Supreme Court of India (Full Bench (FB)- Three Judge)

Appeal (Civil), 888 of 2016, Judgment Date: Feb 05, 2016

                                                                  REPORTABLE

                        IN THE SUPREME COURT OF INDIA

                        CIVIL APPELLATE JURISDICTION

                    CIVIL APPEAL NO.     888     OF 2016
              (ARISING OUT OF S.L.P. (CIVIL) NO. 35037 OF 2015)


GOVT. OF NCT OF DELHI AND ANR.                          .....APPELLANT(S)            
                                                                       
                                   VERSUS   
                                                               
ANAND ARYA AND ORS.                                    .....RESPONDENT(S)           

                                    WITH
                      CIVIL APPEAL NO.   889    OF 2016
              (ARISING OUT OF S.L.P. (CIVIL) NO. 35038 OF 2015)

                               J U D G M E N T


A.K. SIKRI, J.

                 Notice, returnable forthwith.

Respondent Nos. 1 and 2 (hereinafter referred to as the “respondents”),  who
are the real contesting respondents, have appeared on  Caveat  and  accepted
notice. Keeping in view the nature of order which  we  propose  to  pass  in
these appeals, it was  not  found  necessary  to  serve  other  respondents.
Insofar  as  counsel  for  the  appellants  as  well  as  counsel  for   the
respondents are concerned, they were ready  to  argue  the  matter  finally.
Accordingly, we heard the matter finally at this stage itself.

Leave granted in both these matters.

The appellants in these two appeals are  Government  of  NCT  of  Delhi  and
Delhi Transport  Corporation  respectively.   They  feel  aggrieved  by  the
orders dated October 20, 2015 passed by the High Court of Delhi  in  CM  No.
12299 of 2015 in Writ Petition (Civil) No. 5481 of 2011.  In order  to  have
a glimpse of the controversy, we may state that the matter pertains  to  the
construction of Bus Depot by the appellants on  an  area  situated  next  to
Nizamuddin Bridge and behind I.P. Power Station.  Writ Petition (Civil)  No.
5481 of 2011 was disposed of by the High Court vide orders  dated  September
13, 2015.  It was found that as per the Master  Plan  2021  (MPD  2021)  for
Delhi the aforesaid Bus Depot, popularly known as Millennium Bus Depot,  was
shown as “river flood plain” and  on  such  are  no  construction  could  be
carried out as per MPD 2021.  The High  Court,  however,  gave  six  months'
time to the authorities to change the Master Plan, as per law,  if the  same
was permissible, failing which the Millennium Bus Depot was  to  be  removed
from the site.  This has not happened, though the order of  the  High  Court
is dated September 13, 2012.  The DTC filed an application for extension  of
time , i.e., CM No. 12299 of 2015.  By the impugned order dated October  20,
2015, the High Court has rejected the  prayer  for  extension  of  time  and
dismissed the application.  It is this order which is the subject matter  of
the instant appeals.

The matter has some history.  In order to appreciate the position  taken  by
the parties on the either side,  it  would  be  necessary  to  traverse  the
historical trajectory.  As we unfold the events that have taken  place,  the
narration thereof would not only reflect the position taken by  the  parties
on either side, some of the answers which apparently flow from  these  facts
would also automatically become available.  For these reasons, we take  note
of  these  events  that  are  material  for  these  appeals   but   avoiding
unnecessary details at the same time.

As is clear from the glimpse of the  lis  mentioned  above,  the  appellants
have constructed Millennium Bus Depot at the site in question.  As  per  the
respondents, the site is river flood plain and as per Master  Plan  –  2021,
no construction can be carried out on such an area.  The  area  in  question
is next to Nizamuddin Bridge and behind I.P. Power Station and falls in Sub-
Zone-06, Zone-O, between Nizamuddin Railway Bridge and  National  Highway-24
measuring  390  hectares.   This  prompted  the  respondents  to  file  Writ
Petition (Civil) No. 5481 of 2011 by way of Public Interest Litigation.  The
petition was filed at a time when the construction was still underway.   The
respondents wanted stay of construction as well.  However, no  such  interim
prayer was granted.  By the time the matter came up for final  hearing,  the
construction had been completely carried out and DTC Bus Depot  had  started
functioning therefrom. Under these circumstances,  the  respondents  pressed
their relief for demolition of the construction and restoration of  area  in
its original condition.

