Supreme Court of India (Division Bench (DB)- Two Judge)

Appeal (Civil), 610 of 2015, Judgment Date: Mar 10, 2015

                        IN THE SUPREME COURT OF INDIA

                        CIVIL APPELLATE JURISDICTION

                         CIVIL APPEAL NO. 610   2015
                  [Arising out of SLP(C) NO. 36643 OF 2014]



      Harmony Innovation Shipping Ltd.                      ... Appellant

                                      Versus

      Gupta Coal India Ltd. & Anr.                         ...Respondents



                               J U D G M E N T



      Dipak Misra, J.
           The issue that has emanated for consideration in this appeal  is
      whether in the obtaining factual matrix, especially regard  being  had
      to the nature of the arbitration clause, the High Court  is  justified
      in setting aside the order passed by the learned  Additional  District
      Judge, Ernakulam on 25.9.2014 in I.A. No. 4345 of 2014 in  O.P.  (ARB)
      No.  802/2014  directing  the  first  respondent  therein  to  furnish
      security for US$ 11,15,400  or  its  equivalent  (approximate)  Indian
      Rupees 6,60,00,000/- or to show cause on or before 01.10.2014, and  as
      an interim measure conditionally attaching the cargo belonging to  the
      first respondent herein, while dealing with an application moved under
      Section 9 of the Arbitration and Conciliation Act, 1996 (for  brevity,
      "the Act"), on the foundation that Section 9 of the Act is limited  to
      the applications to arbitration that takes place in India and  has  no
      applicability to arbitration which takes place outside India  in  view
      of the pronouncement in  Bharat  Aluminium  Co.  v.  Kaiser  Aluminium
      Technical Services Inc.[1] inasmuch as clause 5 of the contract  which
      is the arbitration clause clearly spells out that the contract  is  to
      be governed and construed according to English law and if the  dispute
      of the claim does not exceed USD 50,000,  the  arbitration  should  be
      conducted in accordance with small  claims  procedure  of  the  London
      Maritime Arbitration Association.
      2.    Regard being had to the lis in question,  suffice  it  to  state
      that an agreement was entered into between the parties  on  20.10.2010
      in respect of 24 voyages of coal shipment belonging to the  appellant,
      the first respondent before the High Court, from Indonesia  to  India.
      The respondent no. 1 herein, Gupta Coal India Ltd., undertook only  15
      voyages and that resulted in disputes which ultimately stood  referred
      to arbitration.  Be it noted, an addendum to contract was executed  as
      regards the remaining voyages  on  3.4.2013  when  disputes  arose  in
      respect of the principal/main agreement.  As the facts  would  undrape
      arbitration proceedings were initiated and  eventually  an  award  was
      passed.
      3.    After the award came into existence, the present appellant filed
      an application under Section 9 before the  District  Court,  Ernakulam
      for its enforcement under Sections 9/47 and 49 of  the  Act.   As  the
      factual narration would further uncurtain in respect of  the  addendum
      to contract, when disputes arose relating  to  the  same,  arbitration
      proceedings were initiated and at that juncture, the  appellant  moved
      the learned 2nd Additional District Court, Ernakulam under  Section  9
      of the Act seeking attachment of the cargos as an interim  relief  and
      the learned Additional District Judge, as  has  been  stated  earlier,
      issued conditional order of attachment.
      4.    The order passed by the learned Additional District Judge,   was
      assailed before the High Court in a Writ Petition, O.P.(C) No. 2612 of
      2014 raising a singular contention that the impugned order therein was
      absolutely without jurisdiction and hence, unsustainable in law.
      5.    A counter affidavit was filed contending, inter alia,  that  the
      application  before  the  learned  Additional   District   Judge   was
      maintainable inasmuch as the contract between the parties was  entered
      into prior to the  decision  in  Bharat  Aluminium  Co.  (supra)  and,
      therefore, the principle laid  down  in  the  said  decision  was  not
      attracted to the facts of the case, and in fact, it  was  governed  by
      the principles stated in Bhatia International v. Bulk Trading S.A[2].
      6.    The High Court,  after  hearing  the  learned  counsel  for  the
      parties, referred  to  main  agreement,  Exhibit  P-1,  the  addendum,
      Exhibit P-2, and the arbitration clause  in  the  main  agreement  and
      considered the decisions in Bhatia International (supra)  and  Venture
      Global Engg. v. Satyam Computer Services Ltd.[3],  some  decisions  of
      the High Court, reproduced a passage from Russell on  Arbitration  and
      eventually came to hold as follows:
           "The contention that since Ext.P1 was entered  into  before  the
           judgment in  Bharat  Aluminium  Co.'s  case  and  therefore  the
           principles laid down in the said decision is not  applicable  to
           the facts of the case cannot be countenanced.  The law laid down
           by  the  Supreme  Court  in  Bharat  Aluminium  Co.'s  case   is
           declaratory in  nature  and,  therefore,  the  first  respondent
           cannot be heard to say that he is not bound by the same and that
           the said principle cannot be applied to the case  on  hand.   In
           the case of a declaration, it is supposed to have been  the  law
           always and  one  cannot  be  heard  to  say  that  it  has  only
           prospective effect.  It is deemed to have been the  law  at  all
           times.  If that be so, the petition before the  court  below  is
           not maintainable and is only to be dismissed."

      7.    At the very outset, it is necessary to clear the maze as regards
      the understanding of the ratio in Bharat Aluminium Co. (supra) by  the
      High Court.  In the said case,  the  Constitution  Bench  has  clearly
      ruled thus:
           "197. The judgment in Bhatia International was rendered by  this
           Court on 13-3-2002. Since then, the aforesaid judgment has  been
           followed by all the High Courts as well  as  by  this  Court  on
           numerous occasions. In fact,  the  judgment  in  Venture  Global
           Engg. has been rendered on 10-1-2008 in terms of  the  ratio  of
           the decision in Bhatia  International.  Thus,  in  order  to  do
           complete justice, we hereby order, that the law now declared  by
           this Court shall apply prospectively,  to  all  the  arbitration
           agreements executed hereafter."

            The aforesaid judgment by the Constitution Bench was decided  on
      September 6, 2012.  In the instant case, the arbitration agreement was
      executed prior to that date and the addendum,  as  mentioned  earlier,
      came into existence afterwards.  Therefore, there can be no  scintilla
      of doubt that the authority in Bharat Aluminium Co. case would not  be
      applicable for determination of the controversy in hand.  In fact, the
      pronouncement in Bhatia International (supra) would be  applicable  to
      the facts of the present case inasmuch as  there  is  nothing  in  the
      addendum to suggest any arbitration and, in fact, it is controlled and
      governed by the conditions postulated in the principal  contract.   We
      shall advert to this aspect slightly  more  specifically  at  a  later
      stage.
      8.    Keeping the  aforesaid  in  view,  it  is  necessary  to  keenly
      understand the decision in Bhatia International (supra).  In the  said
      case, the agreement entered into between  the  parties,  contained  an
      arbitration clause which provided that arbitration was to  be  as  per
      Rules of International Chambers of Commerce  (for  short,  "the  ICC).
      The parties had agreed that the arbitration was to be held  in  Paris,
      France.  The first respondent filed an application under Section 9  of
      the Act before the learned Additional  District  Judge,  Indore,  M.P.
      with an interim prayer.  A plea was raised by the appellant  that  the
      Indore Court had no jurisdiction and application was not maintainable.
       The said stand was repelled by the learned Additional District Judge,
      which found favour with the High Court.  Before  this  Court,  it  was
      urged on behalf of the appellant that Part I of the Act  only  applies
      to arbitration where the place of arbitration is in India, but if  the
      place of arbitration is not in India, then Part II of  the  Act  would
      apply.  On behalf of the respondent therein, it was urged that  unless
      the parties, by their agreement either expressly or impliedly  exclude
      its  provisions,  Part  I  would  also  apply  to  all   international
      commercial arbitrations including those that take place in India.  The
      three-Judge Bench came to hold thus:-
           "To conclude, we hold that the provisions of Part I would  apply
           to all arbitrations and to  all  proceedings  relating  thereto.
           Where such arbitration is held in India the provisions of Part I
           would compulsorily apply and parties are free to deviate only to
           the extent permitted by the derogable provisions of Part  I.  In
           cases of international commercial arbitrations held out of India
           provisions  of  Part  I  would  apply  unless  the  parties   by
           agreement, express  or  implied,  exclude  all  or  any  of  its
           provisions. In that case the laws or rules chosen by the parties
           would prevail. Any provision, in Part I, which is contrary to or
           excluded   by   that   law   or   rules   will    not    apply."
           [Emphasis supplied]

