Supreme Court of India (Division Bench (DB)- Two Judge)

Appeal (Civil), 13785 of 2015, Judgment Date: Nov 27, 2015

This Court has repeatedly held that where discretion is  required  to
be exercised by a statutory authority, it must be permitted to do so. It  is
not for the courts to take over the  discretion  available  to  a  statutory
authority and render a decision. In the present case,  the  High  Court  has
virtually taken over the function of the BDA by requiring it to take  action
against Sadananda Gowda  and  Jeevaraj.
 In Mansukhlal Vithaldas Chauhan v. State  of  Gujarat[9]  this  Court
held that it is  primarily  the  responsibility  and  duty  of  a  statutory
authority to take a decision and  it  should  be  enabled  to  exercise  its
discretion independently. If  the  authority  does  not  exercise  its  mind
independently, the decision taken by the statutory authority can be  quashed
and a direction given to take an independent decision.
In the performance of this duty, if the authority in whom the discretion  is
vested under the statute, does not act independently  and  passes  an  order
under the instructions and orders of  another  authority,  the  Court  would
intervene in the matter, quash the  order  and  issue  a  mandamus  to  that
authority to exercise its own discretion.”
 To this we may add  that  if  a  court  is  of  the  opinion  that  a
statutory authority cannot take an independent or impartial decision due  to
some external or internal pressure, it must give its reasons for  coming  to
that conclusion. The reasons given by the court for disabling the  statutory
authority from taking a decision can always be tested  and  if  the  reasons
are found to be inadequate,  the  decision  of  the  court  to  by-pass  the
statutory authority can always be set aside.  If  the  reasons  are  cogent,
then in an exceptional case, the court may take a decision  without  leaving
it to the statutory authority to do so. However, we  must  caution  that  if
the court were to take over the  decision  taking  power  of  the  statutory
authority it must  only  be  in  exceptional  circumstances  and  not  as  a
routine.  Insofar as the present case is concerned, the High Court  has  not
given any reason why it virtually took over the decision taking function  of
the authorities and for this reason alone the mandamus issued  by  the  High
Court deserves to be set aside, apart from the merits of the case  which  we
have already adverted to.

                                                                  REPORTABLE

                        IN THE SUPREME COURT OF INDIA

                        CIVIL APPELLATE JURISDICTION

                       CIVIL APPEAL NO. 13785 OF 2015
                (Arising out of S.L.P. (C) No. 37226 OF 2012)


D.N. Jeevaraj                                                   ….Appellant

                                       versus

Chief Secretary,
Govt. of Karnataka & Ors.                                      …Respondents

                                    WITH

                       CIVIL APPEAL NO. 13786  OF 2015
                 (Arising out of S.L.P. (C) No. 38453/2012)


D.V. Sadananada Gowda                                           .….Appellant

                                       versus

K.G. Nagalaxmi Bai & Ors.                                      ….Respondents


                               J U D G M E N T

Madan B. Lokur, J.
1.     Leave granted in both petitions.
2.     The question for consideration is whether the  appellants  (Sadananda
Gowda and Jeevaraj) have per se violated the  terms  of  the  lease-cum-sale
agreement that they  have  individually  entered  into  with  the  Bangalore
Development Authority  (for  short  ‘the  BDA’)  by  constructing  a  multi-
storeyed  residential  building  on  the  plots  allotted   to   them.   The
alternative question is whether the construction made by  them  is  contrary
to the plan sanctioned by the Bruhat Bangalore Mahanagara Palike (for  short
‘the BBMP’) and thereby violated the lease-cum-sale agreement with the  BDA.
The term of the lease-cum-sale agreement alleged to have  been  violated  is
clause 4 which reads as follows:

“4. The Lessee/Purchaser shall not  sub-divide  the  property  or  construct
more than one dwelling house in it.

    The expression ‘dwelling house’ means building constructed  to  be  used
wholly for human habitation and shall not  include  any  apartments  to  the
building whether attached thereto or not, used as a shop or  a  building  of
warehouse or building in  which  manufactory  operations  are  conducted  by
mechanical power or otherwise.

(a)  The Lessee shall plant at least two trees in the site leased to him.”

