.   The
Insurer will be entitled to file complaint/claim before any  court  of  law,
tribunal or any other adjudicatory authority and plead the  same  on  behalf
of ourselves  and  in  getting  success  in  adjudication  therein  will  be
entitled to retain the amount paid.......
.......................................................................
........................................................................

In witness whereof we get our hands on this Subrogation letter on  the  11th
day of March 2011.
                                  For Genus Power Infrastructure ltd.
                                  Authorized Signatory
                                  Signature

4.    After nearly three weeks i.e on 31.03.2011  the  respondent  issued  a
notice to the appellant stating that the discharge voucher was signed  under
extreme duress, coercion and undue influence exercised by the appellant  who
took  undue  advantage  of  the  extreme  financial  difficulties   of   the
respondent.   The  respondent  further  sought  to   appoint   its   nominee
arbitrator.  On  21.04.2011  the  appellant  replied  that  there   was   no
arbitrable dispute  which  existed  between  the  parties  inasmuch  as  the
respondent had voluntary signed the letter of subrogation and  had  accepted
payment in full and final settlement of  its  claim.  In   the  meantime  on
05.04.2011 the respondent had filed a  petition  under  section  11  of  the
Arbitration and Conciliation Act, 1996 (The  'Act'  for  short)  before  the
High Court of Delhi alleging that it had  accepted  the  payment  as  stated
above because of extreme financial  difficulty,  duress  and  coercion.   On
10.05.2013 the High Court after recording rival submissions of  the  parties
adjourned the matter which was then taken up on 30.05.2013  when  the   High
Court observed;
"Vide order dated 10th May, 2013,  this  Court  has  already  observed  that
there is a valid arbitration agreement between the  parties  and  there  are
disputes which are covered under the  arbitration  agreement.   The  learned
counsel for the respondent submits that the  disputes  are  not  arbitrable.
The respondent can raise this objection before the learned arbitrator."

      In that view of the matter the High Court proceeded to appoint a  sole
arbitrator to adjudicate the disputes between the parties.

5.    The  aforesaid  order  dated  30.05.2013  is  the  subject  matter  of
challenge in the present appeal.  Appearing for  the  appellant  Mr.  Gaurab
Banerji, learned Senior Advocate submitted that the  letter  of  subrogation
was a detailed agreement which was finalized and signed  after  negotiations
between the parties and in  the  presence  of  two  witnesses.   The  amount
agreed to was the  amount  recommended  by  the  surveyor,  reduced  by  the
mandatory reinstatement premium payable under clause 15 of  the  policy  and
as such  the  settlement  took  place  at  the  amount  recommended  by  the
surveyor.  Placing reliance on the financial status of  the  respondent,  it
was submitted that its annual turnover is more than Rs.500 crores  for  last
few years and it was  quite  improbable  that  such  a  company  would  feel
financially constrained and stand coerced as alleged,  in  giving  discharge
on receipt of  Rs.5.98  crores.   Mr.  Krishnan  Venugopal,  learned  Senior
Advocate appearing for  the  respondent  submitted  that  knowing  that  the
respondent was under tremendous pressure owing to the  complete  destruction
of its manufacturing unit and not being in  a  position  to  negotiate,  the
appellant by using its dominant position had forced the respondent  to  sign
the discharge voucher and accept the payment as stated above.   In  support,
reliance was placed on the decision of this court in National Insurance  Co.
Ltd. vs. Boghara Polyfab (P) Ltd.[1] by Mr. Venugopal.

6.    The question that arises is whether the discharge in the present  case
upon acceptance of compensation and signing of subrogation  letter  was  not
voluntary and whether the claimant was subjected to compulsion  or  coercion
and as such could validly invoke the jurisdiction under Section  11  of  the
Act.  The law on the point  is  clear  from  following   decisions  of  this
court.  In National Insurance Co. Ltd. vs.  Boghara  Polyfab  Pvt.  Ltd.  in
paras 26 and 51 it was stated as under:-
"26.  When we refer to a discharge of contract by  an  agreement  signed  by
both  the  parties  or  by  execution  of  a  full   and   final   discharge
voucher/receipt by  one  of  the  parties,  we  refer  to  an  agreement  or
discharge voucher which is validly and voluntarily executed.  If  the  party
which has executed the discharge agreement  or  discharge  voucher,  alleges
that the execution of such discharge agreement or voucher was on account  of
fraud/coercion/undue influence practiced by the other party and is  able  to
establish the same, then obviously the discharge of  the  contract  by  such
agreement/voucher is rendered void and cannot be acted upon.   Consequently,
any dispute raised by such party would be arbitrable.

51.  The Chief Justice/his designate exercising jurisdiction  under  Section
11  of  the  Act  will  consider  whether  there  was  really   accord   and
satisfaction or discharge of contract by performance. If the  answer  is  in
the affirmative, he will refuse to refer the dispute to arbitration. On  the
other hand, if the Chief Justice/his designate comes to the conclusion  that
the full and final settlement receipt or discharge voucher  was  the  result
of any fraud/coercion/undue influence, he will have to hold that  there  was
no discharge  of  the  contract  and  consequently,  refer  the  dispute  to
arbitration.  Alternatively,  where  the  Chief  Justice/his  designate   is
satisfied prima facie that the discharge voucher was not issued  voluntarily
and the claimant was under some compulsion or coercion, and that the  matter
deserved detailed consideration,  he  may  instead  of  deciding  the  issue
himself,  refer  the  matter  to  the  Arbitral  Tribunal  with  a  specific
direction that the said question should be decided in the  first  instance."