            After the said conclusion was recorded, the stand of the learned
      senior counsel for the appellant was put thus:-
           "Faced with this situation Mr Sen submits that, in this case the
           parties had agreed that the arbitration be as per the  Rules  of
           ICC. He submits that thus by  necessary  implication  Section  9
           would not apply. In our view, in such cases the  question  would
           be  whether  Section  9  gets  excluded  by  the  ICC  Rules  of
           Arbitration. Article 23 of the ICC Rules reads as follows:-
               Conservatory and interim measures
                 1.    Unless the parties have otherwise agreed, as soon  as
              the file has been transmitted to it,  the  Arbitral  Tribunal
              may, at the request of a party,  order  any  interim[pic]  or
              conservatory  measure  it  deems  appropriate.  The  Arbitral
              Tribunal may make the granting of any such measure subject to
              appropriate security being furnished by the requesting party.
              Any such measure shall take the  form  of  an  order,  giving
              reasons, or of an award, as the Arbitral  Tribunal  considers
              appropriate.
                 2. Before the file is transmitted to the Arbitral Tribunal,
              and in appropriate circumstances even thereafter, the parties
              may apply to any competent judicial authority for interim  or
              conservatory measures.  The  application  of  a  party  to  a
              judicial   authority   for   such   measures   or   for   the
              implementation of any such measures ordered  by  an  Arbitral
              Tribunal shall not be deemed  to  be  an  infringement  or  a
              waiver of the arbitration agreement and shall not affect  the
              relevant powers reserved to the Arbitral Tribunal.  Any  such
              application and any measures taken by the judicial  authority
              must be  notified  without  delay  to  the  Secretariat.  The
              Secretariat shall inform the Arbitral Tribunal thereof."

            After so stating, the Court referred to Article 23  of  the  ICC
      Rules and interpreted thus:-
           "Thus Article 23 of the ICC Rules permits parties to apply to  a
           competent  judicial  authority  for  interim  and   conservatory
           measures. Therefore, in such cases an application  can  be  made
           under Section 9 of the said Act."

      9.    The decision in Bhatia International  (supra)  was  followed  in
      Venture  Global  Engg.  (supra).   The  Court  scanned  the   ultimate
      conclusion recorded  in  Bhatia  International  (supra)  and  in  that
      context, referred to various paragraphs and came to hold as follows:-
           "32. The learned Senior Counsel for the respondent based on para
           26 submitted that in the case of foreign award which was  passed
           outside India is  not  enforceable  in  India  by  invoking  the
           provisions of the Act or CPC. However, after  critical  analysis
           of para 26, we are unable to accept the argument of the  learned
           Senior Counsel for the respondent. Paras  26  and  27  start  by
           dealing with the arguments of Mr Sen who argued that Part  I  is
           not applicable to foreign awards. It is  only  in  the  sentence
           starting at the bottom of para  26  that  the  phrase  "it  must
           immediately be clarified" that  the  finding  of  the  Court  is
           rendered. That finding is to  the  effect  that  an  express  or
           implied agreement of parties can exclude  the  applicability  of
           Part  I.  The  finding  specifically  states:  "But  if  not  so
           excluded, the provisions of  Part  I  will  also  apply  to  all
           'foreign awards'." This exception which is carved out, based  on
           agreement of the parties,  in  para  21  (placita  e  to  f)  is
           extracted below: (Bhatia International case SCC p. 119e to f)

                 "21. ... By omitting to provide that Part I will not  apply
                 to international commercial arbitrations which  take  place
                 outside India the effect would be that Part  I  would  also
                 apply to international commercial arbitrations held out  of
                 India.  But  by  not  specifically   providing   that   the
                 provisions of Part  I  apply  to  international  commercial
                 arbitrations held  out  of  India,  the  intention  of  the
                 legislature appears to be to ally (sic  allow)  parties  to
                 provide by agreement that Part I or any  provision  therein
                 will not apply. Thus in respect of arbitrations which  take
                 place outside India even the  non-derogable  provisions  of
                 Part I can be excluded. Such an agreement may be express or
                 implied."

           33. The very fact that the judgment holds that it would be  open
           to the parties to exclude the application of the  provisions  of
           Part  I  by  express  or  implied  agreement,  would  mean  that
           otherwise the whole of Part I would  apply.  In  any  event,  to
           apply Section 34 to foreign international awards  would  not  be
           inconsistent with Section 48 of the Act, or any other  provision
           of Part II as a situation may arise, where, even in  respect  of
           properties situate in India and where an award would be  invalid
           if opposed to the public policy of  India,  merely  because  the
           judgment-debtor  resides  abroad,  the  award  can  be  enforced
           against properties in India through personal compliance  of  the
           judgment-debtor and by holding out the threat of contempt as  is
           being sought to be done in the present case. In such  an  event,
           the judgment-debtor cannot [pic]be deprived of his  right  under
           Section 34 to invoke the public policy of India,  to  set  aside
           the award. As observed  earlier,  the  public  policy  of  India
           includes - (a) the fundamental  policy  of  India;  or  (b)  the
           interests of India; or  (c)  justice  or  morality;  or  (d)  in
           addition, if it is patently illegal. This extended definition of
           public policy can be bypassed by taking the award to  a  foreign
           country for enforcement."

            After so holding the Court dealt with  the  contentions  of  the
      learned senior counsel who highlighted the concept  of  'transfer'  of
      shares and the procedure involved therein under the  Indian  Companies
      Act, 1956 and the impact of Foreign Exchange Management Act, 1999  and
      adverted to the impact and effect of the legal and regulatory scrutiny
      under  both  the  Act  and  accepted  the  submission.    The   Court,
      thereafter, scanned the shareholders agreement and eventually came  to
      hold that in terms of the decision in Bhatia International  (supra)  ,
      Part I of the Act is applicable  to  the  award  that  was  called  in
      question in the said case, even though it was a foreign award.
      10.   The aforesaid decision clearly lays down that it would  be  open
      to the parties to exclude the application of the provision of  Part  I
      by express or implied agreement.  Unless there is express  or  implied
      exclusion, the whole of Part I would  apply.   The  Court,  as  stated
      earlier, was dealing with shareholders agreement between the  parties.
      Sections 11.05 (b) and (c) of the shareholders agreement  between  the
      parties read as follows:-
           "(b) This agreement shall be construed in  accordance  with  and
           governed by the laws of the State of  Michigan,  United  States,
           without  regard  to  the  conflicts  of  law   rules   of   such
           jurisdiction.  Disputes  between  the  parties  that  cannot  be
           resolved via negotiations shall be submitted for final,  binding
           arbitration to the London Court of Arbitration.

           (c) Notwithstanding anything to the contrary in this  agreement,
           the shareholders shall at all times act in accordance  with  the
           Companies Act and other applicable Acts/rules being in force, in
           India at any time."

            The said clauses were interpreted by the Court  not  to  exclude
      either expressly or impliedly the applicability of Part I of the Act.
      11.   In this context, it will be useful to refer to the  decision  in
      Indtel Technical Services (P) Ltd. v. W.S. Atkins Rail Ltd.[4] wherein
      the designated Judge was called to decide the issue of appointment  of
      sole arbitrator.  The arbitration clause read as follows:-
            "13. Settlement of disputes
              13.1.  This  agreement,  its   construction,   validity   and
           performance shall be governed by and constructed  in  accordance
           with the laws of England and Wales;
              13.2. Subject to Clause  13.3  all  disputes  or  differences
           arising out of, or in  connection  with,  this  agreement  which
           cannot be settled amicably by the parties shall be  referred  to
           adjudication;
              13.3. If any  dispute  or  difference  under  this  agreement
           touches or concerns any dispute or difference  under  either  of
           the sub-contract agreements, then the parties  agree  that  such
           dispute  or  difference  hereunder  will  be  referred  to   the
           adjudicator or the courts as the case may be appointed to decide
           the  dispute  or  difference  under  the  relevant  sub-contract
           agreement and the parties hereto agree to abide by such decision
           as if it were a decision under this agreement."

