Supreme Court of India (Division Bench (DB)- Two Judge)

Appeal (Civil), 7184 of 2008, Judgment Date: Jun 29, 2016

                                                                  REPORTABLE
                        IN THE SUPREME COURT OF INDIA

                        CIVIL APPEALLATE JURISDICTION

                        CIVIL APPEAL NO. 7184 OF 2008


M/S. EMM ENN ASSOCIATES                                   … APPELLANT(S)


                                   VERSUS


COMMANDER WORKS ENGINEER                                … RESPONDENT(S)
& ORS

                                   WITH

                       CIVIL APPEAL NO. 7185 OF 2008


                               J U D G M E N T


ASHOK BHUSHAN, J.


These two appeals  raising  identical  questions  of  law  have  been  heard
together and are being decided by this common judgment.  For  deciding  both
the appeals, it shall be sufficient to  refer  to  facts  and  pleadings  in
Civil Appeal No. 7184 of 2008.  Appeal No.  7184  of  2008  has  been  filed
against judgment of  Chief  Justice  of  Punjab  &  Haryana  High  Court  in
Arbitration Case No. 184 of 2006 by which  judgment  learned  Chief  Justice
has dismissed the application, filed by appellant for referring the  dispute
to an arbitrator in exercise of power under Section 11  of  the  Arbitration
and Conciliation Act 1996 (hereinafter referred to as ‘Act’).

2.    Civil Appeal No.  7185  of  2008  has  also  been  filed  against  the
identical judgment of learned Chief Justice in Arbitration Case  No.  89  of
2006 by which the application filed  by  the  appellant  for  appointing  an
arbitrator has been dismissed.

3.    Brief facts giving rise to Appeal No. 7184 of  2008  now  need  to  be
noted.

       The  appellant  a  partnership  firm  was  allotted  a  contract   on
10.11.1998 for providing additional  security  fencing  at  Mullanpur.   The
work was completed on 10.7.2000. Work  completion  certificate  was  issued.
Final bill was prepared on 20.2.2001 and the payment of final bill was  made
to the petitioner on 10.04.2001. Payment  of  the  undisputed  part  of  the
final bill was made by cheque dated 10.04.2001.

4.    Although Clause 67 of general conditions of contract contemplated  for
recovery from contractor in several contingencies one of which  as  referred
in sub-Clause (f) was that if  as  a  result  of  any  audit  and  technical
examination, any over payment is discovered in respect of  work  done  under
this contract, the contractor shall on demand make payment of  a  sum  equal
to the amount of over-payment. Sub-Clause  (g)  further  provided  that  the
Government shall not be  entitled  to  recover  any  over-payment  beyond  a
period of two years from the date of payment of the  undisputed  portion  of
the final bill.

5.    Even though, two years period expired after payment of final bill,  no
demand for any recovery was issued by the Government.  Contractor by  letter
dated 23.02.2005 served a notice stating that  final  bill  amount  as  paid
during April, 2001 did not include the payments due  to  contractor  against
several items which were claimed as per appendix A annexed to the notice.

6.    It was further stated that the decision be communicated within  thirty
days failing which it shall be  assumed  that  the  claim  is  disputed  and
contractor shall be left with no remedy except to seek  adjudication  by  an
arbitrator appointed in terms of the contract.

7.    The Garrison Engineer issued a letter dated 22.03.2005 informing  that
contractor had signed the final bill without any protest and had  given  ‘No
Further Claim’ certificate.  Hence no arbitrable dispute exists.  The  claim
now intimated after the lapse of a period of approx four years  is  baseless
and hence denied.

8.    A letter dated 24.03.2005 was written by the contractor to  the  chief
engineer in  reference  to  notice  dated  23.02.2005  with  a  prayer  that
arbitrator under condition 70 of the Contract may  kindly  be  appointed  to
adjudicate the dispute.   The  appellant  thereafter  filed  an  application
under Section 11 of the Arbitration Act before District  Judge,  Ropar.  The
application was ultimately taken by Chief Justice of the High Court  and  by
an order dated 12.03.2007, the application  was  rejected  taking  the  view
that appellant’s claim is not a live  claim.  Aggrieved  against  the  above
judgment dated 12.03.2007 in Arbitration Case No. 184 of  2006,  Appeal  No.
7184 of 2008 has been filed.

