Supreme Court of India (Full Bench (FB)- Three Judge)

Writ Petition (Civil), 328 of 2002, Judgment Date: Feb 08, 2017

                                                        REPORTABLE

                       IN THE SUPREME COURT OF INDIA

                       CIVIL ORIGINAL JURISDICTION

                       IA NOS.42,43,50-51 & 52-53
                                  IN
                       WRIT PETITION(C) NO. 328/2002


Narmada Bachao Andolan                            ..Petitioner

                            versus

Union of India and others                         ..Respondents

In the Matter of:

Kailash Awasya and others etc. etc.               ..Applicants

                                  WITH

                 SPECIAL LEAVE PETITION(C) NO.7663/2016




                                  O R D E R


JAGDISH SINGH KHEHAR, CJI


            We have heard this matter over a number of  days.   The  instant
exercise is being carried out, so as to arrive at an  equitable  settlement,
for the rehabilitation of the 'project affected families',  consequent  upon
the implementation of the Sardar Sarovar  Project.  The  figures,  which  we
will indicate in our order, may be treated as tentative.  It  will  be  open
to others similarly situate, to seek the same relief, by establishing  their
credentials (before the Grievance Redressal Authority).
2.          We  are  informed,  that  rehabilitation  packages,  had  to  be
offered to 4998 'project affected families' in the State of Madhya  Pradesh.
 Out of these 'project affected  families',  4774  families  opted  for  the
'Special Rehabilitation Package', namely, they would accept cash payment  as
compensation,  and  would  purchase  land  out  of  the  said  payment.  The
aforestated  payment  was  to  be  made  in  two  installments.   The  first
installment would be spent as earnest  money,  and  the  second  installment
would constitute the final payment for executing the sale deed.  Out of  the
4774 families, who had opted for the 'Special Rehabilitation Package',  4264
families are stated to have accepted, both installments.  Out  of  the  4998
'project affected families', according to the learned Attorney General  (and
the other learned counsel representing  the  concerned  State  Governments),
4264 have been fully compensated.  These 4264  'project  affected  families'
are not entitled to any further compensation.
3.          Out of those, who had  opted  for  the  'Special  Rehabilitation
Package', 386 families were extended the first installment only,  and  could
not be favoured with the second installment.   They  are  disputants  before
this Court.  In addition to these disputants, there were 120  families,  who
did not accept any money whatsoever, and another 4 families  which  were  in
litigation with reference to the compensation payable.  Calculated in  terms
of the figures,  indicated  hereinabove,  510  (386  +  120  +  4)  'project
affected families', are still entitled to  compensation,  as  they  had  not
been extended full compensation. This position has been acknowledged by  the
Union of India (as also, the concerned State Governments).
4.           Besides  those  who  opted  for  the  'Special   Rehabilitation
Package', there were some families who had sought land in lieu of land,  and
not cash payment, under the 'Special Rehabilitation Package'.  In  fact,  we
are informed, there were 224 such families.  Out of those 224  families,  53
families accepted the land offered to them, without  any  objection.   These
53 project affected families, according  to  the  learned  Attorney  General
(and other learned counsel representing the  concerned  State  Governments),
have been fully compensated, and as such, their claim cannot be  treated  as
a surviving claim.  The remaining 171 families, have not  been  compensated,
even though they  are  'project  affected  families'.   These  171  'project
affected families' are admittedly entitled to their rehabilitation claim.
5.          Based on the figures, depicted in the foregoing two  paragraphs,
it is apparent, that 681 families are yet to be extended  compensation  (510
'project affected families', which had originally  opted  for  the  'Special
Rehabilitation Package' + 171 families which had claimed  land  in  lieu  of
land).
6.          During the course of our deliberations, it came to  be  accepted
at one stage, that compensation to these 681 families should  be  determined
under the provisions of the Land Acquisition Act, 2013.  However,  based  on
the  suggestions  made  at  the  behest  of  the  learned  counsel  for  the
applicants, that the land value in the vicinity ranges from  Rupees  fifteen
lakhs per hectare, to Rupees eighty lakhs per hectare, we were of the  view,
that it would be more appropriate to  finally  determine  the  compensation,
here and now. The average suggested payment at the  behest  of  the  learned
counsel for the applicants would be in the range of Rupees thirty lakhs  per
hectare,  and  as  such,  every  affected  family  would  be   entitled   to
approximately, Rupees sixty lakhs, in terms of their  entitlement  (for  two
hectares of land) as compensation.   Mr.  Mukul  Rohatgi,  learned  Attorney
General for India suggested, that the agreed  figure  be,  fixed  at  Rupees
forty five lakhs, in lieu  of  two  hectares  of  land  to  which  they  are
entitled, and that, the matter be concluded here and now itself.
7.          Having given our thoughtful  consideration  to  the  suggestions
made at the behest of the learned counsel for  the  rival  parties,  we  are
satisfied in directing the concerned authority, to pay compensation  to  the
681 'project affected families', who have yet to receive  compensation,  and
who have been fully described above,  at the rate of Rupees sixty lakhs  per
family, as a matter of full and final settlement.  An  undertaking  in  this
behalf should be obtained, before the amount of compensation is released.
8.          It is also apparent, that a large number  of  families,  out  of
the 4264 families which had received both installments, under  the  'Special
Rehabilitation Package', were duped.  The number of duped 'project  affected
families', indicated in the Justice S.S. Jha Commission's Report,  is  1358.
This number is affirmed by the  learned  Attorney  General  for  India,  and
confirmed  by  the  respective  State  counsel.   Referring  to  these  1358
families, the  Jha  Commission   in  its   report  of   January,  2016,  had
observed as under:

“(29) Poor oustees particularly  tribals  have  been  looted  by  middlemen.
They  have  lost  their  livelihood  and  are  not  daily   wagers.    Their
installments  have  been  siphoned  off  by  the  middlemen.   When  oustees
appeared before the Commission were not even having clothes to  wear.   They
have wrapped small cloth or towel  round  their  waist  when  they  appeared
before the Commission.”

                                       (emphasis is ours)

It is in the above circumstances,  that  the  Jha  Commission  recorded  the
following conclusions, in its report:
                 “CONCLUSION
1.    The reason for  fake  sale  deeds  is  a  faulty  SRP  policy  of  the
Government. The Government was not having sufficient irrigated  agricultural
lands in their Land Banks near the R  &  R  sites.   The  Policy  itself  is
against Narmada Award, and the judgment of the Supreme Court. Supreme  Court
has observed that the PAFs  and  PAPs  should  live  better  life  has  been
frustrated by this Policy.

(i).  By not allowing any scrutiny of the sale deeds and free hand has  been
given to the  Rehabilitation  Officers  and  Land  Acquisition  Officers  in
disbursing the compensation which resulted into large number  of  fake  sale
deeds.

(ii)  The free access to middlemen in the Office  of  NVDA  in  getting  the
money  withdrawn  of  the  oustees  also  reflects  about  the  interest  of
middlemen and nexus with NVDA officials. Though  evidence  is  not  received
against the NVDA officials all the oustees have stated that they  were  made
to sit outside the NVDA office and their work was done by the middlemen  and
they were made to  sign  on  the  papers  without  explaining  the  contents
discloses that NVDA officials had obtained signatures or  thumb  impressions
of the oustees without explaining the contents demonstrate  irregularity  on
their part and they are prima facie responsible for  large  number  of  fake
registries.

2.    The quality of construction was very poor without  any  planning.   No
geographical mapping was done before selecting  the  R  &  R  sites  whereby
cultivable good black cotton soil is converted  into  house  building  sites
for residential plots.  There was a faulty  policy  of  not  establishing  a
laboratory to test the soil for carrying  out  constructions  on  the  black
cotton soil.  The construction was done on the R & R sites  on  common  maps
and designs of the building. Superior officers had never cared to visit R  &
R sites to examine the  construction  work.  The  Government  has  found  40
engineers responsible for substandard quality of construction, but  has  not
cared to rectify the defect  after  finding  the  substandard  construction.
Most of the places the expenditure on construction has gone waste as  the  R
& R sites are not occupied by the oustees or they are occupied by  very  few
PAPs and PAFs.  Thus, the expenditure on these sites is waste of money.

3.    The NVDA has not maintained  proper  records  relating  to  livelihood
grants and alternative livelihood which itself demonstrate  that  there  was
large scale corruption in the livelihood grants and alternative livelihood.