            The Court referred  to  the  decision  in  Bhatia  International
      (supra) and  Lesotho  Highlands  Development  Authority  v.  Impregilo
      SpA[5] and came to hold as follows:-
           "It is no doubt true that it is fairly well settled that when an
           arbitration agreement is silent as to the law and  procedure  to
           be followed in implementing the arbitration agreement,  the  law
           governing the said agreement would ordinarily be the same as the
           law governing the contract itself. The  decisions  cited  by  Mr
           Tripathi and the views of the jurists referred  to  in  NTPC  v.
           Singer Co.[6] case support such a  proposition.  What,  however,
           distinguishes the various decisions and views of the authorities
           in this case is the fact that in Bhatia International this Court
           laid down the proposition that notwithstanding the provisions of
           Section 2(2) of the  Arbitration  and  Conciliation  Act,  1996,
           indicating that Part I of the said Act  would  apply  where  the
           place  of  arbitration  is  in  India,  even   in   respect   of
           international commercial agreements, which are to be governed by
           the laws of another country, the parties would  be  entitled  to
           invoke the provisions  of  Part  I  of  the  aforesaid  Act  and
           consequently the application made under Section 11 thereof would
           be maintainable."

      12.   Mr. Vishwanathan, learned  senior  counsel,  apart  from  citing
      aforesaid authorities,  have  also  drawn  inspiration  from  Citation
      Infowares Ltd. v. Equinox Corp.[7] wherein the designated  Judge  held
      that unless the provisions of Part  I  of  the  Act  are  excluded  by
      agreement between the parties either expressly or by implication, Part
      I of the Act including Section 11 would be applicable even  where  the
      international commercial  agreements  are  governed  by  the  laws  of
      another country.  It may be that the arbitrator might be  required  to
      take into account the applicable laws which may be  the  foreign  laws
      but that does not affect the jurisdiction under Section 11 which falls
      in Part I which  has  been  specifically  held  applicable  in  Bhatia
      International case.
      13.   Referring to the  arbitration  clause,  submits  learned  senior
      counsel  that  there  is  no  express  or  implied  exclusion  of  the
      applicability of Part I of the Act and, therefore, the Courts in India
      have jurisdiction and the learned Additional District  Judge  had  not
      flawed in exercise of jurisdiction.
      14.   Mr. Giri, learned senior counsel appearing for  the  respondents
      would submit that when the juridical seat is in London, Part I of  the
      Act would not be applicable.  To bolster the aforesaid submission,  he
      has placed reliance on Reliance  Industries  Limited  and  Another  v.
      Union of India[8].  It is also  urged  by  Mr.  Giri,  learned  senior
      counsel that after the principal agreement, an addendum  was  executed
      between the parties after pronouncement  of  the  decision  in  Bharat
      Aluminium Co. case and, therefore, the principles laid down in  Bhatia
      International (supra) would not be applicable.
      15.   It is seemly to exposit the controversy and to  appreciate  what
      has been laid down in the case of Reliance Industries Limited (supra).
       The appellant in the said case has assailed the judgment of the  High
      Court of Delhi whereby the High Court had allowed the  petition  filed
      by the respondent under Section 34 of the Act, challenging  the  final
      partial award, whereby the objections raised by  the  Union  of  India
      relating to the arbitrability of the claims  made  by  the  petitioner
      therein in respect of royalties, cess, service tax and CAG audit  were
      rejected.  The Court  referred  to  various  agreements  entered  into
      between the parties.  It reproduced  Articles  32  and  33  which  was
      entered into between the parties.  The relevant clause for the present
      purpose is 33.12.  We think it appropriate to reproduce  the  relevant
      part of the said clause.
           "33. Sole expert, conciliation and arbitration:

           33.12. The venue  of  conciliation  or  arbitration  proceedings
           pursuant to this article, unless the  parties  otherwise  agree,
           shall be London, England and shall be conducted in  the  English
           language. The arbitration agreement contained in this Article 33
           shall  be  governed  by  the  laws  of   England.   Insofar   as
           practicable, the parties shall continue to implement  the  terms
           of this contract  notwithstanding  the  initiation  of  arbitral
           proceedings and any pending claim or dispute."

      16.   As per Article 33.12, the arbitral proceedings were to  be  held
      in London as the neutral venue.  The venue of the arbitral  proceeding
      was shifted to Paris and again re-shifted  to  London.   Consequently,
      the parties agreed for amendment of the agreement, which  is  relevant
      for the purpose of  understanding the principle, ultimately stated  in
      the said authority:-
           "4.  Applicable law and  arbitration  -  Except  the  change  of
           venue/seat of arbitration from London to Paris, Articles 32  and
           33 of the contract shall be deemed to be set out in full n  this
           agreement mutatis mutandis and so that references therein to the
           contract shall be references to this agreement."

      17.   As issues arose, the Arbitral  Tribunal  was  constituted  under
      Article 33.12, the venue of arbitration was in London.  A  substantial
      hearing was held  in  Singapore.   Thereafter,  by  agreement  of  the
      parties, the Arbitral Tribunal made  a  final  partial  consent  award
      which was as follows:-
           "3. Final partial award as to seat
           3.1. Upon the agreement of the parties, each represented by duly
           authorised representatives and  through  counsel,  the  Tribunal
           hereby finds, orders and awards:

              (a) That without prejudice to the right  of  the  parties  to
              subsequently agree otherwise in writing, the  juridical  seat
              (or legal place) of  arbitration  for  the  purposes  of  the
              arbitration  initiated  under  the   claimants'   notice   of
              arbitration dated 16-12-2010 shall be London, England.
              (b) That any hearings in this arbitration may take  place  in
              Paris, France, Singapore or any other location  the  Tribunal
              considers may be convenient.
              (c) That, save as set out above, the terms and conditions  of
              the arbitration agreements in Article 33 of  the  PSCs  shall
              remain in full force and effect and  be  applicable  in  this
              arbitration."

      18.   The respondent, Union of India, had invoked the jurisdiction  of
      the Delhi High Court by stating that the terms  of  the  PSCs  entered
      would manifest an unmistakable intention of the parties to be governed
      by the laws of India and more particularly the Arbitration Act,  1996;
      that the contracts were signed and executed in India; that the subject-
      matter of the contracts, namely, the Panna Mukta and the Tapti  fields
      are situated within India; that the obligations  under  the  contracts
      had been for the past more than 15 years performed within India;  that
      the contracts stipulate that they "shall be governed  and  interpreted
      in accordance with the laws of India"; that they  also  provided  that
      "nothing in this contract" shall entitle  either  of  the  parties  to
      exercise the rights, privileges and powers conferred upon them by  the
      contract "in a  manner  which  will  contravene  the  laws  of  India"
      (Article 32.2); and that the contracts  further  stipulate  that  "the
      companies and the operations under this contract shall be  subject  to
      all fiscal legislation of India" (Article 15.1)".
      19.   On behalf of the appellant, the  issue  of  maintainability  was
      raised.  The High Court answered the issue in the following manner:
           "Upon consideration of the entire matter,  the  High  Court  has
           held that undoubtedly the governing law  of  the  contract  i.e.
           proper law of the contract is the law of India.  Therefore,  the
           parties never intended to altogether exclude the laws of  India,
           so far as contractual rights are concerned. The laws of  England
           are limited in their applicability in  relation  to  arbitration
           agreement contained in Article 33.  This  would  mean  that  the
           English law would be applicable only with regard to  the  curial
           law matters i.e. conduct of the arbitral  proceedings.  For  all
           other matters, proper law of the contract would  be  applicable.
           Relying on Article 15(1), it has been held that the fiscal  laws
           of India cannot be derogated from. Therefore, the  exclusion  of
           Indian public policy was not envisaged by  the  parties  at  the
           time when they entered into the contract. The High Court further
           held that to hold that the agreement  contained  in  Article  33
           would envisage the matters other than procedure  of  arbitration
           proceedings would be to rewrite the  contract.  The  High  Court
           also held that the question of arbitrability  of  the  claim  or
           dispute cannot be examined  solely  on  the  touchstone  of  the
           applicability of the law relating to arbitration of any  country
           but applying the public policy under the laws of the country  to
           which the parties have subjected the contract  to  be  governed.
           Therefore,  according  to  the  High  Court,  the  question   of
           arbitrability  of  the  dispute  is  not  a  pure  question   of
           applicable law of arbitration or lex arbitri but  a  larger  one
           governing the public policy."

