Supreme Court of India (Division Bench (DB)- Two Judge)

Appeal (Civil), 9732 of 2016, Judgment Date: Sep 27, 2016

                                                                  REPORTABLE

                        IN THE SUPREME COURT OF INDIA

                        CIVIL APPELLATE JURISDICTION

                         CIVIL APPEAL NO…9732../2016
                (arising out of S.L.P.(Civil) No.11876/2013)


Mahanadi Coalfields Ltd. & Ors.                         …Appellants

                                    Vs.

M/s. Dhansar Engineering Co. Pvt.Ltd & Anr.       .....Respondents


                             J U D G M E N T

A.M.KHANWILKAR,J.


      Leave granted.


2.    This appeal challenges the judgment of the Division Bench of the  High
Court of Orissa at Cuttack dated 7th November 2012 in Writ Petition  (Civil)
No. 1093/2006.

3.    Briefly stated, on 2nd December  2002  the  appellants  issued  notice
inviting tenders for the  work  of  extraction  and  transfer  of  Coal/Coal
Measure Strata (CMS) by deploying   “Surface  Miners”  on  hiring  basis  at
various Open Cast Projects, inter-alia, at Lakhanpur.

The respondents were declared the lowest bidder having  quoted  Rs.17/-  per
cubic meter for the stated contract.  A  letter  of  intent  was  issued  in
favour of the respondents on 4th April,  2003  which  was  accepted  by  the
respondents on 14th April, 2003. Work order was  issued  in  favour  of  the
respondents on 23rd April, 2003 and a formal agreement was executed  between
the parties on 26th May 2003. The relevant  clauses  of  the  agreement  are
clauses 2 to 5 which read as under:

“2)   Time shall be considered as one of the essence  of  the  contract  and
the  time  for  the  completion  of  the  contract  shall  be  counted  from
16.04.2003 of  from  the  date  of  issue  of  L.O.I.  to  which  terms  the
contractor agreed at the time when his tender was accepted and the  contract
shall be completed by 15.04.2004 provided, sufficient face  is  provided  by
the management.

3)    The work order has already been issued for a period of one year for  a
quantity of 49,50,000 Cum.  At the rate of Rs. 17.00/Cum. for an  amount  of
Rs. 8,41,50,000.00.

4)    The contractor shall re-deploy the Surface Miner in other OCPs as  per
direction of the Company.

5)    The tendered quantity may be reduced  or  increased  by  +/-  30%.  No
claim shall lie on the  company  for  such  variation  in  quantity  whether
increase or decrease.  The tenderer must be in a position  to  increase  the
machine capacity upon 30% extra daily quantity within 45 days notice.”

                                        (emphasis supplied)

4.    As the agreement refers to the terms  and  conditions  of  the  tender
document, we may usefully refer to the relevant clauses therein.


“11.0 VARIATION IN SCHEDULED QUANTITY EXTENT AND RATE

The quantity given in the “Schedule of Quantity’s provisional and  is  meant
to indicate the extent of the work  and  to  provide  a  uniform  basis  for
tendering and any  variation  either  by  addition  or  omission  shall  not
vitiate the contract.

The tendered quantity may be reduced or increased by 30%. No claim shall  be
on the company for such variation in quantity whether increase or  decrease.
 Tenderer must be in a position to increase the machine capacity  within  45
days notice to achieve the extra increased quantity.

If the additional altered or substituted work includes any item of work  for
which no “rate is specified in the contract, “rate” for such item  shall  be
determined by the Company Headquarters in the following manner:-

The rate shall be derived from the rate for similar or near similar item  of
work awarded in the Company, or

The rate shall be derived from contractor’s rate claimed for  such  item  of
work supported by analysis of the rate claimed by the contractor.  The  rate
to  be  determined  by  the  Company  Headquarters  as  may  be   considered
reasonable taking  into  account  percentage  of  profit  and  overhead  not
exceeding ten percent or on the basis of market rate, if any  prevailing  at
the time when work was done.


However,  the  Engineer-in-charge  shall  be  at  liberty  to   cancel   the
instruction by giving notice in writing and to  arrange  to  carry  out  the
work in such manner as he considers advisable under the circumstances.   The
contractor shall under no circumstances suspend the work in the plea of non-
settlement of rates.


The  time  of  completion  of  the  originally  contracted  work  shall   be
extended/reduced   by   the   Company   in   the   proportion    that    the
additional/reduced work (in value) bears to  the  original  contracted  work
(in value), as may be assessed and certified by the Engineer-in-charge.


The company through its Engineer-in-charge or his representative, on  behalf
of the company, shall have power to omit any part of the work for any  other
reason and  the  contractor  shall  be  bound  to  carry  out  the  work  in
accordance with the instruction given to Engineer-in-change.  No  claim  for
extra charges/damages shall be made by the contractor on these grounds.


In the event of any deviation being ordered which  in  the  opinion  of  the
contractor changes radically the original scope and nature of the  contract,
the contractor  shall  under  no  circumstances  suspend  the  work,  either
original or altered or substituted and the dispute/disagreement  as  to  the
nature of deviation or the rate to  be  paid  therefore  shall  be  resolved
separately with the company.


13.   TIME FOR COMPLETION OF CONTRACT

Time is the essence of the contract.

            The contractual period of work shall be as specified in  NIT/LOI
Agreement.  The work shall be deemed to have commenced  within  60  days  of
the issue of Letter of Intent at all  the  places  and  should  be  able  to
execute 100% of the daily awarded quantity from 61th day from  the  date  of
issue of LOI.

            Agreement should be executed before the release of 1st, on  A/c.
bill.

            For failure to reach the  desired  quantity  from  61th  day  of
issue of LOI, contractor shall be liable for penalty @  20%  of  amount  for
shortfall quantity i.e. (shortfall quantity x awarded rate x 20%).