It was  averred  by  the  respondents  that  the  construction  in  question
amounted to encroachment  on  river  flood  plain/river  front  resulting  a
change in the land use.  It was also stated that as  per  the  Master  Plan,
the area is earmarked for recreation  purposes  on  the  West  Bank  (Clause
9.2.1).  It was pointed out that Draft Zonal Plan of the area was  published
in July, 2008 for the purpose of inviting objections.  The  Zonal  Plan  has
specified the land use of the River and confirmed that it would be only  for
recreational use such as Biodiversity  Park,  Botanical  Park,  Forest  etc.
which would help in regenerating  the  environment.   The  respondents  also
pointed out that the DDA vide its communication dated December  2,  2010  in
response to RTI query had confirmed that a 6 hectares strip of land  between
Akshardham Complex and the Commonwealth Games Village was indeed  designated
as 'Parking' in the approved lay out plan.  The Delhi Urban  Art  Commission
(hereinafter referred to as 'the DUAC') after its inspection carried out  on
November 02, 2010 had directed both the DDA and the DTC to vacate the  river
bed and to ensure the removal of all the constructions carried  out  in  the
past.  Even the Shunglu Committee which was set up to go  into  the  conduct
of Commonwealth Games-2010 had adversely commended upon the construction  of
the said structure and in its report by observing as under:-
“All clearances were provided by the Lieutenant  Governor  for  construction
of a 'temporary' structure which was ostensibly to be dismantled  after  the
conclusion of the Games.  But this Project was implemented by the  Transport
Department, GNCTD  and  DTC  right  from  the  beginning  as  a  'permanent'
structure.  It appears as if the hosting  of  CWG  provided  a  pretext  for
'land grab' by  various  Government  agencies  after  short  circuiting  the
established rules and procedures.”

      In its affidavit filed by the DUAC, it  also  categorically  mentioned
that no proposal regarding the alleged construction  was  ever  referred  to
the DUAC at any time and no sanction or approval was thus obtained.  It  was
also mentioned that site was inspected by the  DUAC  and  thereafter  matter
was considered by the DUAC in its meeting held on November 10, 2010.
      In nutshell,  the  case  set  up  by  the  respondents  was  that  the
construction of Bus Depot is contrary to Master Plan; it  would  affect  the
ecology and environment of the area; by ignoring  the  same  the  appellants
were violating the principle of  Puyblic  Trust,  principle  of  Sustainable
Development,  Polluter  Pays  Principle,  Principle  of   Inter-Generational
Equity; and all this amounted to infuriation of Articles  21,  48A,  51A  of
the Constitution.

The DTC and Delhi Government filed their  respective  affidavits  explaining
that the land in question was allotted for the development of a  Bus  Deport
to be used during the Commonwealth Games which  where  to  be  held  in  New
Delhi in October, 2010.  The position taken by  the  DTC  was  that  it  was
imperative to have such a bus depot which was utilised for  operating  buses
in the city of Delhi and almost 900 buses were providing services from  this
Depot which was serving major bus terminals. Since  it  was  serving  public
purpose, there was necessity for such a depot.  At the same time,  DTC  also
accepted the position that as per Master Plan, the area was shown  as  river
bed and no such construction could be carried our on river bed. In  view  of
such a situation, it was stated in the affidavit that the  DTC  vide  letter
dated November 09, 2010 had requested the DDA for change of land use.
      The public purpose was highlighted  by  stating  that  the  Millennium
Park Bus Parking acts as a life line  for  nearly  one  fourth  of  the  bus
commuters of Delhi.  It caters to approximately ten lakhs people  every  day
and is immensely beneficial to lower and middle class  sections  of  society
who cannot afford a means  of  transport  other  than  public  bus  service.
Shutting down the Millennium Park Bus Parking would deprive lakhs of  people
of cheap and convenient bus service and would render  jobless  nearly  2,000
employees of the DTC such a drivers, conductors, mechanics, etc.

The DTC also denied that there is a construction  on  the  flood  plains  of
Yamuna River.  As per the DTC, the Millennium Park  Bus  is  situated  at  a
suitable distance from  the  river  bund.   It  was  submitted  that  before
development of the said land into a bus depot, the  same  was  used  by  the
Indraprastha Thermal Power Plant for dumping of  residual  fly-ash.   Almost
20 meters of fly-ash spared over many  acres  were  leveled,  compacted  and
covered with granular sub base to enable the ground to  bear  the  13.5  ton
weight of each Low Floor Bus.   Incidentally,  a  high  tension  electricity
transmission tower-which is an essential part of the  infrastructural  needs
of the city, is situated right in the center of this  area.   The  DTC  also
sought to project that no  commercial  activity  to  the  detriment  of  the
ecological balance of the said land or the Yamuna River is taking  place  as
a result of the operation of the bus depot.  It emphasized that the DTC  had
spent an amount of approximately ?100 crores  on  the  development  of  this
infrastructure.