      20.   Addressing the issue of maintainability, this Court referred  to
      the decision in Bhatia International (supra) and took note of the fact
      that parties have agreed and as is also  perceivable  from  the  final
      partial consent award that  the  juridical  seat  or  local  place  of
      arbitration  for  the  purpose  of  arbitration  initiated  under  the
      claimants' notice shall be London, England.   The  parties  have  also
      agreed that the hearing of the notice for arbitration may  take  place
      at Paris,  France,  Singapore  or  any  other  location  the  Tribunal
      considers may be convenient.  The Court posed the question whether  in
      the factual matrix, there has been express or implied exclusion of the
      applicability of Part I of  the  Act.   In  that  context,  the  Court
      referred to paragraph 32 of Bhatia International case and, thereafter,
      analysed the relevant  articles  of  the  PSC  to  discover  the  real
      intention of the parties as to whether the provisions of the  Act  had
      been excluded.   The Court referred to Articles  32.1  and  32.2  that
      dealt with the applicable law and language of the  contract.   Article
      32.1 provided that the proper law of the  contract  would  be  law  of
      India and under Article 32.2 made a declaration none of the provisions
      contained in the contract would entitle either the Government  or  the
      contractor to exercise the rights,  privileges  and  powers  conferred
      upon it by the contract in a manner which would contravene the laws of
      India.  The Court observed that the basis of controversy  involved  in
      the case pertain to analysis of the anatomy of the Article 33.12 which
      provided that venue of the arbitration shall be London  and  that  the
      arbitration agreement shall be governed by the laws of England.   That
      apart, the parties had agreed that juridical seat or  legal  place  of
      arbitration for the purpose initiated under the claimants'  notice  of
      arbitration would be at London.   The Court posed the question whether
      such stipulations excluded the applicability of the Act or  not.   The
      Court repelling  the  contention  that  clauses  do  not  exclude  the
      applicability of the 1996 Act, observed thus:-
           "In our opinion, the expression  "laws  of  India"  as  used  in
           Articles 32.1 and 32.2 has a reference only to  the  contractual
           obligations to be performed by the parties under the substantive
           contract i.e. PSC. In other words, the provisions  contained  in
           Article 33.12 are not governed by the  provisions  contained  in
           Article 32.1. It must be emphasised that Article 32.1  has  been
           made subject to the provision of Article  33.12.  Article  33.12
           specifically provides that the arbitration  agreement  shall  be
           governed by the laws of England. The two articles are particular
           in laying down that the contractual obligations with  regard  to
           the exploration of oil and gas under the PSC shall  be  governed
           and interpreted  in  accordance  with  the  laws  of  India.  In
           contradistinction, Article 33.12 specifically provides that  the
           arbitration  agreement  contained  in  Article  33.12  shall  be
           governed by the laws of England. Therefore, in our opinion,  the
           conclusion is inescapable that applicability of the  Arbitration
           Act, 1996 has  been  ruled  out  by  a  conscious  decision  and
           agreement of the parties. Applying the ratio of law as laid down
           in Bhatia International it would lead to the conclusion that the
           Delhi High Court had no jurisdiction to entertain  the  petition
           under Section 34 of the Arbitration Act, 1996."

      21.   After so stating, the Court opined that it is too  late  in  the
      day to contend that the seat of arbitration is  not  analogous  to  an
      exclusive jurisdiction  clause.   Once  the  parties  had  consciously
      agreed that juridical seat of the arbitration would be London and that
      the agreement would be governed by the  laws  of  London,  it  was  no
      longer open to contend that provisions of Part I of the Act would also
      be applicable to the arbitration agreement.  The Court referred to the
      decision in Videocon Industries Ltd. v. Union of India[9].   Referring
      to clause in the Videocon Industries Ltd. (supra), the Court proceeded
      to state that:-
           47. ....The first issue raised in Videocon Industries  Ltd.  was
           as to whether the  seat  of  arbitration  was  London  or  Kuala
           Lumpur. The second issue was with  regard  to  the  courts  that
           would  have  supervisory  jurisdiction  over   the   arbitration
           proceedings. Firstly, the plea of Videocon Industries  Ltd.  was
           that the seat could not have been changed from Kuala  Lumpur  to
           London only on agreement of the parties without  there  being  a
           corresponding amendment in the PSC. This plea was  accepted.  It
           was held that seat of arbitration  cannot  be  changed  by  mere
           agreement of parties.  In  para  21  of  the  judgment,  it  was
           observed as follows: (SCC p. 170)

                 "21. Though, it may appear repetitive, we deem it necessary
              to mention that as per the terms of agreement,  the  seat  of
              arbitration was Kuala Lumpur. If the parties wanted to  amend
              Article 34.12, they could have done  so  only  by  a  written
              instrument which was required to be signed by  all  of  them.
              Admittedly, neither  was  there  any  agreement  between  the
              parties to the PSC to shift the juridical seat of arbitration
              from Kuala Lumpur to London nor was  any  written  instrument
              signed by them for amending  Article  34.12.  Therefore,  the
              mere fact that the parties to the particular arbitration  had
              agreed for shifting of the  seat  of  arbitration  to  London
              cannot be interpreted as anything except physical  change  of
              the venue of arbitration from Kuala Lumpur to London."

           48. The  other  issue  considered  by  this  Court  in  Videocon
           Industries Ltd. was as to whether a petition under Section 9  of
           the Arbitration Act, 1996 would be  maintainable  in  the  Delhi
           High Court, the parties  having  specifically  agreed  that  the
           arbitration agreement would be governed by the English law. This
           issue was decided against the Union of India  and  it  was  held
           that the Delhi High Court  did  not  have  the  jurisdiction  to
           entertain the petition filed by the Union of India under Section
           9 of the Arbitration Act.

      22.    While  discussing  about  the  ratio  laid  down  in   Videocon
      Industries Ltd. (supra), the  Court  analysed  the  agreement  of  the
      earlier case, and mainly the relevant parts of Articles 33, 34 and 35.
       Article 34.12 in Videocon Industries Ltd. case read as follows:
           "34.12. Venue and law of  arbitration  agreement.-The  venue  of
           sole expert, conciliation or arbitration proceedings pursuant to
           this article, unless the parties otherwise agree, shall be Kuala
           Lumpur,  Malaysia,  and  shall  be  conducted  in  the   English
           language. Insofar as practicable, the parties shall continue  to
           implement  the  terms  of  this  contract  notwithstanding   the
           initiation of arbitral proceedings  and  any  pending  claim  or
           dispute. Notwithstanding the provisions  of  Article  33.1,  the
           arbitration agreement contained in  this  Article  34  shall  be
           governed by the laws of England."

            Clause 35.2 of the agreement pertaining to amendment  stipulated
      that the said contract  shall  not  be  amended  modified,  varied  or
      supplemented in any respect except by an instrument in writing  signed
      by all the  parties,  which  shall  state  the  date  upon  which  the
      amendment or modification shall be effective.  Thereafter,  the  Court
      had proceeded to state what we have reproduced hereinbefore.
      23.   In Reliance Industries Ltd. (supra), the Court took note of  the
      fact that parties had made necessary amendment in the PSCs to  provide
      that the juridical  seat  of  arbitration  shall  be  London  and  the
      arbitration agreement will be governed by the laws of England  and  in
      that context observed that the ratio laid down in Videocon  Industries
      Ltd. (supra) would be relevant and binding.  Proceeding  further,  the
      Court stated thus:
           "The arbitration agreement in this appeal is  identical  to  the
           arbitration agreement  in  Videocon  Industries.  In  fact,  the
           factual situation in the present appeal is on a stronger footing
           than in Videocon Industries Ltd. As noticed earlier, in Videocon
           Industries, this Court concluded that the parties could not have
           altered the seat of arbitration  without  making  the  necessary
           amendment to the PSC. In the present appeal, necessary amendment
           has been made in the PSC. Based on the aforesaid amendment,  the
           Arbitral Tribunal has rendered the final partial  consent  award
           of 14-9-2011 recording that the juridical seat (or legal  place)
           of the arbitration for the  purposes  of  arbitration  initiated
           under the claimants'  notice  of  arbitration  dated  16-12-2010
           shall be London, England. Furthermore, the judgment in  Videocon
           Industries is subsequent to Venture Global. We  are,  therefore,
           bound by the ratio laid down in Videocon Industries Ltd."