7.    In the decision rendered in Union of  India  vs.  Master  Construction
Co.[2] this court observed as under:
"18. In our opinion, there is no rule of the absolute kind. In a case  where
the claimant contends that a discharge voucher or no-claim  certificate  has
been obtained by fraud, coercion, duress or undue influence  and  the  other
side contests the correctness thereof, the Chief Justice/his designate  must
look into this aspect to find out at least, prima facie, whether or not  the
[pic]dispute is bona fide and genuine.  Where  the  dispute  raised  by  the
claimant with regard to  validity  of  the  discharge  voucher  or  no-claim
certificate or settlement agreement, prima facie, appears to be  lacking  in
credibility, there  may  not  be  a  necessity  to  refer  the  dispute  for
arbitration at all.

19. It cannot be overlooked that the cost of arbitration is quite  huge-most
of the time, it runs into six and seven figures. It may  not  be  proper  to
burden a party, who contends that the dispute is not arbitrable  on  account
of discharge of contract, with huge cost of arbitration merely because  plea
of fraud, coercion,  duress  or  undue  influence  has  been  taken  by  the
claimant. A bald plea of fraud, coercion, duress or undue influence  is  not
enough and the party who sets up such a plea must prima facie establish  the
same by placing material before the  Chief  Justice/his  designate.  If  the
Chief Justice/his designate finds some merit in  the  allegation  of  fraud,
coercion, duress or undue influence, he may decide the same or leave  it  to
be decided by the Arbitral Tribunal. On the other  hand,  if  such  plea  is
found to be an afterthought, make-believe or  lacking  in  credibility,  the
matter must be set at rest then and there.

22. The above certificates leave no manner of doubt  that  upon  receipt  of
the payment, there has been full and final settlement  of  the  contractor's
claim under the contract. That the payment of final bill  was  made  to  the
contractor on 19-6-2000 is not in dispute. After receipt of the  payment  on
19-6-2000, no grievance was raised or lodged by the contractor  immediately.
The authority concerned, thereafter, released the bank guarantee in the  sum
of Rs 21,00,000 on 12-7-2000. It was then  that  on  that  day  itself,  the
contractor lodged further claims."[pic]

8.    It is therefore clear that a bald plea of fraud, coercion,  duress  or
undue influence is not enough and the party who sets up a plea,  must  prime
facie establish the same by placing material before  the  Chief  Justice/his
designate.  Viewed thus, the relevant averments in  the  petition  filed  by
the respondent need to be considered, which were to the following effect:-
"(g)  That the said surveyor, in connivance with the Respondent Company,  in
order  to  make  the  Respondent  Company  escape  its  full  liability   of
compensating the Petitioner of such huge loss, acted  in  a  biased  manner,
adopted coercion undue influence and duress methods of  assessing  the  loss
and forced the Petitioner to sign  certain  documents  including  the  Claim
Form.  The Respondent Company also denied the just claim of  the  Petitioner
by their acts of omission and commission  and  by  exercising  coercion  and
undue influence and made the  Petitioner  Company  sign  certain  documents,
including a pre-prepared discharge voucher for the said amount  in  advance,
which the Petitioner Company were forced to do so in the period  of  extreme
financial difficulty which prevailed during  the  said  period.   As  stated
aforesaid, the Petitioner Company  was  forced  to  sign  several  documents
including a letter accepting the  loss  amounting  to  Rs.6,09,55,406/-  and
settle the claim of Rs.5,96,08,179/- as against the actual  loss  amount  of
Rs.28,79,08,116/- against the interest of the petitioner company.  The  said
letter and the aforesaid pre-prepared  discharge  voucher  stated  that  the
petitioner had accepted the claim amount in full and  final  settlement  and
thus, forced the petitioner company to unilateral acceptance the same.   The
petitioner company was forced to sign the said  document  under  duress  and
coercion  by  the  Respondent  Company.   The  Respondent  Company   further
threatened the petitioner Company to accept the  said  amount  in  full  and
final or the Respondent Company will not pay  any  amount  toward  the  fire
policy.  It was under such  compelling  circumstances  that  the  petitioner
company was forced  and  under  duress  was  made  to  sign  the  acceptance
letter."

9.    In our considered view, the plea raised by the  respondent  is  bereft
of  any  details  and  particulars,  and  cannot  be  anything  but  a  bald
assertion.  Given the fact that there was no protest or demur raised  around
the time or soon after the  letter  of  subrogation  was  signed,  that  the
notice dated 31.03.2011 itself was nearly after three  weeks  and  that  the
financial condition of the respondent was not  so  precarious  that  it  was
left with no alternative but to accept the terms as  suggested,  we  are  of
the firm view that the discharge in the present case and signing  of  letter
of subrogation were not because of exercise of  any  undue  influence.  Such
discharge and signing of letter of subrogation was voluntary and  free  from
any coercion or undue influence.  In the circumstances, we  hold  that  upon
execution of the letter of subrogation, there was full and final  settlement
of the claim.  Since our answer to the question, whether  there  was  really
accord and satisfaction, is in the affirmative, in our  view  no  arbitrable
dispute existed so as to exercise power under section 11  of  the  Act.  The
High Court was not therefore justified in exercising power under Section  11
of the Act.


10.   In the circumstances, we allow the present  appeal  in  the  aforesaid
terms and set aside the order of the High Court .  No order as to costs.

                                        .............................J.
                                        (Anil R. Dave)


                                        .............................J.
                                        (Uday Umesh Lalit)
New Delhi,
December 04, 2014