An additional affidavit was filed by the  DTC  giving  certain  material  to
support its contention that the scientific  study  conducted  by  an  expert
body like NEERI recommended the  area  in  question  for  usage  as  parking
space.

After taking note of the respective stand of  the  parties  the  High  Court
went into the question as to  whether  the  aforesaid  Bus  Depot  could  be
constructed at the given site.   It  was  found  that  since  there  was  no
dispute that as per MPD-2021 the land use of the site was  shown  as  “River
Water Body” on which construction of the type carried out  by  the  DTC  was
impermissible as law mandates construction in  conformity  with  the  Master
Plan. Because of this reason the High Court disposed of  the  writ  petition
by giving six months'  time  to  the  appellants  to  get  the  Master  Plan
amended, if it was possible in law.

The flavour of the said order and the manner in which the writ petition  was
disposed of can be gazed from paras 17 to 19  thereof,  which  we  reproduce
hereunder for sake of clarity:
“17.  The moot question, however, is as to whether this Bus Depot  could  be
constructed at the given site?  The petitioners have sought  to  demonstrate
that the construction is carried out at the place which forms part of  flood
plains/river built (sic - bed) and this id denied by the  DTC/Government  of
NCT of Delhi.  On the other hand, the respondents argue that  it  is  not  a
river bed and having regard to previous user of the  site  for  fly-ash  for
last number of years, use thereof as bus depot  is  appropriate,  it  is  in
public interest and  no  other  suitable  site  is  available  or  at  least
identified by DDA so far.  We are, however, of the view that it may  not  be
necessary even to go into these questions.  The stark  reality  is  that  as
per MPD-2021 the land use of the site is “River  Water  Body”.   Admittedly,
any construction has to be in conformity with the Master Plan.  May  be  for
this reason, when the land was allotted to the DTC to take care of the  need
of Commonwealth Games, it was for the purpose of 'temporary'  parking,  that
too, in view of the security threat perceptions prevailing  in  the  region.
The Government was conscious of the fact that there cannot  be  a  permanent
Bus Depot without amendment of the  Master  Plan,  2021.   It  is  for  this
reason, even during the argument, Mr. Waziri  made  a  submission  that  the
Government was planning to make modification in the Master Plan.

18.  In view of the above, we are of the opinion that  these  petitions  can
be disposed of by permitting the respondents to take steps for amendment  in
the Master Plan, as per law, if it is  permissible.   There  is  a  specific
procedure for effecting the change in the Master Plan which includes  notice
to the public at large and inviting  objections.   Once  this  procedure  is
followed and objections are invited, it would be open to the petitioners  to
file their objections and raise issue of ecology and environment which  will
have to be considered.  Thus, arguments raised before us by the  petitioners
in this  behalf  can  be  duly  taken  into  consideration  at  that  stage.
Naturally, if there is any substance in the contention of  the  petitioners,
it may not result change in the Master Plan.  On the  other  hand,  at  that
stage it will also be open to the  respondents,  particularly  DTC,  to  put
forth its case that the site in question was used as fly-ash purposes  since
1960s and on  the  construction  of  bund,  the  area  was  segregated  and,
therefore, it is not going to have any impact on river  built/flood  plains.
What we are emphasizing is that the respective contentions  on  this  aspect
can be considered and looked into and decision thereupon taken.

19.  These petitions are accordingly disposed  of  by  granting  six  months
time to the respondents to take steps for the change in the Master Plan,  if
it  is  possible,  thereby  changing  the  land  user  and  bringing  it  in
conformity with the present use.  In case, the Master  Plan  is  amended  in
this manner, the natural consequence thereof would be  that  the  Bus  Depot
would continue to operate from the  given  site.   On  the  other  hand,  if
attempt to amend the Master Plan fails, there would  be  no  option  to  re-
locate the Bus Depot to some other place.  In that event,  it  will  be  for
the DTC to ask the DDA to allot alternate site and feasibility  of  site  at
Mayur Vihar can also be considered at that stage.”