3.     In our opinion, both the questions are required  to  be  answered  in
the negative. There has been no violation of  the  lease-cum-sale  agreement
or the sanction plan for construction such as to violate the  lease-cum-sale
agreement with the BDA.
The facts
4.     On or about 5th March, 2002 Sadananda Gowda (the then  Deputy  Leader
of the Opposition in the Legislative  Assembly  in  Karnataka)  addressed  a
letter to the Chief Minister of Karnataka  requesting  for  allotment  of  a
plot from the Bangalore Development Authority.  This request was  favourably
considered and he was  allotted  plot  No.  2-B  in  HSR  layout,  Sector-3,
Bangalore measuring 50 ft x 80 ft. on 30th August,  2006  in  terms  of  the
Bangalore  Development  Authority  (Site  Allotment)  Rules,   2006.[1]   In
accordance with  the  required  formalities,  Sadananda  Gowda  executed  an
affidavit on 1st September, 2006 in the form of an undertaking with the  BDA
in which it was stated as follows:-

“4. In the event that any false statements  or  declarations  furnished  and
sworn to and declared in this Affidavit and in the event that I violate  any
conditions of site allotment, the Authorities are empowered to  resume  such
building and site without  granting  any  compensation  to  me  and  BDA  is
entitled to and empowered to resume the site for  which  BDA  is  authorized
and I hereby declare so and I hereby swear accordingly.”

Pursuant to the execution of the affidavit and completion of  all  necessary
administrative formalities, the BDA executed a lease-cum-sale  agreement  in
favour of Sadananda Gowda on 2nd February, 2007 and on the same  day  handed
over possession of the plot to him.
5.     As far as Jeevaraj is concerned, he too made a request  on  or  about
14th September, 2004 for the allotment of a plot to the  Chief  Minister  of
Karnataka and was allotted a plot  by  the  BDA.  Subsequently  and  on  his
request, the allotment was changed to plot no. 13-B in HSR  layout,  Sector-
3, Bangalore on 30th October, 2008. The area of Jeevaraj’s plot is  also  50
ft. x 80 ft. and it is adjacent to the plot  allotted  to  Sadananda  Gowda.
Jeevaraj too completed all  necessary  administrative  formalities  and  was
handed over possession of the plot on 24th November, 2008.
6.     On 4th  June,  2009  both  Sadananda  Gowda  and  Jeevaraj  moved  an
application before the BDA to  amalgamate  their  plots.   The  request  was
rejected by the BDA and communicated to them on  24th  September,  2009  and
there is no dispute or doubt with regard to the validity of the reasons  for
turning down the proposal for amalgamation.
7.      Thereafter,  both  Sadananda  Gowda  and  Jeevaraj   made   separate
applications for sanction of a building plan  to  the  BBMP.   The  building
plans were for the construction  of  a  ground/stilt  floor  and  two  upper
floors. The plans were considered by the BBMP and sanctioned on  22nd  July,
2010.  At this stage, it may be noted that there  was  some  confusion  with
regard to the sanctioned construction but during the course  of  hearing  it
was clarified that the sanction was for a ground/stilt floor and  two  upper
floors.
8.     Based on the sanction so granted, the construction of  the  buildings
began on the plots owned by Sadananda Gowda and Jeevaraj.
9.     On 2nd August, 2011 the Bangalore Mirror newspaper  carried  a  story
alleging that Sadananda Gowda was making  an  illegal  construction  on  the
plot allotted to him  and  Jeevaraj  by  amalgamating  the  two  plots.  The
newspaper  carried  photographs  of  the  construction  which   showed   one
composite building under construction on the two plots and  it  was  alleged
that the building under construction was a five storeyed  building.  It  was
also alleged that a part of the building  was  to  be  used  for  commercial
purposes although the allotment was for a residential purpose.
10.    Apparently based  on  the  newspaper  report  (and  perhaps  her  own
research) one Nagalaxmi Bai filed a Writ  Petition  in  the  Karnataka  High
Court on 4th August, 2011 wherein a prayer was made for a  declaration  that
the building being constructed on the  plots  above  mentioned  having  been
allotted to Sadananda Gowda by the BDA is an illegally constructed  building
and that the BDA ought to resume  the  site  along  with  the  building  and