            The contractor must be prepared to work continuously  for  three
shifts a day and all the working days in a year.

            If the contractor, without  valid  reason,  commits  default  in
commencing the execution of the work within 60 days from the date  of  issue
of LOI or fails to attain within  specified  date  of  issue  of  Letter  of
Intent, the required quantity  to  give  the  ultimate  output  as  per  the
schedule of quantity, the company  shall  without  prejudice  to  any  other
right or remedy, be at liberty, by giving 15 days notice in writing  to  the
contractor, to forfeit the Earnest Money deposited by him and  to  terminate
the contract.
………………….

14.0  EXTENSION OF DATE OF COMPLETION

      On happening of any event  causing  delay  as  stated  hereunder,  the
contractor shall apply for time extension to the CGM/GM of the Area.

 Abnormally bad weather

 Serous loss or damage by fire

Civil Commotion, strike or lockout affecting execution of       work

Non-availability   of   working    force    or    site    which    is    the
responsibility of the company to supply.

Any other cause which, at the sole discretion of the company, is beyond  the
control of the contractor.

The contractor may request the company in  writing  for  extension  of  time
within 14 days of happening of such event ceasing delay stating  the  period
for  which  extension  is  desired.   The  company  may,   considering   the
eligibility of the request, give a fair and reasonable extension of time  of
completion of  the  work.  Such  extension  shall  be  communicated  to  the
contractor, in  writing,  by  the  company  through  the  Engineer-in-charge
within 1 month of the date of receipt of such request.
……………………

30.0  DEFAULT AND PENALTY


30.1  LOSS OR DAMAGE


Any loss or  any  expenditure  for  damages  incurred  by  company  will  be
recoverable from the contractor whether fully or partly if such  expenditure
for damages have been caused  either  directly  or  indirectly  due  to  any
negligence or failure on the part of the contractor.


30.2.       SHORTFALL PENALTY IN MECHANICAL EXCAVATION AND LOADING


The average daily quantity of the quarter shall be worked  out  by  dividing
the mutually agreed quarterly allotted quantity by the working days  of  the
quarter, ending on 30th June, 30th September, 31st  December  &  31st  March
Average daily quantity of a quarter must conform to average  daily  quantity
of the year contractual period.


In the event of the Contractors failure to comply with the rate of  rate  of
progress as per the agreed progress chart the contractor shall be liable  to
pay a penalty on the quantity by which the contractor has fallen short  from
the allotted quarterly quantity at the rate of 20% of the awarded rate.


For failure of produce size coal as per NIT (-100 mm  size),  the  contactor
shall also be liable for penalty at the rate of 20% of the awarded rate  for
such over size quantity.


The shortfall penalty will be recovered concurrently from the  running  bill
which will be adjusted  annually  subject  to  that  the  total  penalty  is
limited to 20% of (Annual Shortfall Quantity x Rate).


30.3  WAIVAL OF PENALTY


The company may at its sole discretion waive the payment of penalty in  full
or in part in request received from the contractor depending  the  merit  of
the case if the entire work is completed within the  date  as  specified  in
the contract or within extended period approved without imposing penalty.


31.0.       SETTLEMENT OF DISPUTE


Except where otherwise provided for  in  the  contract,  all  questions  and
disputes relating to meaning of the scope,  specification  and  instructions
herein before mentioned and as to any other question, claim right matter  or
thing whatsoever in any way arising out of  or  relating  to  the  contract,
instructions, orders or these conditions or otherwise concerning  the  works
or the execution or failure to execute the same whether arising  during  the
progress of the work or after the completion or abandonment  thereof,  shall
be referred to the Chairman-Cum-Managing Director  of  the  Company  or  any
other person authorized by him.


It is also a terms of the Contract if the contractor (s)  do/does  not  make
any demand for any claim(s) in writing 90 days of receiving  the  intimation
from the company that the bill is ready  for  payment  or  of  the  date  of
receiving payment whichever is earlier, the claim of the Contractor(s)  will
be deemed to have been waived and absolutely barred and  the  Company  shall
be released and discharged of all liabilities under the contract in  respect
of these claims.”


(emphasis supplied)


5.    The respondents commenced the work of surface miners at Lakhanpur  and
completed around 70% of the awarded quantity by the end  of  February  2004.
Due to financial problems faced by the respondents vide  letter  dated  13th
February 2004, they requested the appellants to  allow  them  to  close  the
contract by invoking  power  to  reduce  the  quantity  by  30%  of  awarded
quantity, under clause 11 of the general terms and conditions  of  the  NIT;
and to issue fresh tender for the remaining work.  The  appellants  did  not
accede to the said request and informed the respondents  vide  letter  dated
16th February 2004,  stating  that  the  agreement  is  for  performing  the
contract upto 100% of awarded value and provision  of  executing  extra  30%
quantity on the same terms and conditions.  The  respondents  requested  the
appellants vide letter dated 9th May 2004  to  extend  the  time  frame  for
completion of the remaining contract upto 15th July  2004  as  the  contract
period was only till 15th April, 2004.  The said letter reads thus:

                                                                 ANNEXURE-P8

                     DHANSAR ENGINEERING CO. PVT. LTD.,

                                                                        SITE

P.O. Dhansar                 P.O. Jorabaga

Dhanbad – 828106 (Jharkhand) Via Belpahar

Ph: 0326 – 307161/7074.           Dist.: Jharsuguda (Orissa)

Fax: 0326 303294             Ph.: 06645 -233222

                             E-mail – decopl@dte.vsnl.net.in



Ref: No. DECO/NIT 276/2004              Date: 09.05.2004


To

The chief General Manager

Lakhanpur Area

Mahanadi Coalfields Ltd.,

(Through proper channel)


Sub:  WORK OF  EXTRACTION  AND  TRANSFER  OF  COAL/COAL  MEASURE  STRATA  BY
DEPLOYING SURFACE MINER ON HIRING AT LAKHANPUR OCP OF LAKHANPUR AREA (NIT  –
276) VIDE WORK ORDER NO. MCL/CGM/LKPA/  SO(M)/SUR.  MINER/2003-04/001  DATED
23.04.2003.