The officers of NVDA involved in allotment of  house  plot  sites  have  not
followed the Rules framed by the Government in allotting  the  plots.   They
have allotted the plots in an  arbitrary  matter  and  usurp  the  power  of
changing the allotment which was not vested with  them.   Thus,  this  shows
their corrupt intention. Any arbitrary action  attracts  the  vice  of  mala
fide.  The officers involved in allotment of plots  are  wholly  responsible
for irregularities and corruption in allotment and change of plots.”

                                       (emphasis is ours)

9.          We are of the considered  view,  that  even  though  the  above-
mentioned 1358 project affected families were paid both  installments,  they
need to be further compensated, so as to alleviate their hardship,  as  they
have not been able to purchase land in lieu of land, not  because  of  their
own fault or lapse, but because they were duped. This would enable  them  to
purchase alternative land at  the  lesser  rate  suggested  by  the  learned
counsel for the applicants.  It is in the above view of the matter, that  we
hereby direct the concerned authorities, to pay these 1358 project  affected
families, a sum of rupees  fifteen  lakhs  per  family.   While  making  the
instant payment, earlier  installments  made  to  such  families,  shall  be
deducted (from out of the sum of Rupees  fifteen  lakhs).  At  the  time  of
making  the  above  payment,  the  concerned  authority  shall   obtain   an
undertaking from the concerned 'project affected family', that  the  instant
payment would be as a matter of final settlement  of  their  claim,  arising
out  of  the  implementation  of  the  Sardar  Sarovar  Project.   Any  such
claimant, who fails to furnish the above undertaking, would not be  entitled
to any payment of compensation.
10.          The  above  order  takes  into  consideration  the   issue   of
compensation, towards all 'project affected families'.
11.         We have not addressed the issue of the  amenities,  that  needed
to have been extended to the concerned families, in  terms  of  the  Narmada
Water Disputes Tribunal Award, dated 12.12.1979.  In order  to  address  any
such grievance  (with  reference  to  the  amenities  postulated  under  the
Tribunal's award, referred  to  above),  we  permit  such  of  the  'project
affected families', who have any grievance, to raise the  same,  before  the
concerned Grievance Redressal Authority, within one  month  from  today.  In
case such a representation  is  made,  and  is  accepted  by  the  concerned
Grievance  Redressal  Authority,  the  concerned   State  Government   shall
implement the recommendation, as expeditiously as possible, without  raising
any unnecessary objection. In case, any of the “project  affected  families”
is not satisfied with the recommendations made by  the  Grievance  Redressal
Authority (on the representation, or alternatively, if no decision is  taken
thereon, within three months of registration  of  such  representation),  it
shall be open to such  family,  to  pursue  its  cause  before  a  Court  of
competent jurisdiction, in consonance with law.
12.         All connected petitions/applications  are  disposed  of  in  the
above terms.  Payment in consonance with the instant order,  (to    the  681
'project affected families', referred  to  above)  by  the  concerned  State
Government shall  first  be  released  to  the  Narmada  Valley  Development
Authority (for short 'NVDA'), which in turn shall deposit  the  compensation
payable to the 681 'project  affected  families',  in  the  account  of  the
Grievance Redressal Authority, within two  months  from  today.   The  above
amount shall positively be released, to the concerned 681  project  affected
families, within one month thereafter.  The same procedure  is  directed  to
be followed with respect to the 1358 project affected  families,  which  are
stated to have been duped.
13.         All the occupants including all the 'project affected  families'
shall vacate the submergence area under reference, on or before  31.07.2017,
and in case there  are  individuals  in  the  submergence  area,  after  the
aforesaid deposit has been made into the account of the Grievance  Redressal
Authority, after 31.07.2017, it shall be open to  the  State  Government  to
remove all such individuals forcibly.
14.         The order passed hereinabove, is  exclusively  directed  towards
the resettlement and rehabilitation of the 'project affected  families',  in
the State of Madhya Pradesh.  We hereby direct the  States  of  Gujarat  and
Maharashtra to conclude all the  commuted  resettlement  and  rehabilitation
activities, in the respective States, within three months from today.
15.         In view of the  consolidated  order  passed  by  us  today,  all
pending   litigations,   civil   and   criminal,   emerging   out   of   the
recommendations made by the Jha Commission, in  the  report  dated  January,
2016, shall come to an end.
16.     The instant  order  has  been  passed  by  us  in  exercise  of  our
jurisdiction under Article 142 of the Constitution of India,  and  with  the
tacit consent of the Union of India (and the concerned  State  Governments),
and shall not ever  be  treated   as   a   precedent,  or   be   cited   for
similar  claims  for compensation.
            Disposed of in the aforesaid terms.