forfeit any amount paid in this behalf by Sadananda Gowda.  The  parties  to
the writ petition were the State of Karnataka (respondent  Nos.  1  and  2),
the BDA (respondent No. 3), the Commissioner of  Police  (respondent  No.  4
but later deleted) and Sadananda Gowda (respondent No. 5). Later,  the  BBMP
was impleaded as respondent No. 6 and Jeevaraj was impleaded  as  respondent
No. 7 in the High Court.
11.    For the record, it may be mentioned that on 4th August, 2011 the  day
the writ petition was filed, Sadananda Gowda  was  appointed  as  the  Chief
Minister of Karnataka.
12.    The essence of the grievance of Nagalaxmi Bai was that first  of  all
the two adjacent plots were amalgamated despite refusal by  the  BDA  and  a
composite or consolidated building was  impermissibly  constructed  on  them
and therefore there was a  per  se  violation  of  the  lease-cum-sale  deed
entered into by Sadananda Gowda and Jeevaraj  with  the  BDA.  Secondly  the
constructed  building  was  not  in  conformity  with  the  sanctioned  plan
approved by the BBMP and therefore there was a violation of  the  lease-cum-
sale agreement with the BDA and the affidavit in the form of an  undertaking
given to the BDA. It was also alleged that contrary  to  the  lease-cum-sale
deed, the building was intended to be used for commercial  purposes.   These
were the three principal grievances raised by Nagalaxmi Bai.
13.    The High Court admitted the writ petition and issued  notice  to  the
respondents on 10th January, 2012.
14.    In the meanwhile, Sadananda Gowda  and  Jeevaraj  moved  applications
for modification of the sanctioned building plan. There is no  dispute  that
this was permissible. The request was considered by the  BBMP  and  on  26th
September/3rd October, 2011 sanction was granted for the construction  of  a
basement,  ground  floor  and  three  upper  floors  on  each  plot.   After
admission of the writ petition,  the  modified  building  plan  was  further
modified on the request of Sadananda Gowda  and  Jeevaraj  and  construction
was permitted by the BBMP on  12th  June/22nd  June,  2012  for  a  building
having a  basement,  ground  floor  and  three  upper  floors  entirely  for
residential purposes.
Responses in the High Court
15.    In response to the writ petition, affidavits were filed by  the  BDA,
the BBMP, Sadananda Gowda and Jeevaraj.
16.    The BDA denied that the two plots in question  had  been  amalgamated
and it also stated that it had  no  role  in  the  sanctioning  of  building
plans. The BBMP stated that the allegation that  a  five  storeyed  building
had been constructed was not correct nor was it correct  that  the  building
was being used for commercial purposes. In fact, it was submitted  that  the
construction had not been completed and so it could not be assumed that  the
building was in violation of the sanctioned building  plans  or  was  to  be
used for commercial purposes. Attention was drawn  to  Section  310  of  the
Karnataka  Municipal  Corporations  Act,  1976[2]  which  provided  that   a
building cannot be occupied or permitted to be occupied  without  permission
from the Commissioner.[3] It was submitted that  Sadananda  Gowda  would  be
permitted to occupy the building only after an inspection  of  the  building
and compliance with the sanctioned plan.
17.    The BBMP further stated (in the additional  statement  of  objections
filed on 9th October, 2012 just a few days before  judgment  was  delivered)
that the permissible floor area ratio of the plot in question  is  2.25  and
the  permissible  coverage  is  65%.  However,  since  Sadananda  Gowda  had
purchased transferable development rights, he is entitled to  a  floor  area
ratio of 3.60 and permissible coverage is 82.5%. The BBMP gave  a  chart  of
the permissible floor area ratio, the permissible  coverage  area  and  what
has been achieved in the modified sanctioned plan. This is as follows:
|S.No. |Details            |As per the      |Achieved as against   |
|      |                   |modified plan   |the modified plan     |
|1.    |Permissible floor  |3.60            |2.562                 |
|      |area ratio         |                |                      |
|2.    |Permissible        |82.50%          |64.03%                |
|      |coverable area     |                |                      |