9.    Arbitration Case No. 89 of 2006 has also been filed by  the  appellant
seeking appointment of an arbitrator under Section 11  of  the  Act  in  the
said case and also the work was completed on 23.09.2000 and the  final  bill
was paid on 10.04.2001. Notice along with list of  claim  was  sent  by  the
appellant on 23.02.2005 i.e. on the same  day  when  notice  in  Arbitration
Case No. 184 of 2006 has been sent.

10.    Hon’ble  Chief  Justice  giving  the  same   reasons   rejected   the
application in Arbitration Case No. 89 of 2006 holding that the  claim  made
by the appellant is not a live claim.  Hon’ble Chief Justice by order  dated
12.03.2007 took the view that final bill has been paid  on  10.04.2001,  the
notice having been given only on 23.02.2005 the  period  of  limitation  was
over.  With regard to the Clause 67 of the contract, it was observed by  the
Chief Justice that Embargo of two years as per sub-Clause  (f)  and  (g)  is
with regard to the right of the Government for effecting recovery  from  the
contractor which clause does not extend the period of limitation  in  favour
of the contractor.

11.   Shri O. P. Gupta, the partner of the appellant firm has  appeared  in-
person and made his submission. We  have  also  heard  the  learned  counsel
appearing for the respondents.

12.   The appellant’s case is that the claim raised by contractor by  notice
dated 23.02.2005, was not barred by time and was a live  claim  which  ought
not to have been rejected by the Chief Justice  in  exercise  of  his  power
under Section 11 of the Act.  It is contended that the issues as to  whether
the claim is barred by time are the issues which ought  to  have  been  left
for decision of arbitrator.  It is contended that payment in respect to  the
final bill made  on  10.04.2001,  was  payment  with  regard  to  undisputed
amount.  Apart from  undisputed  amount  there  were  other  claims  of  the
contractor and the ‘No Liability’ certificate given  by  the  appellant  was
only with regard to undisputed claim.  Payment made on  10.04.2001  was  the
payment only in  reference  to  undisputed  claim  and  that  in  no  manner
precluded the appellant from raising claim.

13.   As per Clause 67 of the contract,  there  was  two  years  period  for
effecting any recovery from the contractor and when  no  claim  against  the
contractor was raised during the  aforesaid  period,  the  appellant  raised
the claim for disputed amount which was not paid.  The period of  two  years
is defect liability period and it was clearly  open  for  the  appellant  to
raise the claim for disputed amount after expiry of the aforesaid period  of
two years.

14.   The respondents never adjudicated the disputed part of the final  bill
and after serving notice the appellant had rightly sought  for  adjudication
by an arbitrator which  application  has  been  rejected  by  Hon’ble  Chief
Justice not on valid considerations.

15.   Learned counsel appearing for the respondents supported  the  judgment
of  the  Chief  Justice  and  contends  that  for  filing  any   application
limitation is three years as per Article 137 of the  Limitation  Act,  1963.
Final bill had been paid on 10.04.2001, any application  for  any  claim  in
respect to final bill ought to have been raised within three  years.  It  is
contended that the respondents have raised  the  preliminary  objections  in
reply objecting the application for  arbitration  filed  by  the  appellant,
which has rightly been rejected by the Chief Justice.

16.   We have considered the  submissions  of  both  the  parties  and  have
perused the record,  what  is  the  nature  of  jurisdiction  of  the  Chief
Justice while deciding an application  under  Section  11  of  the  Act  has
elaborately been considered by Seven Judge Bench of this court in SBP &  CO.
versus Patel Engineering Ltd and another (2005) 8 SCC 618.  In  para  47  of
the judgment, conclusions were recorded by the larger Bench.  Conclusion  IV
is relevant for the present case which is quoted as below:

“47. We, therefore, sum up our conclusions as follows:

 (iv) The Chief Justice or the designated  Judge  will  have  the  right  to
decide the preliminary aspects as indicated in  the  earlier  part  of  this
judgment. These will be his own jurisdiction to entertain the  request,  the
existence of a valid arbitration agreement, the existence or otherwise of  a
live claim, the existence of the condition for the  exercise  of  his  power
and on the qualifications  of  the  arbitrator  or  arbitrators.  The  Chief
Justice or the designated Judge would be entitled to seek the opinion of  an
institution in the matter of nominating an arbitrator qualified in terms  of
Section 11(8) of the Act if the need arises but  the  order  appointing  the
arbitrator could only be  that  of  the  Chief  Justice  or  the  designated
Judge.”