Following aspects are discernible from the aforesaid order:
(a)  The construction  of  Millennium  Bus  Depot  is  on  the  land,  which
according to MPD-2021 is shown as 'River Water Body'.
(b)  Position in law is clear, on  which  there  is  no  dispute,  that  any
construction has to be in conformity with the Master Plan.
(c)  If the land use of the site in question is 'River Water  Body'  as  per
MPD-2021, construction thereupon is not permissible and such area cannot  be
used as Bus Depot.
(d)  The DTC, however, contended that land site was wrongly shown as  'River
Water Body' in the MPD 2021 as it was actually not so.   It  contended  that
the previous user of the site was  for  fly-ash  and  the  argument  of  the
appellants in the  High  Court  was  that  it  was  not  a  river  bed  and,
therefore, same could be used  as  Bus  Depot,  which  user  was  in  public
interest.  The respondents herein, on the other  hand,  contended  that  the
user of the site as Bus Depot was a threat to ecology and environment.
(e)  Since as per the MPD-2021, the land use of the  site  is  'River  Water
Body', on which construction was not permissible without  amendment  of  the
Master Plan, the appellants conceded that  in  order  to  continue  the  Bus
Depot, amendment in the Master Plan was needed.

Keeping in mind the aforesaid aspects, the High  Court  granted  six  months
time to the authorities to take steps for change in the Master Plan,  if  it
was possible in law, thereby changing the  land  user  and  bringing  it  in
conformity with the present use.  It was  pointed  out  that  the  procedure
that  has  to  be  followed  for  change  of  Master  Plan  included  giving
opportunity to the respondents herein to file  their  objections  and  raise
the issue of ecology and environment and for DTC to put forth its case  that
the site in question  was  used  as  fly-ash  purposes  since  1960  and  on
construction of the Bund the area was  segregated  and,  therefore,  use  of
site as Bus Depot was not going to have any impact on  the  river  bed/flood
plains.  The purpose was, thus, to give an opportunity to the appellants  to
establish that area could not be treated as  'river  bed'  and  if  that  is
proved, it could pave way for change of MPD 2021.

There is no amendment in the MPD-2021 till date on the aforesaid aspect  and
as per the said Master Plan, land use remains the same, which has  not  been
altered.  The DTC has its own explanation as it  is  contended  that  though
steps were taken by the DDA to change the land use, but it was  taking  time
because of the dispute  that  had  arisen  between  DDA  and  the  Land  and
Development Office (L&DO) about the ownership of the land in  question.   Be
as it may, the Master Plan remains unaltered.

Since time of  six  months  granted  by  the  High  Court  expired  and  the
consequence thereof was that as per the directions contained  in  the  order
dated 13.09.2012 the appellants had to relocate the Bus Depot to some  other
place, and the same was not done,  the  respondents  herein  filed  Contempt
Petition No.  474  of  2013  in  Writ  Petition  No.  5481  of  2011.   Some
significant developments which took place in the Contempt Petition  need  to
be mentioned at this stage.

On receiving  the  notice  of  contempt,  in  which  Chairman-cum-  Managing
Director (CMD) of DTC was impleaded as respondent/ contemnor, the CMD  filed
an affidavit dated 23.01.2014 on behalf of the DTC wherein  undertaking  was
given to the Court to vacate the site in question on or  before  31.10.2014.
It was also mentioned by the DTC in the affidavit that the problem could  be
solved by  the  DDA  with  the  allotment  of  alternate  land.   Since  the
officials of the DDA was also impleaded as a contemnor in the said  Contempt
Petition, they filed periodic Status Reports  in  respect  of  allotment  of
land.  The  ultimate  result  was  that  the  DDA  allotted  8.25  acres  of
additional land at Sarai Kale Khan, 10 acres of land at Narela, 16.33  acres
of land at Anand Vihar and 20 acres of land at Rohini  Phase-V.   The  stand
of the DTC was that some portion of the land allotted by the  DDA  had  been
encroached upon illegally and  the  land  use  had  also  not  been  changed
because of which the DTC was unable to shift.
      In the meantime, the application for extension of time was  filed,  as
aforesaid, which was pending consideration by  the  Division  Bench  of  the
High Court and because of this reason, the Contempt Petition  was  adjourned
from time to time to await the result of the said application.
      When the Division Bench dismissed the  application  for  extension  of
time vide impugned order dated 20.10.2015, the Contempt Petition  was  taken
up by the learned Single Judge of the High Court  and  taking  note  of  the
said dismissal, the High Court pointed out that the  DTC  had  to  forthwith
comply with the order dated 13.09.2012.  As on that date, the  DTC  informed
the Court that  500  out  of  800  buses  that  were  being  parked  at  the
Millennium Bus Depot had already been shifted to other Bus Depots.  In  this
scenario, the Court granted the DTC  two  months  further  time,  i.e.  till
27.01.2016, to vacate the Bus Depot by shifting remaining buses as  well  to
some other Depots.