      24.   The  Court  also  referred  to  Bharat  Aluminium  Co.  (supra),
      especially para 123, which is as follows:
           "123. ... '... an agreement as to the seat of an arbitration  is
           analogous to an exclusive jurisdiction clause. Any claim  for  a
           remedy ... as to the validity of an existing  interim  or  final
           award is agreed to be made only  in  the  courts  of  the  place
           designated as the seat of arbitration'."
                                                      [emphasis in original]

      25.   The two-Judge Bench referred to  Dozco  India  Private  Ltd.  v.
      Doosan Infracore Company Ltd.[10], Sumitomo Heavy Industries  Ltd.  v.
      ONGC Ltd.[11], Yograj Infrastructure Ltd.  v.  Ssang  Yong  Engg.  and
      Construction Co. Ltd.[12] and quoted a  paragraph  from  C  v.  D[13],
      which was approved in Bharat Aluminium Co. (supra) and  reiterated  in
      Enercon  (India)  Ltd.  v.  Enercon  GmbH[14]  and  further  quoted  a
      paragraph from the  said  authority  which  we  think  condign  to  be
      reproduced:-
           "this follows from the express terms  of  the  Arbitration  Act,
           1996 and, in particular,  the  provisions  of  Section  2  which
           provide that Part I of the Arbitration Act, 1996  applies  where
           the seat of the arbitration is in England and Wales or  Northern
           Ireland.  This  immediately  establishes  a  strong   connection
           between the arbitration agreement itself and the law of England.
           It is for this reason that recent authorities have  laid  stress
           upon the  locations  of  the  seat  of  the  arbitration  as  an
           important  factor  in  determining  the  proper   law   of   the
           arbitration agreement."

            Thereafter, the two-Judge Bench held thus:-
           "In our opinion, these observations in Sulamerica  Cia  Nacional
           de Seguros SA v. Enesa Engelharia  SA  --  Enesa[15]  are  fully
           applicable to the facts and  circumstances  of  this  case.  The
           conclusion reached by the High Court would lead to  the  chaotic
           situation where the parties would be left rushing between  India
           and England for redressal of their grievances. The provisions of
           Part I of the Arbitration Act,  1996  (Indian)  are  necessarily
           excluded;  being  wholly  inconsistent  with   the   arbitration
           agreement which provides "that arbitration  agreement  shall  be
           governed by English law". Thus the remedy for the respondent  to
           challenge any award  rendered  in  the  arbitration  proceedings
           would  lie  under  the  relevant  provisions  contained  in  the
           Arbitration Act, 1996 of England and Wales. Whether or not  such
           an application would now be entertained by the courts in England
           is not for us to [pic]examine, it would have to be  examined  by
           the court of competent jurisdiction in England."

      26.   Elaborating the said facet, the Court  discussed  the  principle
      that has been stated in Bhatia International (supra)  laying  that  in
      cases of international commercial  arbitrations  held  out  of  India,
      provisions of Part I would apply  unless  the  parties  by  agreement,
      express or implied, exclude all or any of  its  provisions.   In  that
      case, the laws or rules chosen by  the  parties  would  prevail.   Any
      provision, in Part I, which is contrary to or excluded by that law  or
      rules will not apply.  Elaborating further, it proceeded to  lay  down
      thus:
           "In this case, the parties have by agreement provided  that  the
           juridical seat of arbitration will be in London. On the basis of
           the aforesaid agreement, necessary amendment has  been  made  in
           the PSCs. On the basis of the agreement and the consent  of  the
           parties, the Arbitral  Tribunal  has  made  the  "final  partial
           consent award" on 14-9-2011 fixing the juridical seat (or  legal
           place) of arbitration for the purposes of arbitration  initiated
           under the claimants' notice of arbitration dated  16-12-2010  in
           London, England. To make it even further clear  that  the  award
           also records that any hearing in the arbitration may take  place
           in Paris, France, Singapore or any other location  the  Tribunal
           considers convenient. Article 33.12 stipulates that  arbitration
           [pic]proceedings shall be conducted  in  English  language.  The
           arbitration agreement contained in Article 33 shall be  governed
           by the laws of England. A combined effect of all  these  factors
           would clearly show that the parties have  by  express  agreement
           excluded the applicability of Part I  of  the  Arbitration  Act,
           1996 (Indian) to the arbitration proceedings."

      27.   On a further analysis of the said decision, we notice  that  the
      Court repelled the submission  that  irrespective  of  the  provisions
      contained in Article 33.12, the Act would be applicable to arbitration
      proceeding and the English law would be applicable only in relation to
      the conduct of the arbitration up to the passing of the partial  final
      award, as in the said case, it was the  partial  final  award  was  in
      question.  In justification in repelling such a submission, the  Court
      opined thus:
           "69.  ...... As noticed earlier, Article  32.1  itself  provides
           that it shall be subject to  the  provision  of  Article  33.12.
           Article 33.12 provides that the arbitration agreement  contained
           in this article shall be governed by the laws  of  England.  The
           term "laws of England" cannot  be  given  a  restricted  meaning
           confined to only curial law. It is permissible under law for the
           parties to provide for different laws of the  contract  and  the
           arbitration agreement and the curial law. In  Naviera  Amazonica
           Peruana SA v. Compania Internacional De  Seguros  Del  Peru[16],
           the Court of Appeal in England  considered  an  agreement  which
           contained a clause providing for the jurisdiction of the  courts
           in Lima, Peru in the event [pic]of judicial dispute and  at  the
           same time contained a  clause  providing  that  the  arbitration
           would be governed by the English law and the procedural  law  of
           arbitration shall be  the  English  law.  The  Court  of  Appeal
           observed as follows:

                 All contracts which provide for arbitration and  contain  a
              foreign  element  may  involve  three  potentially   relevant
              systems  of  law:  (1)  the  law  governing  the  substantive
              contract; (2) the law governing the  agreement  to  arbitrate
              and the performance of that agreement; (3) the law  governing
              the conduct of the arbitration. In the majority of cases  all
              three will be the same. But (1) will often be different  from
              (2) and (3). And occasionally, but rarely (2) may also differ
              from (3).

           70. From the above, it is  evident  that  it  was  open  to  the
           parties to agree that the law governing the substantive contract
           (PSC) would be different from the law governing the  arbitration
           agreement. This is precisely the situation in the present  case.
           Article 32.1 specifically provides that the performance  of  the
           contractual obligations under the  PSC  would  be  governed  and
           interpreted under the laws of India. So far as  the  alternative
           dispute redressal agreement i.e. the  arbitration  agreement  is
           concerned, it would be governed by the laws of England. There is
           no basis on which the respondents can be heard to say  that  the
           applicability of laws of England related only to the conduct  of
           arbitration reference. The law  governing  the  conduct  of  the
           arbitration is interchangeably referred to as the curial law  or
           procedural law or the lex fori. The  delineation  of  the  three
           operative  laws  as  given  in  Naviera   Amazonica   has   been
           specifically followed by this Court in Sumitomo. The Court also,
           upon a survey, of a number of decisions rendered by the  English
           courts and after referring to the  views  expressed  by  learned
           commentators on international commercial  arbitration  concluded
           that:

                 16. The law which would apply to the filing of  the  award,
              to its enforcement and to its setting aside would be the  law
              governing the agreement to arbitrate and the  performance  of
              that agreement."