Dear Sir,

            Management is fully aware that tender rate of Rs. 17/-  per  Cum
for the work is all time low and wholly unworkable.  We are working at  this
rate at a colossal loss.

            We started the  work  almost  at  the  approach  of  monsoon  on
16.04.2003  and  we  could  not  also   speed   up   progress   because   of
transportation restriction between 11.00 A.M. & 4.00 P.M. against heat  wave
alert and thereafter on-set of heavy rains consequenting  upon  bad,  water-
logged & slippery road followed by short supply of  rakes.  With  all  these
operational hazards beyond our control, we could accomplish 34.74 Lakhs  Cum
upto 31.03.2004.

            As our financial loss was soaring day by day, we  had  requested
for foreclosure of the work after we have completed  70%  of  the  work  but
this was not agreed to by GM(TC) vide his letter No. 1251 dated 26.03.2004.

            Therefore, being under contractual obligation we had,  no  other
alternative but to apply for extension of time  upto  15.07.2004  and  would
request you to kindly treat the contract as closed with  the  completion  of
the above awarded quantity as we are ill-afford to bear further loss.


Thanking You,


                                                           Yours faithfully,

                                                                        Sd/-

                                      For Dhansar Engineering Co. Pvt. Ltd.”


6.    This request of the respondents was considered by  the  appellants  in
its 68th Meeting of the Board. Extension of three months  time  was  granted
while reserving the right to impose penalty. The respondents  were  informed
accordingly vide letter dated 5th June 2004. As a result of  this  decision,
the contract period was extended until 15th July 2004 on the same terms  and
conditions agreed upon. As the contract  period  was  subsisting  till  15th
July 2004, the appellants issued an approval order dated 11th June  2004  to
increase of 30% extra quantity i.e. 14.8 Lakh cubic meter  at  the  existing
rate of next tender rate or whichever is  lower,  amounting  to  Rs.  252.42
Lakh. The respondents by letter dated 11th June  2004,  however,  reiterated
that the contract be treated as closed -  as  they  were  on  the  verge  of
completing the quantity specified in the contract by  15th  June  2004.  The
said letter reads thus:

                                                              “ANNEXURE – P9

                     DHANSAR ENGINEERING CO. PVT. LTD.,

                                                                        SITE


P.O. Dhansar                 P.O. Jorabaga

Dhanbad – 828106 (Jharkhand) Via Belpahar

Ph: 0326 – 307161/7074.           Dist.: Jharsuguda (Orissa)

Fax: 0326 303294             Ph.: 06645 -233222

                             E-mail – decopl@dte.vsnl.net.in



Ref: No. DECO/NIT 276/2004              Date: 11.06.2004

To

The chief General Manager

Lakhanpur Area

Mahanadi Coalfields Ltd.,


Sub:        NIT NO. 276 –  EXTRACTION  AND  TRANSFER  OF  COAL/COAL  MEASURE
STRATA BY DEPLOYING SURFACE MINER ON HRING BASIS AT LAKHANPUR OCP OF MCL


Dear Sir,

            We would like to inform you that the  order  quantity  of  49.50
lakh Cum is in the verge of completion, and is expected that  this  quantity
will be fully completed by 15.06.2004.


            In this connection kindly refer to our  letter  No.  DECO/NIT  –
276/2004 dated 09.05.2004 under which we had  requested  your  good-self  to
treat the contract as closed with the completion of the  quantity  of  49.50
lakh Cum.  In reiterating our request we would inform you  that  we  may  be
forced to stop the machine as it is giving trouble and we are  not  able  to
repair the machine for dire scarcity of fund.

Thanking You,

                                                           Yours faithfully,

                                                                        Sd/-

                                       For Dhansar Engineering Co. Pvt. Ltd.


Copy to:     1)  The Director (Technical) MCL, Burla,

             2)   The General Manager, Lakhanpur Area.”


7.    The respondents by another letter dated 6th July 2004 seeking  closure
of contract due to financial hardship, stated  that  they  were  withdrawing
their operations. The appellants, however, by letter  dated  7th  July  2004
called upon the respondents to continue with  the  remaining  work  assigned
under the contract which was still  subsisting;  and  also  noted  that  the
respondents had by then completed only 105% of  the  contract  work  out  of
130%. The said communication reads thus:

                                                              “ANNEXURE –P12


“UNDER JURISDICTION OF SAMBALPUR COURT ONLY”

                         MAHANADI COALFIELDS LIMITED

                     (A SUBSDIARY OF COAL INDIA LIMITED)


Corporate Office                  Office of the Chief General Manager


M.C.L. Complex               LAKHANPUR AREA

Jagriti Vihar                     P.O. bandhabahal – Via: Belpahar

Burla – 768018               Dist.: Jharsuguda, Pin 768217

Dist: Sambalpur (Orissa) phone: 33202, STD CODE: 06645


Ref: No. MCL/CGM/LKPA/SO(M)/932   Date: 07.07.2004


To


M/s Dhansar Engineering Co. pvt. Ltd.

Site Office: P.O. Jorabaga, Via – Belpahar,

Dist: Jharsuguda (Orissa)

Pin: 768217.

Ref:  (1) Work order No.  MCL/CGML/LKPA/SOM(M)/Sur  Miner/2003-04/001  dated
23.04.2003 for Extraction  and  Transfer  of  Coal/Coal  measure  strata  by
deploying ‘Surface Miners” on hiring basis at Lakhanpur OCP (NIT-276).

Sub: Contract of Surface Miner work at Lakhnapur OCP (under NIT No. 276)

Dear Sir,

      Kindly refer to your letter No. DECO/NIT-276/2004 dated  6.07.2004  on
the above subject.