The position that emerges from the aforesaid events  can  be  summed  up  as
under:
      Though an opportunity was granted by the High Court to the  appellants
to have the MPD-2021 amended, if the same was possible, and the time of  six
months was granted for this purpose, even when almost four and a half  years
have passed, there is no amendment in the Master Plan.  In  the  absence  of
said amendment, the legal position is  that  Millennium  Bus  Depot  at  the
given site cannot operate.  In the Contempt Petition, undertaking was  given
by the DTC to vacate the Bus Depot by 31.10.2014.  That undertaking  is  not
adhered to.  No doubt, application for extension of  time  was  pending  and
because of this reason the Contempt Petition  was  adjourned  from  time  to
time, but the said application for extension has been dismissed taking  note
of the fact that the appellants have failed to get the Master Plan  amended.
 In the impugned order, while dismissing  the  said  application,  the  High
Court has taken note of the circumstances  because  of  which  there  is  no
amendment to the Master Plan.

Another material fact which is to be noticed is  that  in  respect  of  this
very issue, there was a meeting held under the  Chairmanship  of  the  Chief
Minister of Government of NCT of Delhi on 15.01.2014 wherein the  background
of the development of the Millennium Bus Depot was explained  by  the  Chief
Secretary.  After understanding this background, the Chief Minister  pointed
out the urgent need to protect the land along  the  riverbed  of  the  river
Yamuna to increase recharge and to supplement the water needs  of  the  city
of Delhi.  He was, therefore, of the view that DTC should  vacate  the  land
in question and move its buses to some alternate location and  the  same  be
done in a time bound manner.  As the Minutes of the  said  meeting  reflect,
the demand of the Chairman of the DTC was that the  DDA  should  immediately
provide alternate land for relocating thousand buses which  are  parked  and
maintained at the said Depot.  It was explained that if  no  alternate  site
is immediately made  available,  the  DTC  will  face  great  difficulty  in
parking its fleet as there are huge constraints in its existing  depots  for
the fleet in question.  DTC even gave the explanation by submitting that  it
had got the Environmental Impact Assessment from  WAPCOS  (a  Government  of
India body under the Ministry of Water Resources) and it  was  committed  to
following the said Report in all respects.  It also mentioned that  the  DTC
was making efforts in creating greenery  in  the  area  and  setting  up  of
effluent treatment plants.  Significantly, notwithstanding  the  above,  the
Chief Minister expressed that DTC should relocate to some other place.   The
entire discussion thereof proceeded on the alternate land to be allotted  by
the DDA to the DTC.

If only the aforesaid features are to be kept in mind, there is  hardly  any
reason to interfere with the order passed by the High Court. In  fact,   Mr.
Shanti Bhushan and Mr. Jayant Bhushan, learned senior counsel appearing  for
the  respondents,  on  the  other  hand,  submitted   that   the   aforesaid
circumstances, as pointed out by the  appellants,  had  no  bearing  on  the
issue and having regard to the solemn undertaking given by the  DTC  in  its
affidavit to shift the Bus Depot  by  31.10.2014,  which  had  already  been
flouted, and the DTC was in clear contempt,  no  further  chance  should  be
given to the appellants in this behalf.

Notwithstanding the above  position,  Mr.  K.K.  Venugopal,  learned  senior
counsel appearing for  the  DTC,  and  Dr.  Rajeev  Dhawan,  learned  senior
counsel appearing for the Govt. of NCT of Delhi, made a passionate plea  for
grant of some more time as according to them there was still  a  possibility
of amending the Master Plan suitably  in  near  future.   Such  a  plea  was
predicated on the developments which have taken place after the  passing  of
the impugned order.  Explaining the  position,  it  was  submitted  that  no
amendment in MPD 2021 would be carried out earlier because of the  following
three hurdles:
1)    L&DO land ownership issue.
2)    Yamuna Standing Committee approval.
3)    Foresh Department approval.
       Mr.  Venugopal  submitted  that  on  all  three  fronts,  the  ground
realities had undergone a total change.  It was pointed out that  even  when
L&DO had raised the issue of land ownership, it had  in  principle  accepted
to grant No Objection Certificate for the retention of DTC Bus Depot.   Even
Yamuna Standing Committee had granted its approval in principle,  which  was
evident from the Minutes of the Meeting held on 17.09.2013  and  04.10.2013.
Likewise, Forest Department approval  was  under  consideration,  which  was
clear from the correspondence that was exchanged in this behalf and  it  was
explained that no prior environment clearance was needed  in  this  case  as
the built up area in the complex is less than 20,000  sq.mts.   The  learned
counsel also  referred  to  the  minutes  of  the  meeting  held  under  the
Chairmanship  of  A.S.  (UD)  in  the  Ministry  of  Urban  Development,  on
17.10.2015 wherein following was agreed:
(i)   DDA will take immediate steps, possibly within a period of one  month,
for demarcation of 'O' zone area after collecting  the  required  statistics
from the Irrigation & Flood Control Department of GNCTD.