      28.   After so holding, the  Court  referred  to  the  legal  position
      stated in Dozco's case wherein it has been ruled thus:
           "In the backdrop of these conflicting claims, the question boils
           down to as to what is the true  interpretation  of  Article  23.
           This Article 23 will have to be read in the backdrop of  Article
           22 and more particularly, Article 22.1. It  is  clear  from  the
           language of Article 22.1  that  the  whole  agreement  would  be
           governed by and construed in accordance with  the  laws  of  The
           Republic of Korea. It is for this  reason  that  the  respondent
           heavily relied on the law laid down in Sumitomo Heavy Industries
           Ltd. v. ONGC Ltd. This judgment is a complete authority  on  the
           proposition that the arbitrability  of  the  dispute  is  to  be
           determined in terms of the law governing  arbitration  agreement
           and  the  arbitration  proceedings  have  to  be  conducted   in
           accordance with the curial law. This Court,  in  that  judgment,
           relying on Mustill and Boyd: The Law and Practice of  Commercial
           Arbitration in England, 2nd Edn., observed in para 15 that where
           the law governing the conduct of the reference is different from
           the law governing  the  underlying  arbitration  agreement,  the
           court looks to the arbitration agreement to see if  the  dispute
           is arbitrable, then to the curial law to see how  the  reference
           should be conducted, "and then returns to the first law in order
           to give effect to the resulting award". In para 16, this  Court,
           in no uncertain terms, declared that the law which  would  apply
           to the filing of the  award,  to  its  enforcement  and  to  its
           setting aside would  be  the  law  governing  the  agreement  to
           arbitrate and the performance of that agreement."

            The said view was accepted by the two-Judge Bench.
      29.   Eventually, the Court dislodged the decision of the  High  Court
      of Delhi stating that:
           "76.2. We further overrule and set aside the conclusion  of  the
           High Court that, even though the arbitration agreement would  be
           governed by the laws of England and that the juridical  seat  of
           arbitration would be in London, Part I of  the  Arbitration  Act
           would still be applicable as the laws governing the  substantive
           contract are Indian laws.

           76.3. In the event a final award is made against the respondent,
           the enforceability of the same in India can be resisted  on  the
           ground of public policy.

           76.4. The conclusion of the High Court that in  the  event,  the
           award is sought to be enforced outside India, it would leave the
           Indian party remediless is without any basis as the parties have
           consensually provided that the  arbitration  agreement  will  be
           governed by the English law. Therefore, the remedy  against  the
           award will have to be sought in  England,  where  the  juridical
           seat is located.  However,  we  accept  the  submission  of  the
           appellant that since the substantive law governing the  contract
           is  Indian  law,  even  the  courts  in  England,  in  case  the
           arbitrability is challenged, will have to decide  the  issue  by
           applying Indian law viz. the principle of public policy, etc. as
           it prevails in Indian law."

      30.   We have dealt with the said decision as it has taken note of all
      the pronouncements in the field and further, Mr. Giri, learned  senior
      counsel appearing for the respondents would heavily rely on it and Mr.
      Viwanathan, learned senior counsel would leave no  stone  unturned  to
      distinguish the same on the factual foundation especially in reference
      to the arbitration clause.
      31.   At this juncture, it is profitable  to  note  that  in  Reliance
      Industries Ltd. (supra), the authority in Venture Global Engg. (supra)
      has been distinguished by taking note of the various  clauses  in  the
      agreement and opined that as there was a non obstante  clause  in  the
      agreement hence, the claim of the appellant therein can be enforced in
      India.
      32.   In view of the aforesaid propositions laid down by  this  Court,
      we are required to scan the tenor of  the  clauses  in  the  agreement
      specifically, the arbitration clause in appropriate perspective.   The
      said clause read as follows:
           "5.   If any dispute  or  difference  should  arise  under  this
           charter, general average/arbitration in London to apply, one  to
           be appointed by each of the parties hereto, the third by the two
           so chosen, and their decision or that of any two of them,  shall
           be final and binding, and this agreement may, for enforcing  the
           same, be made  a  rule  of  Court.  Said  three  parties  to  be
           commercial men who are the members  of  the  London  Arbitrators
           Association.  This contract is  to  be  governed  and  construed
           according to English Law.  For disputes where total amount claim
           by either party does  not  exceed  USD  50,000  the  arbitration
           should be conducted in accordance with small claims procedure of
           the London Maritime Arbitration Association."

      33.   Two aspects emerge for consideration: (i) Whether on  the  basis
      of construction placed on the said clause in the agreement it  can  be
      stated that the ratio laid down in Bhatia International (supra)  would
      not be attracted, but what has been laid down in  Reliance  Industries
      Ltd. (supra) would be applicable and (ii) whether the execution of the
      addendum would attract the principles laid down  in  Bharat  Aluminium
      Co. case and oust the jurisdiction of the Indian courts.
      34.   First, we shall advert to the first proposition.   There  is  no
      cavil over the principle stated in Bhatia International  (supra)  that
      Part I of the Act is applicable to  arbitrations  held  outside  India
      unless the parties have either expressly  or  impliedly  excluded  the
      provisions of the Act.  Mr. Vishwanathan, learned senior  counsel  has
      submitted in the case at hand  there  is  no  express  exclusion,  for
      clause remotely does not suggest so.  For the  said  purpose,  he  has
      commended us to the decisions in A.B.C. Laminart Pvt. Ltd. and Anr. v.
      A.P.  Agencies,  Salem[17]  and  Rajasthan  SEB  v.  Universal  Petrol
      Chemicals Ltd.[18] It is also urged by him that the stipulation in the
      agreement does not even remotely impliedly exclude the jurisdiction of
      the Indian courts.  He would submit that to  apply  the  principle  of
      implied exclusion, the Court has to test the "presumed intention"  and
      in such a situation, it is the duty of the Court to adopt an objective
      approach, that is to say,  what  would  have  been  the  intention  of
      reasonable parties in the  position  of  the  actual  parties  to  the
      contract.  Learned senior counsel would also contend that the  concept
      of fair result has to be kept in view while construing a contract.  To
      buttress the aforesaid submissions, he has drawn inspiration from  Kim
      Lewison's The Interpretation of Contracts, pages 26, 41, 110  and  217
      wherein various judgments have been referred.
      35.   The issue has to be tested, as we perceive, on the parameters of
      law laid down in the cases of Videocon Industries Ltd. (supra),  Dozco
      (supra) and Reliance Industries Ltd. (supra).
      36.   In Videocon Industries Ltd. (supra), the Court has  referred  to
      Section 3 of  the  English  Arbitration  Act,  1996,  which  reads  as
      follows:
            "3. The seat of the arbitration.-In this Part 'the seat of  the
           arbitration'  means  the  juridical  seat  of  the   arbitration
           designated-

           (a) by the parties to the arbitration agreement, or

           (b) by any arbitral or other institution or person vested by the
           parties with powers in that regard, or

           (c) by the Arbitral Tribunal if so authorised by the parties, or
           determined, in the  absence  of  any  such  designation,  having
           regard  to  the  parties'  agreement  and   all   the   relevant
           circumstances."

            Analysing the said provision, the Court proceeded  to  state  as
      follows:
           "A reading of the above reproduced provision  shows  that  under
           the English law the seat of arbitration means juridical seat  of
           arbitration, which can be  designated  by  the  parties  to  the
           arbitration agreement or by any arbitral or other institution or
           person empowered by the parties to do  so  or  by  the  Arbitral
           Tribunal, if so authorised by the parties. In contrast, there is
           no provision in the Act under which the Arbitral Tribunal  could
           change the juridical seat  of  arbitration  which,  as  per  the
           agreement of the parties,  was  Kuala  Lumpur.  Therefore,  mere
           change in the physical venue of the hearing from Kuala Lumpur to
           Amsterdam and London did not amount to change in  the  juridical
           seat of arbitration."

            Eventually, the Court in the said case has ruled thus:
           "In  the  present  case  also,  the  parties  had  agreed   that
           notwithstanding  Article   33.1,   the   arbitration   agreement
           contained in Article 34 shall be governed by  laws  of  England.
           This necessarily implies that the parties had agreed to  exclude
           the provisions of Part I of the Act. As a corollary to the above
           conclusion, we hold that the Delhi High Court did not  have  the
           jurisdiction to entertain the petition filed by the  respondents
           under Section 9 of the Act and the mere fact that the  appellant
           had earlier filed similar petitions was not sufficient to clothe
           that High Court with the jurisdiction to entertain the  petition
           filed by the respondents."