17.   The Chief Justice exercises the judicial power while passing an  order
under Section 11 of the Act thus can examine the question as to whether  the
claim  which  has  been  raised  before  him  survives  and  needs   to   be
adjudicated.  It goes without saying that if Chief Justice finds that  claim
is a dead claim, he can exercise jurisdiction in rejecting the  application.

18.   A two Judge Bench of this court had occasion to  consider  what  is  a
‘live claim’ within the meaning of Section 11 of the  Act.  Elaborating  the
jurisdiction of the Chief Justice, under Section 11  of  the  Act  following
was laid down by this court in para 14 of the judgment:

“14. Normally, when a power is conferred on the highest  judicial  authority
who normally performs judicial functions and is the head  of  the  judiciary
of the State or of the country, it is difficult to assume that the power  is
conferred on the Chief Justice as persona designata.  Under  Section  11(6),
the Chief Justice is given a power  to  designate  another  to  perform  the
functions under that provision. That power has generally been designated  to
a Judge of the High Court or of  the  Supreme  Court  respectively.  Persona
designata, according to Black’s Law Dictionary, means “a  person  considered
as an individual rather than as a member of a  class”.  When  the  power  is
conferred on the Chief Justices of the High Courts, the power  is  conferred
on a class and not considering that person  as  an  individual.  In  Central
Talkies Ltd. v. Dwarka Prasad while considering  the  status  in  which  the
power was to be exercised  by  the  District  Magistrate  under  the  United
Provinces (Temporary) Control of Rent and  Eviction  Act,  1947  this  Court
held: (SCR pp. 500-01)

“A persona designata is ‘a person who is pointed  out  or  described  as  an
individual, as opposed to a person ascertained as a member of  a  class,  or
as filling a particular character’. (See Osborne’s Concise  Law  Dictionary,
4th Edn., p. 253.) In the words of Schwabe,  C.J.,  in  Kokku  Parthasaradhi
Naidu Garu v. Chintlachervu Koteswara Rao Garu4,  personae  designatae  are,
‘persons selected to  act  in  their  private  capacity  and  not  in  their
capacity as Judges’. The same consideration applies  also  to  a  well-known
officer like the District Magistrate named by  virtue  of  his  office,  and
whose powers the Additional District Magistrate can also  exercise  and  who
can create other officers equal to himself for the purposes of the  Eviction
Act.”

In Mukri Gopalan v. Cheppilat  Puthanpurayil  Aboobacker  this  Court  after
quoting the above passage  from  Central  Talkies  Ltd.  v.  Dwarka  Prasad3
applied the test to come to the conclusion  that  when  Section  18  of  the
Kerala  Buildings  (Lease  and  Rent  Control)  Act,  1965  constituted  the
District Judge as an Appellate Authority under  that  Act,  it  was  a  case
where  the  authority  was  being  conferred  on  the  District  Judges  who
constituted a class and, therefore, the Appellate  Authority  could  not  be
considered to be persona designata. What can be gathered from  P.  Ramanatha
Aiyar’s Advanced Law Lexicon, 3rd Edn., 2005, is  that  “persona  designata”
is a person selected to act in his private capacity and not in his  capacity
as a judge. He is a person pointed out or  described  as  an  individual  as
opposed to a person ascertained as a member of  a  class  or  as  filling  a
particular character. It is also seen that one of the tests  to  be  applied
is to see whether the person concerned could  exercise  the  power  only  so
long as he holds office or  could  exercise  the  power  even  subsequently.
Obviously, on ceasing to be a Chief  Justice,  the  person  referred  to  in
Section 11(6) of the Act could not exercise the power.  Thus,  it  is  clear
that the power is conferred on the Chief Justice under Section 11(6) of  the
Act not as persona designata.”