(ii)  MD, DTC will actively coordinate with DDA for facilitating  collecting
the data and also in whatever way possible for  conducting  the  demarcation
of  'O'  zone  and  also  approaching  the  Principal  Committee   for   its
permission.

(iii)   Once  the  required  permission  from  the  Principal  Committee  is
available and the court cases are disposed  of,  L&DO  will  take  necessary
action for issuing the required NOC for land use for the Bus Depot.

      It was submitted that Minutes of the said Meeting were  prepared  only
on 28.10.2015 and, therefore, could not be  placed  before  the  High  Court
when the matter was taken up on 20.10.2015 and impugned order passed.

Another significant development which was pointed out was  the  order  dated
13.01.2015 of the National Green Tribunal passed in OA  No.  6/2012  and  MA
Nos. 967/2013 and 275/2014 in the matter of Manoj Mishra v. Union  of  India
& Ors.  That case pertains to cleaning of River Yamuna.   In  the  aforesaid
order, after  comprehensively  reviewing  the  situation  in  the  light  of
various technical reports etc.,  the  Tribunal  has  given  some  directions
which, inter alia, include  the  direction  to  all  concerned  authorities,
including the DDA, Municipal Corporations and the Govt. of NCT of Delhi,  to
take immediate and effective steps for identification  of  floodplain.   The
Tribunal has directed preparation of a map in  this  regard  and  physically
demarcate  the  entire  floodplain.   There  is  also  a  direction  to  the
Principal Committee to identify which structures were to be  demolished  and
which ones were to be retained, in the interest of ecology and  environment.
 The public interest in retaining the said Bus Depot  was  again  emphasized
and it was submitted that once the aforesaid exercise of demarcation of  the
entire floodplain is carried out by the Principal Committee,  the  stand  of
the appellants would be vindicated that the area in question where  the  Bus
Depot has been constructed does  not  fall  within  the  floodplain  thereby
paving way for the amendment of the Master Plan.

We have considered the respected submissions  of  learned  counsel  for  the
parties on either side.  As is clear from the tenure and spirit  behind  the
orders dated 13.09.2012 passed by the High Court, the chance  was  given  to
the appellants to have the MPD 2021 amended if it  was  permissible  in  law
and the period of six months was given for this purpose.  This was  done  by
the High Court keeping in view the submission of the appellants herein  that
the Bus Depot in question was constructed to serve greater  public  purpose;
the area in question was, as a matter of fact, was not falling on the  river
bed; and there was no threat to environment or ecology  in  having  the  Bus
Depot at the given site.  Exercise to consider the aforesaid aspect has  not
taken place, or for some reason or the other,  whether  it  was  because  of
dispute between L&DO and DDA on the issue of land  ownership  or  otherwise.
However,  the  development  which  have  taken  place   in   recent   times,
particularly the orders of the National Green Tribunal,  point  out  to  the
fact that things are started moving and it would be known in near future  as
a result of study conducted  by  the  Expert   Committee,  whether  area  in
question where the Bus Depot stands, is viable  for  this  purpose  or  not,
directing the DTC to demolish the Bus Depot at  this  juncture  may  not  be
appropriate and the decision in this regard can be deferred  for  some  time
to await the outcome of the report of the identification of floodplain.

Accordingly, we dispose of these appeals by granting one year  time  to  the
DTC during which period the DTC shall  either  get  the  MPD  2021  amended,
failing which it shall shift the Depot in question.      We  make  it  clear
that no further time on any ground  whatsoever  shall  be  granted  in  this
behalf.



                                ….......................................CJI.
                                                                (T.S.THAKUR)


                             .............................................J.
                                                                (A.K. SIKRI)


                             .............................................J.
                                                              (R. BANUMATHI)


NEW DELHI;
FEBRUARY 05, 2016.