                                             …...................CJI
                                             [JAGDISH SINGH KHEHAR]


                                             …....................J.
                                             [N.V. RAMANA]


NEW DELHI;                             ….....................J.
FEBRUARY 08, 2017.                           [Dr. D.Y. CHANDRACHUD]



ITEM NO.10               COURT NO.1               SECTION PIL(W)

               S U P R E M E  C O U R T  O F  I N D I A
                       RECORD OF PROCEEDINGS

I.A. Nos. 42, 43, 50-51 & 52-53 in Writ Petition(s)(Civil) No(s).  328/2002

NARMADA BACHAO ANDOLAN                             Petitioner(s)

                                VERSUS

UNION OF INDIA AND ORS.                            Respondent(s)

In The Matter of:

Kailash Awasya and others etc. etc.                 Applicant(s)
(for directions, permission to file addl. documents & exemption from filing
O.T.  and office report)
WITH
SLP(C) No. 7663/2016
(With appln.(s) for permission to file lengthy list of dates and Interim
Relief and Office Report)

Date : 08/02/2017 These applications/petition were called on for
     hearing today.

CORAM :
         HON'BLE THE CHIEF JUSTICE
         HON'BLE MR. JUSTICE N.V. RAMANA
         HON'BLE DR. JUSTICE D.Y. CHANDRACHUD


For Applicant(s) Mr. Sanjay Parikh, Adv.
                       Mr. Clifton Doozario, Adv.
                       Ms. Anitha Shenoy, Adv.
                       Ms. Nini Susan Thomas, Adv.
                       Ms. Surabhi Aggarwal, Adv.
                       Ms. Srishti Agnihotri, Adv.
                       Ms. Medha patkar, in person

For Petitioner(s)      Mr. Prashant Bhushan,AOR
in WP 328/2002

For Petitioner(s)      Mr. P.S. Patwalia, ASG
in SLP 7663/2016 Mr. C. D. Singh,Adv.
& for respondent(s)    Ms. Sakshi Kakkar, Adv.
in WP & IAs

For Respondent(s)      Mr. Mukul Rohatgi, AG
(Narmada Control Mr. Tushar Mehta, ASG
Authority)       Mr. Syed Naqvi, Adv.
                       Mr. Rajesh Kumar, Adv.
 for MOEF              Mr. Tushar Mehta, ASG
                       Mr. A.K. Ganguli, Sr. Adv.
                       Mr. N.K. Karhail, Adv.
                       Ms. Manita Verma, Adv.
                       for Mr. G.S. Makker, AOR

For MOWR               Mr. Tushar Mehta, ASG
                       Mrs. V. Mohana, Sr. Adv.
                       Ms. Kiran Bhardwaj, Adv.
                       Mr. Rajat Nair, Adv.
                       for Mr. M.K. Maroria, AOR

State of Gujarat Mr. Ashok Desai, Sr. Adv.
                       Ms. Hemantika Wahi, Adv.
                       Ms. Jesal Wahi, Adv.
                       Ms. Mamta Singh, Adv.

State of               Mr. Arvind V. Savamt. Sr. Adv.
Maharashtra            Mr. Nishant R. Katneshwarkar, Adv.

State of Rajasthan     Mr. S.S. Shemshery, AAG
                       Mr. Amit Sharma, Adv.
                       Mr. Ankit Raj, Adv.
                       for Mr. Milind Kumar, AOR

          UPON hearing the counsel the Court made the following
                             O R D E R

            Interlocutory applications/petitions stand disposed of, in
terms of the Reportable signed order.



  (Renuka Sadana)                            (Parveen Kumar)
Assistant Registrar                       AR-cum-PS
      [Reportable Signed Order is placed on the file]