19.   Further this court has observed that an application under  Section  11
of the Act is expected to contain pleading about the existence of a  dispute
and the applicant is not expected to justify the claim or plead  extensively
in regard to limitation or production of document to demonstrate that  claim
is within time  in  proceeding  under  Section  11  and  that  issue  should
normally be left to the Arbitral Tribunal. Following was  observed  in  para
15:

15. Normally a persona designata  cannot  delegate  his  power  to  another.
Here, the Chief Justice of the High Court or the Chief Justice of  India  is
given the power to designate another to exercise the power conferred on  him
under Section 11(6) of the Act. If the power is  a  judicial  power,  it  is
obvious that the power could be conferred only on a judicial  authority  and
in this case, logically on another Judge of the High Court or on a Judge  of
the Supreme Court. It is logical to consider the conferment of the power  on
the Chief Justice of the High Court and on the Chief  Justice  of  India  as
Presiding Judges of the High Court and the Supreme Court  and  the  exercise
of the power so  conferred,  is  exercise  of  judicial  power/authority  as
Presiding Judges of the respective courts. Replacing of the word “court”  in
the Model Law with the expression “Chief Justice” in the Act, appears to  be
more for excluding the exercise of power by the District Court  and  by  the
court as an entity leading to obvious consequences  in  the  matter  of  the
procedure to be followed and the rights of appeal governing the matter.  The
departure from Article 11 of the Model Law and the  use  of  the  expression
“Chief Justice” cannot be taken to  exclude  the  theory  of  its  being  an
adjudication under Section 11 of the Act by a judicial authority.

20.   From the above, it is clear that Chief Justice may  chose  to  hold  a
claim as a dead claim only when the claim is  evidently  and  patently  long
time barred claim and there is no need for  any  detailed  consideration  of
evidence. An illustration have been given in para  14  as  extracted  above.
The above illustration becomes relevant for the facts of the  present  case.
In the present case also, the appellant has  raised  the  claim  beyond  the
three years of completing of the work but within five  years  of  completion
of the work.
21.   In the present case, the appellant has also contended that there is  a
defect liability period of two years during which any recovery can  be  made
from the contractor.  Further the categorical  case  of  the  appellant  was
that final  payment  made  at  10.04.2001  was  the  final  payment  of  the
undisputed claim and there were other claims of  the  appellant  which  were
disputed  and  the  payment  received  on  10.4.2001  was  with  regard   to
undisputed claim. There being no adjudication with regard to disputed  claim
the claim raised by notice dated 23.02.2005 cannot be said to be  barred  by
time or a dead claim.
22.   In the present appeal by IA No. 03 of 2012, the appellant has  brought
certain additional materials for consideration of the  Court.   By  annexure
16 certain certificates which were given by  the  contractor  on  20.02.2001
that is when the final bill was prepared, has been brought on  record.   The
payment was made by cheque dated 10.04.2001 and para 3/4 of the  certificate
filed at the 2nd page of the annexure 16 states as follows:

“3. Printed Certificate signed by the petitioner at the  time  of  receiving
payment of the undisputed part of the Final Bill.

Received Rs. 57532/-. This payment is in full and final  settlement  of  all
money due under C WE/AF CHD / CHD-5/98-99 and I have  no  further  claim  in
respect of the  ………………..
Sd/- Contractor”

“4.   Payment by Cheque of the undisputed part of the  Final  Bill  made  by
the dispersing officer, mentioned-herein-below:-

Cheque No. H – 916930 dated 10.4.2001 for Rs. 57532/- issued  in  favour  of
M/s Emm Enn Associates on SBI AF Chandigarh Treasury.
                                  Sd/-
Signature of Dispersing Office ”

23.   Para 04 of the above certificate  as  quoted  above  clearly  mentions
payment by cheque of the  undisputed  part  of  the  final  bill  and  above
certificate also clearly indicates that payment on 10.04.2001  was  made  of
the undisputed part of the final  bill  which  presupposes  that  there  are
certain other claims which are disputed.  Clause 67 of the contract  entered
between the parties also uses expressions “undisputed portion of  the  Final
Bill”
24.   Appellant had relied on Clause 67 which contains a  heading  “Recovery
From Contractor” under sub-Clause (f) and (g)  which  is  to  the  following
effect:

(f) If, as a result of such  audit  and  technical  examination,  any  over-
payment is discovered in respect of the work done under this  Contract,  the
contractor shall on demand make payment of a sum  equal  to  the  amount  of
over-payment or agree for effecting necessary adjustment  from  any  amounts
due to him by Government.  If however, he refuses or neglects  to  make  the
payment on demand or does  not  agree  for  effecting  adjustment  from  any
amounts due to him, Government shall be entitled to take action as  in  sub-
para (a)  hereinbefore.   If  as  a  result  of  such  audit  and  technical
examination any under payment is discovered, the  amount  of  under  payment
shall be duly paid to the Contractor by Government.

(g) Provided,  that,  nothing  hereinbefore  contained  shall  entitled  the
Government to recover any  over-payment  in  respect  of  any  price  agreed
between the C.W.E or the G.E. and the  Contractor  under  the  circumstances
specifically prescribed for such method of  assessment  and  that  the  said
right of the Government to adjust over-payment from any sum due or from  any
sum which may become due to the  Contractor  or  from  Security  Deposit  or
Security Bond amount and adjust under payment, shall  not  extend  beyond  a
period of two years from the date of payment of the  undisputed  portion  of
the Final Bill or in the case of minus Bill, from the date, the  net  amount
of the final bill is communicated to the Contractor. “

 25.  In sub-Clause (g) the period of two years under which  the  Government
is entitled to make recovery is “from the date of payment of the  undisputed
portion of the final bill”. The  examination  of  the  additional  materials
brought on this appeal, does indicate that the case  required  consideration
of relevant bills and certificates and determination on the question  as  to
whether the claim laid by appellant was a dead claim  and  was  not  a  live
claim depended upon scrutiny of relevant documents.  The  pleadings  in  the
proceeding under Section 11 by the appellant  were  clearly  to  the  effect
that on 10.04.2001, he was paid only undisputed part and the  appellant  has
reserved his right to raise claim to the disputed part.

26.   In view of the Division Bench judgment in Indian Oil Corporation  Ltd.
supra para 14 as extracted above, the present was the case  which  ought  to
have been  left  for  the  decision  by  the  Tribunal.  We,  however,  have
proceeded further to examine the  claim  raised  by  the  appellant  in  his
notice dated 23.02.2005.  The pleadings of the appellant are categorical  to
the effect that the final payment made on 10.04.2001 was  only  with  regard
to undisputed portion and he has reserved his  right  to  raise  claim  with
regard to other disputed claims.

27.   The disputed claims having never been adjudicated, we are of the  view
that there was a dispute which needed an  adjudication  after  looking  into
all relevant  documents,  bills  and  certificates  which  could  have  been
appropriately examined by Arbitral  Tribunal  and  the  observation  of  the
Chief Justice “As the appellant has failed to prima facie  show  this  court
that there was a live claim of the appellant” does not commend us.

28.   The claim raised by petitioner in the facts  of  the  case  could  not
have been said to be a dead claim. Especially  in  view  of  the  additional
documents which have been placed before us by IA No.  03  of  2012.  We  are
thus of the view that the order dated 12.03.2007 passed in Arbitration  Case
No. 184 of 2006 and 89 of 2006 deserves to be set-aside.

29.   As a consequence thereof, the application made by the appellant  under
Section 11 of the Act is allowed.  We,  however,  consider  it  apposite  to
remit the case to the High Court (designated Judge)  to  pass  consequential
orders for appointment of the arbitrator for  deciding  the  disputes  which
have arisen between the parties. The appointment of the  arbitrator  may  be
made in the first instance with the consent of the parties and if,  for  any
reason, it is not possible  to  do  so  then  the  Court  will  appoint  the
arbitrator in its discretion. It be done within one month from the  date  of
the parties appearance.

30.   Parties to appear before the designated Judge in  the  High  Court  on
25.07.2016 to enable the Court to pass appropriate  consequential  order  as
directed above.  Both the appeals are accordingly allowed.

                                      ………………….…...........................J.
                                              (ABHAY MANOHAR SAPRE)

                                      ………………..…...........................J.
                                                 (ASHOK BHUSHAN)
NEW DELHI,
JUNE 29, 2016.





For the Latest Updates Join Now