This is to bring to your notice that as per clause No.2 of  the  work  order
forming part of the agreement the tendered quantity can be increased by  30%
and no claim shall lie on the company for  such  variation  till  date  only
105% (approx.) of the awarded quantity has been executed by you.   There  is
no communication from MCL-HQ for finalization of new contract for the  above
work till date.

      In such condition you are requested  to  continue  your  operation  of
surface miner at Lakhanpur  OCP  till  completion  of  30%  extra  quantity.
Withdrawal of operations of Surface  Miner  at  this  stage  will  seriously
affect dispatch of coal to our Pit head customer (OPGC)  and  other  linkage
customers earning a bad name to the company.

Thanking You,

                                                           Yours faithfully,
                                                                        SD/-
                                                             GENERAL MANAGER
                                                              LAKHANPUR AREA

Copy to:

The Chairman-cum-Managing Director, MCL Buria
The Director (T), MCL, Burla
The General Manager (TC), MCL HQ, Burla
The Staff Officer (Mining) LKPA”

8.    The respondents, however, renewed their request to the  appellants  to
allow them to close the contract vide letters dated 8th July 2004  and  12th
July 2004. The respondents finally wrote to  the  appellants  on  15th  July
2004 which reads thus:

                                                             “ANNEXURE – P15


                     DHANSAR ENGINEERING CO. PVT. LTD.,

                                                                        SITE


P.O. Dhansar                            P.O. Jorabaga

Dhanbad – 828106 (Jharkhand)            Via Belpahar

Ph: 0326 – 307161/7074.                 Dist.: Jharsuguda (Orissa)

Fax: 0326 303294                  Ph.: 06645 -233222

                                        E-mail – decopl@dte.vsnl.net.in



Ref: No. DECO/NIT 276/2004                         Date: 15.07.2004


To


The General Manager,

Lakhanpur Area, MCL,


Sub:        Closing Down of work of Surface Miner  at  lakhanpur  OCP  under
NIT No. 276


Dear Sir,


A copy of our letter No. DECO/NIT/2004 dated  12.07.2004  addressed  to  CMD
MCL Burla with copies to D(T) and GM(TC), MCL HQ is  enclosed  herewith  for
your information.


As notified this is to  inform  you  that  we  are  stopping  the  work  and
withdrawing from operations at Lakhanpur OCP  with  effect  from  16.07.2004
(FN).  It is not out of place to mention that we  had  been  expressing  out
intention to abandon execution after completing 100% of the work on  account
of our un-economical plight out has been continuing  wit  the  execution  to
cooperate with the management to arrange next  recourse,  so  as  to  ensure
that the production schedule of Lakhanpur OCP does not suffer any set  back.

We could not  however  elicit  any  communication  to  our  letters  or  any
sympathetic decision from the management.  In  the  meanwhile  the  contract
period also expired by 15.07.2004.

In view of the above situation we have no other alternative but to  withdraw
from operation after working the full period of the contract.

You are therefore requested to  kindly  take  up  final  measurement  as  on
15.07.2004 and finalise the contract.

Thanking you and assuring you of our best cooperation to all time come.


                                                           Yours faithfully,



                                                                        Sd/-

                                       For Dhansar Engineering Co. Pvt. Ltd.



Copy to:

The CMD, MCL, Burla Fax No. 0663 -2432066/2542366

The D(T), MCL, Burla, Fax No. 0663 – 2542509

The GM (TC), MCL, Burla, Fax No. 0663 – 2542629.”


9.    As the respondents  had  already  informed  the  appellants  of  their
intention to withdraw from operation  after  the  full  contract  period,  a
fresh tender process was commenced by the appellants which  culminated  with
a letter of intent in favour  of  third  party  (Sainik  Mining  and  Allied
Services) but at a higher rate of Rs.31.50 per cubic meter.

10.   The bills submitted by the respondents for  the  work  executed  under
the contract dated 26th May  2003  were  considered  by  the  Board  of  the
appellants in its 72nd meeting. The decision taken in the said  meeting  was
communicated to the respondents by letter  dated  8th  December  2014  which
reads thus:

“ANNEXURE R/9


MAHANADI COALFIELDS LIMITED

(A subsidiary of Coal India Limited)

P.O. – Jagruti Vihar, Burla, Distt. Sambalpur-768020 (Orissa)

Gram : SAMBCOAL,:      Fax : (0663) 2542770

Phone : PBX :- (0663) 2542461 to 2542469


Ref. No. MCL/SBP/GM(TC)/2004/1047 Dt. 08.12.2004


To,

      General Manager,

      Lakhanpur Area


Dear Sir,

            Enclosed herewith please find a copy of Extract from  the  Draft
Minutes of the 72nd meeting of the Board of Directors of MCL  held  on  27th
November, 2004  at  Kolkata  in  respect  of  imposing  penalty  by  way  of
forfeiture of Earnest Money Deposit of  Rs.  20.00  lakhs  to  M/s.  Dhansar
Engineering (P) Ltd., for non-performance of 130% of  the  total  contracted
quantity under NIT – 276.  The relevant extract is appended below:-

             “The  Board  deliberated  on  the  subject  in  detail  and  in
consideration of the facts and circumstances highlighted in the agenda  note
and  in  recognition  of  the  clarification  offered  during  deliberation,
decided that penalty as  proposed  in  the  agenda  note  in  terms  of  the
provisions of the contract be imposed on M/s Dhansar Engineering  pvt.  Ltd.
For non-performance of 130% of the total contracted quantity under NIT-276.

            Proposed in the Agenda Note

      Clause No. 16 – (Forfeiture of Earnest Money)

            The contractor is liable  for  forfeiture  Money  Deposit  under
Clause No. 16(a) and 16(d) which reads as under:-

16(2) withdraws his offer during the validity period of offer.