It was  specifically  stated  by  the  BBMP  that  “The  modified  plan  now
sanctioned is purely for residential purpose.” The BBMP further stated  that
an inspection of the building was carried out  by  the  Assistant  Director,
Town Planning and Assistant Executive Engineer of the  BBMP  with  reference
to the sanctioned plan.  During  the  inspection,  certain  deviations  were
noticed and appropriate action would be  taken  in  that  regard  under  the
Karnataka Municipal Corporations  Act  and  that  an  occupancy  certificate
would be issued only after the  BBMP  is  satisfied  that  the  construction
meets the requirements of law.
18.    Sadananda Gowda also filed an affidavit in the High  Court  in  which
he denied any violation of the lease-cum-sale agreement  or  the  sanctioned
building plan. He denied that a five storeyed building  was  constructed  or
that the two plots in question were amalgamated. He submitted that  an  area
of 20% could be earmarked for  commercial  activity  and  that  he  had  not
violated the sanctioned building plan. Jeevaraj also filed a  more  or  less
similar affidavit emphasizing, however, that no relief was  claimed  against
him in the writ petition.
Decision of the High Court
19.    After going through the affidavits filed by the various  parties  and
after hearing learned counsel, the High  Court  allowed  the  writ  petition
filed by Nagalaxmi Bai  by  its  impugned  judgment  and  order  dated  19th
October, 2012. The High Court held that the two  plots  of  Sadananda  Gowda
and Jeevaraj were amalgamated despite the refusal to grant permission to  do
so by the BDA and also that a ‘homogenous structure’  had  come  up  on  the
amalgamated plots. There was, therefore, a violation of condition No.  4  of
the lease-cum-sale agreement. The High Court also  held  that  the  building
plan sanctioned by  the  BBMP  on  22nd  July,  2010  was  in  violation  of
condition No. 4 of the lease-cum-sale  agreement  and  that  the  subsequent
modifications were an exercise in ‘belated damage control’. The  High  Court
considered the decision of  this  Court  in  R  &  M  Trust  v.  Koramangala
Residents Vigilance Group[4] and held it inapplicable to the  facts  of  the
case. Accordingly,  the  High  Court  quashed  the  orders  sanctioning  the
building construction plans in favour of Sadananda  Gowda  and  Jeevaraj  by
the BBMP and directed the BDA to  take  action  against  them  in  terms  of
condition No. 4 of the lease-cum-sale agreement as well as the affidavit  in
the form of an undertaking given by them to  the  BDA  for  abiding  by  the
terms and conditions thereof and the allotment rules.
20.    The sum and substance of the decision of the  High  Court  is  to  be
found in paragraph 53 and paragraph 61 thereof and these read as follows:
“53. From the facts pleaded and materials on record and even  the  averments
as contained in the statements of objections filed on behalf of  respondents
and annexures such  as  photographs  produced  by  the  petitioner  and  the
respondents, it cannot  be  disputed  nor  in  any  manner  doubted  that  a
homogenous structure which has been characterized as one  plus  four  floors
or otherwise, had been put up  and  this  construction  has  come  up  after
rejection of a joint request  of  the  fifth  and  seventh  respondents  for
amalgamating the two sites and putting up a commercial complex  or  combined
structure, is a structure which is flawed from the  very  beginning  and  is
clearly in contravention of the order passed by BDA  rejecting  the  request
of the fifth and seventh respondents for amalgamating the two sites.   Apart
from enabling provisions of the  building  byelaws  and  zonal  regulations,
which  are  brought  to  our  attention,  which  may,  perhaps,   enable   a
modification of the plans and a revised plan may be  permitted,  if  all  is
within the limits of law and not prohibited by a basic law.  In the  instant
case, as is pointed out by the  learned  counsel  for  the  petitioner,  the
construction initially was in violation of condition No. 4 of the lease-cum-
sale agreement and also therefore violating affidavit of undertaking.”