      37.   In Dozco (supra), the Court referred to Article 22  and  Article
      23  of  the  agreement,  which  dealt  with  the  governing  laws  and
      arbitration.   Article  22.1  in  the  said  case  provided  that  the
      agreement shall be governed by and construed in  accordance  with  the
      laws of the  Republic  of  Korea.   Article  23.1,  which  dealt  with
      arbitration, stipulated that all disputes arising in  connection  with
      the agreement, shall be finally settled by arbitration in Seoul, Korea
      or such other place as the parties may agree in writing,  pursuant  to
      the rules of agreement then in force of the I.C.C.  The Court referred
      to the decisions in Bhatia  International  (supra),  Indtel  Technical
      Services (supra), Citation Infowares  Ltd.  (supra),  NTPC  v.  Singer
      Co.[19] and while analysing the  import  of  Clause  23.1,  the  Court
      placed heavy reliance on Naviera Amazonica Peruana SA (supra) and held
      thus:
           "19. In respect  of  the  bracketed  portion  in  Article  23.1,
           however, it is to be seen that it was observed in Naviera case:
                 "... It seems clear that  the  submissions  advanced  below
              confused the legal 'seat', etc. of an  arbitration  with  the
              geographically  convenient  place  or  places   for   holding
              hearings. This distinction is nowadays a  common  feature  of
              international arbitrations  and  is  helpfully  explained  in
              Redfern and Hunter in the following passage under the heading
              'The Place of Arbitration':

                 'The preceding discussion has been on the basis that  there
                 is only one "place" of arbitration. This will be the  place
                 chosen by or on behalf of  the  parties;  and  it  will  be
                 designated in the arbitration agreement  or  the  terms  of
                 reference or the minutes of proceedings or  in  some  other
                 way as the place or "seat" of the  arbitration.  This  does
                 not mean, however, that the Arbitral Tribunal must hold all
                 its meetings or  hearings  at  the  place  of  arbitration.
                 International commercial arbitration often involves  people
                 of  many  different  nationalities,  from  many   different
                 countries. In  these  circumstances,  it  is  by  no  means
                 unusual for an Arbitral Tribunal to hold meetings - or even
                 hearings - in a place other than the  designated  place  of
                 arbitration, either for its  own  convenience  or  for  the
                 convenience of the parties or their witnesses....

                 It may be more convenient for an Arbitral Tribunal  sitting
                 in one country to conduct a hearing in  another  country  -
                 for instance, for the purpose  of  taking  evidence....  In
                 such circumstances, each move of the Arbitral Tribunal does
                 not of  itself  mean  that  the  seat  of  the  arbitration
                 changes. The seat of  the  arbitration  remains  the  place
                 initially agreed by or on behalf of the parties.'
              These aspects need to be borne in mind when one comes to  the
              Judge's construction of this policy."
           It would be clear from this that the bracketed  portion  in  the
           article was not for deciding upon the seat of  the  arbitration,
           but for the convenience of the parties in case they find to hold
           the arbitration proceedings somewhere else  than  Seoul,  Korea.
           The part which has been  quoted  above  from  Naviera  Amazonica
           Peruana S.A. v.  Compania  International  de  Seguros  del  Peru
           supports this inference.

           20. In that view, my inferences are that:

              (i)  The  clear  language  of  Articles  22  and  23  of  the
           distributorship agreement  between  the  parties  in  this  case
           spells out a clear agreement between the parties excluding  Part
           I of the Act.
           [pic]
              (ii) The law  laid  down  in  Bhatia  International  v.  Bulk
           Trading S.A. and Indtel Technical  Services  (P)  Ltd.  v.  W.S.
           Atkins Rail Ltd., as also in Citation Infowares Ltd. v.  Equinox
           Corpn. is not applicable to the present case.

              (iii) Since the interpretation of Article 23.1 suggests  that
           the law governing the arbitration will be  Korean  Law  and  the
           seat of arbitration will be Seoul in Korea,  there  will  be  no
           question of applicability of Section 11(6) of the  Act  and  the
           appointment of arbitrator in terms of that provision."

      38.   In Yograj Infrastructure Ltd.  (supra),  two-Judge  Bench  dealt
      with the concept of  "procedural  law"  and  "curial  law".   In  that
      context, it referred to the agreement in the contract, namely, Clauses
      27 and 28.  In that context the Court opined that:
           "..... As indicated hereinabove, Clause 28  indicates  that  the
           governing law of the agreement would be the law  of  India  i.e.
           the Arbitration and Conciliation Act, 1996. The learned  counsel
           for the parties have quite correctly spelt out  the  distinction
           between the "proper law" of the contract and the "curial law" to
           determine the law which is to  govern  the  arbitration  itself.
           While the proper law is the  law  which  governs  the  agreement
           itself,  in  the  absence  of  any  other  stipulation  in   the
           arbitration clause as to which law would apply in respect of the
           arbitral proceedings, it is now well settled that it is the  law
           governing the contract which would also be the law applicable to
           the Arbitral Tribunal itself. Clause 27.1 makes it  quite  clear
           that the curial law which regulates the procedure to be  adopted
           in conducting the arbitration would be the SIAC Rules. There is,
           therefore, no ambiguity that the SIAC Rules would be the  curial
           law of the arbitration proceedings. It  also  happens  that  the
           parties had agreed to make Singapore the  seat  of  arbitration.
           Clause 27.1 indicates that the arbitration proceedings are to be
           conducted in accordance with the SIAC Rules."
                                                         [Emphasis supplied]

      39.   After so stating, the Court posed the question whether in such a
      case, the provisions of Section 2(2), which indicates that Part  I  of
      the Act would apply, where the place of arbitration is India, would be
      a bar to the invocation of provisions of Sections 34  and  27  of  the
      Act, which have been conducted in Singapore.  The  Court  referred  to
      the decision in Bhatia International (supra) wherein it was held  that
      there cannot be any automatic exclusion, but  on  express  or  implied
      exclusion and opined regard being had to  the  Rule  32  of  the  SIAC
      Rules, the law laid down in Bhatia International (supra) would not  be
      applicable.   The said Rule, being pertinent to the issue in question,
      is reproduced below:-
            "32. Where the seat of arbitration is Singapore, the law of the
           arbitration  under  these  Rules  shall  be  the   International
           Arbitration Act (Cap. 143-A, 2002 Edn., Statutes of the Republic
           of Singapore) or its modification or re-enactment thereof."

            And in that context, the Court ruled thus:
           "Having agreed to the above, it was no longer available  to  the
           appellant to contend that the  "proper  law"  of  the  agreement
           would apply to the  arbitration  proceedings.  The  decision  in
           Bhatia International v. Bulk Trading  S.A.,  which  was  applied
           subsequently in Venture Global  Engg.  [pic]v.  Satyam  Computer
           Services Ltd. and Citation  Infowares  Ltd.  v.  Equinox  Corpn.
           would have no application once the parties agreed by  virtue  of
           Clause 27.1 of the agreement that  the  arbitration  proceedings
           would be conducted in Singapore i.e.  the  seat  of  arbitration
           would  be  in  Singapore,  in  accordance  with  the   Singapore
           International Arbitration Centre Rules as in force at  the  time
           of signing of the agreement.

                         xxxxx      xxxxx      xxxxx

           In the instant case, once the parties  had  specifically  agreed
           that  the  arbitration  proceedings  would   be   conducted   in
           accordance with the SIAC Rules,  which  includes  Rule  32,  the
           decision in Bhatia International1 and the  subsequent  decisions
           on the same lines, would no longer apply  in  the  instant  case
           where the parties had willingly agreed to  be  governed  by  the
           SIAC Rules."
                                                            [Emphasis added]

      40.   In Reliance Industries Ltd. (supra), the two-Judge Bench,  while
      referring to the submissions of the learned counsel for the  appellant
      therein  had  also   referred   to   the   pronouncement   in   Yograj
      Infrastructure Ltd. (supra) and dealt with it thus:
           "Again this Court in  Yograj  Infrastructure  (two-Judge  Bench)
           considered a similar arbitration agreement. It was provided that
           the arbitration proceedings shall be  conducted  in  English  in
           Singapore  in  accordance  with  the   Singapore   International
           Arbitration Centre  (SIAC)  Rules  (Clause  27.1).  Clause  27.2
           provided that the arbitration shall take place in Singapore  and
           be conducted in English language. This Court  held  that  having
           agreed that the seat of arbitration would be Singapore and  that
           the curial law of the arbitration proceedings would be the  SIAC
           Rules, it was no longer open to the appellant to contend that an
           application under Section 11(6) of  the  Arbitration  Act,  1996
           would be maintainable. This judgment has specifically taken into
           consideration the law laid  down  in  Bhatia  International  and
           Venture Global. The same view has been taken by the  Delhi  High
           Court, the Bombay High Court and the Gujarat High Court, in fact
           this  Court  in   Videocon   has   specifically   approved   the
           observations made by the Gujarat High Court in Hardy Oil and Gas
           Ltd. v. Hindustan Oil Exploration Co. Ltd.[20]"