16(a) fails to execute the order as per terms and conditions thereof.

In the present case the EMD is Rs. 20.00 lakhs.

Clause No. 30.2 (Shortfall penalty in Mechanical excavation and loading)


      130% of Contract Quantity – 63,70,000.00 Cu.m.

      Final quantity executed – 53,49,437.55 Cu.m.

      Balance quantity to be executed – 10,20,562.45 Cu.m.

      Working rate           - Rs. 17.00 per Cu.m.

      20% of working rate       Rs. 3.40 per Cu.m.

      Payable penalty for not executing

            Upto 130% quantity    Rs. 34,69,911.00


      These penalties may be imposed individually or collectively  depending
on the decision taken by the Management.  The imposition of penalty  may  be
decided on the background that the contractor working at  a  very  low  rate
has executed 108.47% in spite of incurring heavy losses  and  withdrew  only
when the new contract was  finished  ensuring  that  there  is  no  loss  of
production.



                                                            Yours faithfully

                                                              Sd/- Illegible

                                                        General Manager (TC)


Encl : As above”


11.   The Board of the appellants in its  78th  Meeting  decided  to  impose
penalty for non-execution of the balance contract work  by  the  respondents
and  including  the  financial  loss  incurred  by  the  appellants  due  to
allocation of that work to third party at higher  rate.  In  terms  of  that
decision, an approval order for  recovery  of  penalty  was  issued  by  the
appellants on 3rd November 2005 which reads thus:

                                                               “ANNEXURE -19


MAHANADI COALFIELDS LIMITED

(A subsidiary of Coal India Limited)

P.O. – Jagriti Vihar

Burla – 768018

Distt: Sambalpur-768020 (Orissa)

Gram : SAMBCOAL,:      Fax : (0663) 2542770

Phone : PBX :- 2542461 to 2542470


Ref: No. MCL/SBP/GM(TC)/2005/1100       Date: 03.11.2005


                               APPROVAL ORDER


Sub:  Imposition of penalty to M/s Dhansar Engineering  Company  Pvt.  Ltd.,
under NIT-276 (Dt; 01.12.2002) for the work of “Extraction and  Transfer  of
Coal/Coal Measure Strata by deploying “Surface Miners” on  hiring  basis  at
lakhanpur OCP, Lakhanpur Area.


            On recommendation of the  committee  to  examine  the  issue  on
imposition of penalty under NIT  –  276  dated  02.12.2002  to  M/s  Dhansar
Engineering Company Pvt. Ltd., for the work of “Extraction and  Transfer  of
Coal/Coal Measure Strata by deploying “Surface Miners” on  hiring  basis  at
Lakhanpur  OCP,  Lakhanpur  Area,  the  same  has  been   agreed   by   D(T)
/D(F)/D(P)/CMD/MCL.  The MCL Board in its 78th meeting  held  on  27.10.2005
under item  No.  78.C/20  has  been  pleased  to  approve  the  proposal  of
imposition of penalty in terms of provision of the contract to M/s.  Dhansar
Engineering Company Pvt. Ltd. By non performance of 130% of total  contacted
under NIT -276 (dt: 02.12.2002) for an amount of Rs. 1,57,40,655.22  (Rupees
One Crore Fifty-seven Lakh Forty Thousand Six Hundred Fifty-five  and  paisa
Twenty-two  only)  under  the  Clause  –  30.1  (loss   or  damage)  of  the
agreement.


                                                   Sd/- General Manager (TC)


Distribution:

GM Lakhanpur Area

CGM(F) MCL, HQ

TS to CMD, MCL

TS to D(T), MCL

Secy. To D(F), MCL

Sanction Order file”


12.   Aggrieved, the respondents filed Writ Petition under  Article  226  of
the Constitution of India and prayed as follows:

                                   “PRAYER


In the  circumstances,  it  is  therefore  prayed  that  Your  Lordships  be
graciously pleased to issue a Rule NISI in the nature of certiorari  calling
upon the Opposite Parties, to show cause as why the  impugned  letter  dated
08.12.2004 vide Annexure-22 issued by the  General  Manager  (TC),  Mahanadi
Coal Fields Limited, Opposite party  No.2  imposing  penalty  shall  not  be
quashed and if the Opposite Parties fail to show cause or show  insufficient
cause make the said Rule absolute.


                                     AND


Issue a Writ in the nature of mandamus directing  the  Opposite  parties  to
pay  a sum of Rs. 79,01,434.60 to the Petitioner  No.1  Company,  which  has
been illegally withholding by the Opposite parties.

                                     AND

      Issue a Writ in the nature of Mandamus directing the Opposite  Parties
to pay interest @ 18% per annum  as  the  Opposite  Parties  have  illegally
withhold the  outstanding  dues  of  Rs.  79,01,434.60  of  Petitioner  No.1
Company since 15.07.2004.

                                     AND

      Issue such other  Writ/Writs,  Order/Orders,  Direction/Directions  as
this Hon’ble Court may deem it fit and proper.


And for this act of Kindness the Petitioner shall  as  in  duty  bound  ever
pray.”



13.   The Writ Petition was  opposed  by  the  appellants  by  filing  reply
affidavit.   The  appellants  raised   preliminary   objection   about   the
maintainability of the Writ Petition. On  merits,  the  appellants  asserted
that the demand raised against the respondents was in accord with the  terms
and conditions of the contract and if the respondents were aggrieved by  the
same they were free to resort to the procedure for settlement  under  clause
31 of the agreement. The Division Bench of the High Court, however,  allowed
the Writ Petition preferred by the respondents on the finding  that  it  was
not permissible for the appellants to allot extra work  to  the  respondents
at the fag end of the contract period in terms of clause 5 of  the  contract
which envisaged giving 45 clear days notice for variation  of  the  quantity
under the contract. That notice was given to the respondents  only  on  11th
June 2004 even though the extended contract period was  to  expire  on  15th
July 2004. The Court held that, surprisingly after  extending  the  contract
period on 5th June 2004, within six days on 11th June  2004  the  appellants
decided to enhance the contract quantity by 30%. That  was  not  a  bonafide
act and was unacceptable. The Court also held that the  appellants  had  not
offered any explanation as to  in  what  circumstances  decision  to  impose
penalty was taken by the Board of Directors. The Court  further  noted  that
the respondents had executed the contract upto 108.47% at a very  low  rate,
and incurred heavy losses in  that  regard.  Further,  a  new  contract  for
Lakhanpur OCP was already awarded  and  there  was  no  loss  of  production
caused to the appellants. On these basis, the  Division  Bench  allowed  the
Writ Petition in the following terms:


“16.  Accordingly, the letter dated 8.12.2004 of the General  Manager  (T.C)
Mahanadi Coalfields Limited under Annexure-22 proposing  to  levy  shortfall
penalty as well as, its Approval Order dated 03.11.2005 under Annexure-A  to
the counter affidavit are hereby quashed.  The outstanding dues  payable  to
the petitioner be released in its favour within the period  of  thirty  days
along with simple interest @ 8% per annum to be computed from  the  date  of
conclusion of contract, i.e. from 16.7.2004.  The bank  guarantee  furnished
by the petitioners, pursuant to the direction of this Court dated  28.7.2009
are hereby directed to be  cancelled and  consequently,  directed  that  the
same be returned to the petitioners forthwith.

      The writ petition is allowed with the aforesaid terms.  No Costs.”


14.   Aggrieved, the appellants have filed the present  appeal.  This  Court
passed an interim order on 12th April, 2013, directing  to  maintain  status
quo as it existed on that date until further orders.

15.   According to the appellants the  High  Court  has  committed  manifest
error in entertaining the Writ Petition. Firstly,  in respect  of  a  purely
contractual matter and moreso when efficacious remedy  under  clause  31  of
the contract was  available  to  the  respondents  for  redressal  of  their
grievance.   Secondly,  on  merits  the  High  Court  has  misconstrued  and
misapplied  the  contractual  terms  and  in  particular  clause  5  of  the
contract. However, if the terms and  conditions of the contract are read  as
a whole,  it  leaves  no  manner  of  doubt  that  the  appellants  had  the
discretion to extend the original contract period; and  having  done  so  at
the request of the respondents, the respondents were bound by the  terms  of
the contract till 15th July 2004. Further, before that date at any point  of
time, it was open to the appellants  to  reduce  or  increase  the  contract
quantity upto 30%. The sole plea of the respondents for their  inability  to
perform the contract was founded on financial difficulty and  sufferance  of
further loss due to low contract rate. That  can  be  no  consideration  for
walking out of the contract. Moreso, after the extra quantity was  allocated
the respondents could have asked for further time for completing  the  extra
work, if they were not in  a  position  to  complete  the  same  within  the
contract period. That request could have been considered by  the  appellants
appropriately. The respondents did not do  so.  Instead,  they  insisted  to
withdraw from  operation  merely  because  the  rate  of  contract  was  not
affordable to them. Resultantly, the  appellants  had  to  allot  the  extra
quantity of unfinished work by the respondents, to third party at  a  higher
rate. The fact that the appellants did not suffer any  loss  of  production,
it does not follow that no financial loss was  suffered  by  the  appellants
due to higher rate paid for the unfinished extra work. The appellants  were,
therefore, justified in recovering the difference  of  rate  in  respect  of
unfinished extra work and penalty therefor. That  was  a  legitimate  demand
under the terms and conditions of the contract between the parties.

16.   The respondents, on the other hand, contend that it was unfair on  the
part of the appellants not to allow the respondents to  close  the  contract
as per the original contract and within the extended  contract  period  i.e.
upto 15th July 2004. Further, the respondents cannot be made liable for  the
unfinished extra quantity of work as that was allotted  only  on  11th  June
2004, leaving very little time for the respondents to complete the same  for
which the appellants should blame themselves. According to the  respondents,
the High Court was right in concluding that clause 5 of  the  agreement  did
not permit the appellants to allot an extra quantity of work to  the  extent
of 30% at the fag end of the extended contract period, absent 45 clear  days
notice mandated therein. Further, the High Court  has  passed  an  equitable
order also keeping  in  mind  that  the  respondents  had  already  executed
108.47% of the contract work  by  suffering  heavy  losses,  which  fact  is
substantiated from the execution of new contract at  the  rate  of  Rs.31.50
per cubic meter as against the rate of Rs.17/- per cubic  meter  payable  to
the respondents.  It is also contended that the demand  for  penalty  amount
is unilateral and without any just cause.   The  same  is  illegal.   Hence,
contends the learned counsel, the appeal be dismissed.

17.   Having heard the learned counsel for the parties at  some  length,  we
find force in the  plea  of  the  appellants.  The  challenge  in  the  Writ
Petition filed by the respondents  was  limited  to  the  letter  dated  8th
December 2004,  issued  by  the  General  Manager  of  the  appellants.  The
respondents had not challenged the extension of contract  period  till  15th
July 2004 vide letter dated 5th June 2004, the decision  of  the  appellants
to allot an extra quantity of 30% work and much less  the  decision  of  the
Board to impose penalty taken on 27th October, 2005 and communicated to  the
respondents vide Approval Order dated 3rd November  2005.  The  High  Court,
however, has not only set aside the letter dated 8th December 2004 but  also
the Approval Order dated 3rd November 2005.