      41.   Coming to the stipulations in the present arbitration clause, it
      is clear as day that if any dispute or difference  would  arise  under
      the charter, arbitration in London to apply; that the arbitrators  are
      to  be  commercial  men  who  are  members   of   London   Arbitration
      Association; the contract is to be construed and governed  by  English
      Law; and that the arbitration should be conducted, if the claim is for
      a lesser sum, in accordance with small claims procedure of the  London
      Maritime Arbitration Association.   There is no other provision in the
      agreement that any other law would govern the arbitration clause.
      42.   Mr. Giri, learned senior counsel  would  submit  that  from  the
      clause which is a comprehensive one, it is London, which is  the  seat
      of arbitration.  In Videocon  Industries  Ltd.  (supra),  as  we  have
      analysed earlier, Article 33.1 of the agreement which stipulated  that
      subject to the provisions of Article  34.12,  the  contract  would  be
      governed and interpreted in accordance with the laws of India.  Clause
      34.12 of the agreement read as follows:
           "34.12. Venue and law of  arbitration  agreement.-The  venue  of
           sole expert, conciliation or arbitration proceedings pursuant to
           this article, unless the parties otherwise agree, shall be Kuala
           Lumpur,  Malaysia,  and  shall  be  conducted  in  the   English
           language. Insofar as practicable, the parties shall continue  to
           implement  the  terms  of  this  contract  notwithstanding   the
           initiation of arbitral proceedings  and  any  pending  claim  or
           dispute. Notwithstanding the provisions  of  Article  33.1,  the
           arbitration agreement contained in  this  Article  34  shall  be
           governed by the laws of England."

      43.   In that context, the Court referred to Section 3 of the  English
      Arbitration Act, 1996 and as has been stated earlier, opined  that  as
      per the English law, the seat of arbitration as per the said provision
      would mean "juridical seat of arbitration" and accordingly opined that
      principles  stated  in  Bhatia  International  (supra)  would  not  be
      applicable.
      44.   In the present case, the agreement stipulates that the  contract
      is to be governed and construed according to the  English  law.   This
      occurs in the arbitration clause.  Mr.  Vishwanathan,  learned  senior
      counsel, would submit that this part has to be interpreted as  a  part
      of "curial law" and not as a "proper law" or "substantive law".  It is
      his submission that it cannot be equated with the seat of arbitration.
       As we perceive, it forms as a part of the arbitration clause.   There
      is ample indication  through  various  phrases  like  "arbitration  in
      London to apply", arbitrators are to be the  members  of  the  "London
      Arbitration  Association"  and  the  contract  "to  be  governed   and
      construed according to English Law".  It is worth noting that there is
      no other stipulation relating to the applicability of any law  to  the
      agreement.  There is no other clause anywhere in the  contract.   That
      apart, it is also postulated that if the dispute is for an amount less
      that  US  $  50000  then,  the  arbitration  should  be  conducted  in
      accordance  with  small  claims  procedure  of  the  London   Maritime
      Arbitration Association.  When the aforesaid stipulations are read and
      appreciated in the contextual perspective, "the presumed intention" of
      the parties is clear as crystal that the juridical seat of arbitration
      would be London.  In this context, a  passage  from  Mitsubishi  Heavy
      Industries Ltd. v. Gulf Bank[21] is worth reproducing:
           "It is of course  both  useful  and  frequently  necessary  when
           construing a clause in a contract to have regard to the  overall
           commercial purpose of the contract in the  broad  sense  of  the
           type and general content, the relationship of  the  parties  and
           such common commercial purpose as may clearly emerge  from  such
           an exercise.  However, it does not seem to me  to  be  a  proper
           approach to the construction of a default clause in a commercial
           contract to  seek  or  purport  to  elicit  some  self-contained
           'commercial purpose' underlying the clause which is  or  may  be
           wider than the ordinary or usual construction of  the  words  of
           each sub-clause will yield."

      45.   In  Cargill  International  S.A.  v.  Bangladesh  Sugar  &  Food
      Industries Corp.[22], Potter L.J.  balanced  the  two  approaches  and
      said:
           "In this connection [counsel] has rightly made the  point  that,
           when construing the effect of particular words in  a  commercial
           contract, it is wrong to put a label on the contract in  advance
           and this to approach the question of construction on  the  basis
           of a pre-conception as to the contact's  intended  effect,  with
           the result that a strained  construction  is  placed  on  words,
           clear in themselves, in order  to  fit  them  within  such  pre-
           conception...

                 On the  other  hand,  modern  principles  of  construction
           require the court to have regard to the  commercial  background,
           the context of the contract ad the circumstances of the parties,
           and to consider whether, against  that  background  and  I  that
           context, to give the words a particular  or  restricted  meaning
           would lead to an apparently unreasonable and unfair result."

      46.   Thus, interpreting the clause in question on the bedrock of  the
      aforesaid principles it is vivid that the intended effect is  to  have
      the seat of arbitration at London.   The  commercial  background,  the
      context of the contract and the circumstances of the  parties  and  in
      the background in which the contract was  entered  into,  irresistibly
      lead in that direction.  We are not impressed by the  submission  that
      by such interpretation it will put the respondent in  an  advantageous
      position.  Therefore, we think it would be  appropriate  to  interpret
      the clause that it is a proper clause or substantial clause and not  a
      curial or a procedural one by which the arbitration proceedings are to
      be conducted and hence, we are disposed to  think  that  the  seat  of
      arbitration will be at London.
      47.   Having said that  the  implied  exclusion  principle  stated  in
      Bhatia International (supra) would be applicable, regard being had  to
      the clause in the agreement, there  is  no  need  to  dwell  upon  the
      contention raised pertaining to the addendum, for  any  interpretation
      placed on the said document would  not  make  any  difference  to  the
      ultimate conclusion that we have already arrived at.
      48.   Before parting with the case, it is obligatory on  our  part  to
      state that the Division Bench  of  the  High  Court  has  allowed  the
      petition on the foundation that the Bharat Aluminium  Co.  case  would
      govern the field and, therefore, the court below had  no  jurisdiction
      is not correct.  But as has been analysed and discussed  by  us,  even
      applying the principles laid down in Bhatia International (supra)  and
      scanning the anatomy of the arbitration clause, we have arrived at the
      conclusion that the courts in India  will  not  have  jurisdiction  as
      there is implied exclusion.
      49.    Consequently,  for  different  reasons,  we  concur  with   the
      conclusion arrived at by the High Court and accordingly,  the  appeal,
      being sans  merit,  stands  dismissed.   However,  in  the  facts  and
      circumstances of the case, there shall be no order as to costs.

                                             .............................J.
                                                               [Dipak Misra]



                                             ..........................., J.
                                                          [Prafulla C. Pant]
      New Delhi
      March 10, 2015

-----------------------
[1]  (2012) 9 SCC 552
[2]  (2002) 4 SCC 105
[3]  (2008) 4 SCC 190
[4]  (2008) 10 SCC 308
[5]  (2005) 3 WLR 129
[6]  (1992) 3 SCC 551
[7]  (2009) 7 SCC 220
[8]  (2014) 7 SCC 603
[9]  (2011) 6 SCC 161
[10]  (2011) 6 SCC 179
[11]  (1998) 1 SCC 305
[12]  (2011) 9 SCC 735
[13]  2008 Bus LR 843
[14]  (2014) 5 SCC 1
[15]  (2013) 1 WLR 102
[16]  (1988) 1 Lloyd's Rep 116 (CA)
[17]  (1989) 2 SCC 163
[18]  (2009) 3 SCC 107
[19]  (1992) 3 SCC 551
[20]  (2006) 1 Guj LR 658
[21] [1997] 1 Lloyd's Rep. 343
[22]  [1998] 1 W.L.R. 461 CA