18.   For doing so, the High Court has taken support from clause  5  of  the
Contract. That clause cannot be read  in  isolation.  The  other  terms  and
conditions of the contract must  be  read  as  a  whole.  Clause  5  of  the
agreement dated 26th May 2003 posits authority in the appellants  to  reduce
or increase the tendered  quantity  by  +/–  30%,  whilst  the  contract  is
subsisting. Indisputably, the original contract period was upto 15th  April,
2004. At the instance of these respondents, the  same  stood  extended  till
15th July 2004.  The extra 30% work was allotted to the respondents on  11th
June 2004, before expiry of the extended  contract  period  i.e.  15th  July
2004. As the contract period was extended and that decision was  allowed  to
attain finality, it inevitably obliged the respondents to  fulfill  all  the
contractual stipulations under the original agreement including to  complete
the assigned quantity of work  -  be it original quantity or extra  quantity
- before 15th July 2004. The fact that they had  to  suffer  financial  loss
due to low contract rate could not be cited as an excuse to  extricate  from
that contractual obligation.

19.   Failure to comply with the contractual  obligation  of  executing  the
original quantity of work or the extra work, as the case may be, must  visit
the respondents with liability to compensate  the  appellants  in  terms  of
other express clauses of the contract to the extent of unfinished  work  and
in particular the financial loss suffered by the appellants for getting  the
same work executed through a third agency at a higher rate.  The  fact  that
the respondents executed 108.47% of work before 15th July 2004, could be  no
justification  to  relieve  them  of  their  obligation  to  compensate  the
appellants with suitable amount for the unfinished  contract  work  (out  of
130%).

20.    Presumably to get over this  position,  the  respondents  relying  on
clause 5 of the agreement would contend that  the  extra  quantity  of  work
could not be allotted to them, absent 45 clear days notice that too  at  the
fag end of the contract  period.   This  argument,  in  our  opinion,  is  a
complete misreading of the said clause.  It is one thing  to  say  that  the
contractor should be given  sufficient  time  to  complete  the  extra  work
commensurate with the  extra  quantity  required  to  be  executed  by  him.
However, in law, it is not open to contend that  even  though  the  contract
period is still  subsisting,  the  principal  (appellants)  could  not  have
exercised its option  to  increase  the  quantity  of  work  to  the  extent
permissible under that clause, to be executed by the contractor  within  the
contract period.  The principal (appellants)  could  be  asked  to  exercise
their option to extend the  contract  period  beyond  15th  July,  2004,  to
enable the respondents to complete  the  unfinished  extra  work.   If  such
request  were  to  be  made  by  the  respondents,  there  would  have  been
corresponding obligation on the appellants  to  extend  the  contact  period
commensurate with the increased quantity of work in terms  of  clause  5  of
the agreement.  The respondents, instead, opted to walk out of the  contract
for the sole reason that the contract rate agreed by them was very  low  and
was causing financial loss to them.  That can  be  no  just  reason  to  not
fulfill their contractual obligation.

21.   Relying on the third sentence (last sentence)  in  clause  5,  it  was
contended that the employer could not have increased the  tendered  quantity
in absence of 45 clear days notice. We agree with the  appellants  that  the
said stipulation would come into play only  if  the  respondents  were  also
called upon to increase the machine  capacity  by  upto  30%  extra  “daily”
quantity. In the present case, the  appellants  merely  allotted  extra  30%
quantity without requiring the respondents to increase the  daily  quantity.
There is marked difference between increasing the extra quantity during  the
contract period and that of increasing the extra “daily”  quantity.  In  the
case of latter, the contractor would be required  to  step  up  the  machine
capacity for which giving of 45 clear  days  notice  to  him  is  necessary.
Suffice it to observe that the stipulation in the third sentence  of  clause
5 providing for  45  clear  days  notice  was  not  an  impediment  for  the
appellants to allot extra quantity of work upto  30%,  whilst  the  contract
period was subsisting.

22.   The respondents had then relied on the notings of the Project  Officer
dated 26th January 2005 to contend that  assigning  of  extra  work  to  the
respondents at the fag end of the contract period was doubted  even  by  the
said officer. The observations of the Project Officer cannot  be  the  basis
to construe the scope of Clause 5 of the contract. Besides, it was  only  an
inter-departmental communication which  was  duly  considered  at  different
level in the office of the appellants, but finally it  is  the  decision  of
the Board of Directors of the appellants that must prevail. As a  matter  of
fact, Clause 5 of the agreement  empowers  the  appellants  to  increase  or
reduce the quantity of work upto permissible limit whilst the  contract  was
subsisting.  That  power  having  been  exercised,  the  obligation  of  the
contractor to complete the extra work  in  terms  of  the  subject  contract
within the contract period or extended contract period was  imperative.  The
respondents are not right in contending that the appellants-Company  had  no
authority to grant extension of time  to  complete  the  enhanced  quantity.
This contention deserves to be stated to be rejected, keeping  in  mind  the
other contractual terms such as Clause 11.0 -  providing  for  variation  in
the scheduled quantity, extent and rate; Clause 13 - time for completion  of
contract and more particularly Clause  14.0  -  for  extension  of  date  of
completion. Clause 14.0 (e) was available and ought to have been invoked  by
the respondents in this situation. It postulates that for  any  other  cause
not specifically provided in sub-clauses (a) to (d) of the same  Clause,  at
the sole discretion of the appellants,  the  date  of  completion  could  be
extended, if it was found to be necessary because of  situation  beyond  the
control of the contractor. That clause could be invoked  for  the  situation
in which the respondents were placed due to extra work allocated to them  at
the fag end of the contract (extended) period.

23.   In our opinion, clause 5 did not prohibit the  principal  (appellants)
to allot upto extra 30% quantity of work, for  want  of  45  clear  days  of
subsisting contract period. Whereas, that option could be exercised  by  the
appellants at any time until the contract period was  subsisting,  which  in
this case was until 15th  July  2004.  In  the  present  case,  such  notice
regarding increase of work upto  30%  permissible  under  clause  5  of  the
agreement, was given on 11th June 2004. On  this  finding,  it  must  follow
that the respondents committed breach of their  contractual  obligation,  in
not completing the balance work out of 130% of work (i.e. 130  -   108.47%).
To that extent the respondents became liable to  compensate  the  appellants
including by way of penalty and in particular  towards  the  financial  loss
caused to the appellants due to assigning the unfinished  work  to  a  third
agency (contractor) at a higher rate. The amount demanded by the  appellants
includes the difference of contractual rate and the actual loss suffered  by
the appellants for completing the unfinished work  through  a  third  agency
(contractor) at a higher rate, as is noticed from  the  communication  dated
8th December 2004 sent to the respondents.

24.   The respondents, would  then  contend  that,  the  appellants  without
giving any opportunity to the respondents unilaterally imposed  penalty  and
despite the noting of  the  General  Manager  that  there  was  no  loss  of
production to the appellants.  Similarly,  a  doubt  was  expressed  by  the
Project Officer regarding giving extra work to the respondents  at  the  fag
end of the contract period.  The respondents have relied on the decision  of
this Court in Maula Bux vs. Union of India[1], in which  it  has  been  held
that “where a sum is named in the contract  in  the  nature  of  a  penalty,
where loss  in  terms  of  money  can  be  determined,  the  party  claiming
compensation  must  prove  the  loss  suffered  by  it.”  It  is,   however,
indisputable that financial loss was suffered by the appellants  on  account
of assigning the unfinished work to a third agency (contractor) at a  higher
rate.  In that, the contract rate for the  same  work  to  be  done  by  the
respondents would  have  been  at  Rs.  17/-  per  cubic  meter,  which  the
appellants were required to get it executed at the rate  of  Rs.  31.50  per
cubic meter through a third agency.  The fact that  no  loss  of  production
was suffered by the  appellants  cannot  relieve  the  respondents  of  that
liability.  It is a different matter that the respondents were  not  put  to
notice before the final decision was taken by the appellants to recover  the
financial loss along with penalty.  The respondents  could  have  approached
the appellants for reconsideration  of  their  demand  towards  penalty,  in
terms of Clause 30.3 of the contract; and persuade the appellants  to  waive
the penalty amount to be recovered from  them.   The  respondents,  however,
chose to straightway approach the  High  Court  by  way  of  Writ  Petition.
Notably, the High Court has not set aside the penalty amount  as  such,  but
the entire demand being impermissible.  Since we have reversed the  findings
and conclusion of the High Court and  even  if  this  appeal  succeeds,  the
respondents can be granted an opportunity to make a  representation  to  the
Appellants - company, who in turn can deal with the same in accordance  with
law.  If the appellants accept  the  claim  of  the  respondents  about  the
unjustness of penalty or quantum thereof, they would be free to withdraw  or
modify their claim for recovery of penalty amount, if  so  advised.  In  the
event, the appellants reject  the  representation,  they  will  be  free  to
recover the amount as demanded towards penalty along with  interest  accrued
thereon, as may be permissible in law.  However, that would not absolve  the
respondents from the financial liability arising due to difference  of  rate
of contract and the actual cost incurred by the appellants to  complete  the
unfinished work out of 130%  of  the  contract  quantity,  through  a  third
agency at a higher rate.  That can be recovered by the appellants  from  the
respondents along with interest accrued thereon at  such  rate,  as  may  be
permissible in law, even if the representation made by the  respondents  for
recall or modification of  the  penalty  amount  is  pending  consideration.
Considering the above, it is not necessary for us to  burden  this  judgment
with the contention of the respondents that the penalty imposed without  any
notice or hearing to the respondents is  vitiated;  as  also  the  decisions
relied in support  of  that  contention  in  the  case  of  Gorkha  Security
Services vs. Government (NCT  of  Delhi)  &  Ors.[2]  and  Kumari  Shrilekha
Vidyarthi & Ors vs. State of U.P. [3]

25.   Similarly, it is not necessary for us to  burden  this  judgment  with
the decisions relied on by the respondents, to  contend  that  existence  of
alternative remedy is no bar to entertain a Writ Petition under Article  226
of the Constitution of India, as held in the cases of  Popcorn  Enterainment
vs. City Development Corporation[4], Harbanslal Sahnia  &  Anr.  vs.  Indian
Oil  Corporation  Ltd.  &  Ors.[5],  Union  of  India  &  Ors.  vs.   Tantia
Construction Pvt. Ltd.[6], M.P. State Agro Industries Development  Corpn.  &
Anr. Vs. Jahan Khan[7] and Whirlpool  Corporation  vs.  Registrar  of  Trade
Marks,  Mumbai[8].   For,  we  have  already  examined  the  merits  of  the
controversy  and  more  so  granted  liberty  to  the  respondents  to  make
representation to the appellants on the question of justness of  the  demand
towards penalty or the quantum thereof.  It will be open to the  respondents
to pursue remedy in that behalf, as may be permissible in law.  We  are  not
expressing any opinion one way or the other on the issue of penalty  amount.
 All questions in that behalf are left open.

26.   Accordingly, we  partly  allow  this  appeal.   The  judgment  of  the
Division Bench dated 7th November 2012 is set aside.   The  reliefs  claimed
by the respondents in the Writ Petition are disposed of in the above  terms.

27.   The appeal is partly allowed in the above terms with no  order  as  to
costs.



                                                          ………………………………….CJI
                                                           (T.S. Thakur)


                                                           …………………………………..J.
                                                        (A.M.Khanwilkar)

New Delhi,
September 27, 2016


-----------------------
[1]   [2] (1969) 2 SCC 554
[3]         [4] (2014) 9 SCC 105

[5]         [6] (1991) 1 SCC 212

[7]   [8]          (2007) 9 SCC 593
[9]         [10] (2003) 2 SCC 107

[11]        [12] (2011)5 SCC 697

[13]  [14]          (2007) 10 SCC 88
[15]  [16]          (1998) 8 SCC 1