Paragraph 61 of the decision of the High Court reads as follows:

“61. The municipal  authority,  if  at  all,  is  only  concerned  with  the
building plan being  in  conformity  with  the  zonal  regulations  and  the
building bye-laws.  At the same time, conditions that  are  incorporated  in
the lease-cum-sale agreement are also to  be  looked  into.  The  manner  in
which the initial plan is sanctioned by the municipal authorities  approving
construction of ground plus two floors in itself  indicates  that  they  are
overlooking condition No. 4 of the lease-cum-sale agreement.   Whether  this
initial plan can be characterized  as  a  valid  one  or  otherwise,  it  is
obviously one overlooking one of the conditions of allotment  and  therefore
the allottees, who are very much aware of the conditions imposed on them  by
BDA, cannot take advantage of this plan sanctioned by BBMP to sustain  their
action which is initially flawed and contrary to the terms of  allotment  to
contend that it is based on a  valid  initial  plan  and  revised  plans  as
permitted in law as per the bye-laws etc.”

21.    Feeling aggrieved, Sadananda Gowda and Jeevaraj have preferred  these
appeals.
Discussion
22.    It appears to us, on a plain reading of condition No. 4 of the lease-
cum-sale  agreement  that  it  is   breached   or   violated   under   three
circumstances: (i) If the plot is sub-divided  or  (ii)  If  more  than  one
building is constructed thereon for the  purposes  of  human  habitation  or
(iii) If an apartment whether attached to the building or not is used  as  a
shop or a warehouse etc.
23.     As  far  as  the  first  circumstance  is  concerned,  there  is  no
allegation that either Sadananda Gowda or Jeevaraj  have  sub-divided  their
respective plot. The allegation (though denied) is to  the  contrary,  which
is that they have  amalgamated  their  plots.  Assuming  the  allegation  is
substantiated, it can be said at best, that they have acted contrary to  the
letter dated 24th September, 2009 but there is no  breach  or  violation  of
condition No. 4 of the lease-cum-sale agreement.  The  effect,  if  any,  of
acting contrary to the letter  dated  24th  September,  2009  has  not  been
canvassed or agitated. In any event, the case set up  by  Nagalaxmi  Bai  is
not of a violation of the  letter  dated  24th  September,  2009  but  of  a
violation of condition No. 4 of the lease-cum-sale  agreement.  Under  these
circumstances, frankly, we fail to understand how it has been found  by  the
High Court that amalgamation of the two plots (assuming it to be  so)  is  a
breach or violation of the lease-cum-sale agreement.  Be  that  as  it  may,
factually there is no sub-division of the plots and to that extent there  is
no violation of condition No. 4 of the lease-cum-sale agreement.
24.    As regards the second and third circumstance,  it  is  nobody’s  case
that more than one building has been constructed on either of the  plots  or
that the building or any part thereof is used as a shop  or  warehouse  etc.
Therefore, this need not detain us any further, more particularly since  the
buildings are not yet completely constructed.
25.    The grievance of  Nagalaxmi  Bai  is  that  the  photographs  of  the
building indicate that the construction on  the  two  plots  is  actually  a
composite or a combined or a homogenous structure and that  construction  is
per se in violation of condition No.4 of the  lease-cum-sale  agreement.  It
is her further grievance  that  after  the  writ  petition  was  filed  both
Sadananda Gowda and Jeevaraj made some changes and demolished a part of  the
structure by way of damage control so  that  it  appears  that  there  is  a
separate building on each plot. It is submitted that once the  condition  of
the lease-cum-sale agreement is breached, the demolition of a  part  of  the
combined or composite or homogenous structure  cannot  undo  or  remedy  the
violation that has already occurred.
26.    We are not in agreement with the contention  advanced  on  behalf  of
Nagalaxmi Bai in this regard.  The writ petition was filed by her at a  time
when the construction was in progress – in fact, it is still  not  complete.
It is true that substantial  progress  was  made  in  the  construction  but
nevertheless Sadananda Gowda and Jeevaraj could make changes  therein  until
the grant of an occupancy certificate by the BBMP. It would be  a  bit  far-
fetched to assume, in a  case  such  as  the  present,  that  an  incomplete
structure that can be modified is per se contrary to the  building  bye-laws
or the lease-cum-sale agreement especially  when  changes  or  modifications
could be made therein. Corrective measures can always be made by  the  owner
of a building until an occupancy certificate or a completion certificate  is
granted. It is perhaps pursuant to this ‘entitlement’ to make  changes  that
both Sadananda Gowda and Jeevaraj appreciated that  were  the  structure  to
remain as it is, an occupancy certificate might not be granted by  the  BBMP
and that is perhaps why there was a partial  demolition  of  the  structure.
They cannot  be  faulted  for  taking  corrective  steps,  however  belated,
whether they were voluntary or prompted by the writ petition, or otherwise.
27.    An analogy may be drawn in this connection with regard to  deviations
that sometimes  come  up  in  constructed  buildings.  Some  deviations  are
compoundable and some are not  and  those  that  are  not  compoundable  are
required to be rectified before an occupancy  certificate  or  a  completion
certificate is granted.  Merely because a building has some deviations  from
the sanctioned plan, either  at  the  initial  stage  or  later  on  in  the
construction, does not necessarily mean that  the  construction  is  per  se
illegal unless the deviations are irremediable, in which event an  occupancy
certificate or completion certificate will  not  be  granted.   Changes  and
modifications may be made as required by the building  bye-laws  or  by  the
municipal authority and this is precisely what has happened so  far  as  the
present case is concerned, which  is  that  to  bring  the  construction  in
conformity with the  building  regulations,  a  part  of  the  building  was
demolished  by  Sadananda  Gowda  and  Jeevaraj.  The  stage  at  which  the
modifications are made is not of any consequence, as long as they  are  made
before the occupancy certificate or a completion certificate is granted.
28.    Nagalaxmi Bai is also  aggrieved  that  multi-storeyed  constructions
have come up on the two plots. Like it or not, condition No. 4 of the lease-
cum-sale agreement does not prohibit the construction  of  a  multi-storeyed
building on the plot as long as the construction  is  of  a  dwelling  house
which is used wholly for human habitation and not as a shop or  a  warehouse
or for other commercial purposes. As long as the building  conforms  to  the
terms of the lease-cum-sale agreement and the building regulations and  bye-
laws, no objection can be  taken  to  the  construction,  however  large  or
ungainly it might be. In this regard, the BDA is on record  to  specifically
say that there is no violation of the lease-cum-sale agreement and the  BBMP
is on record to say that there is  no  violation  of  the  sanctioned  plan,
except for some deviations. The BBMP is also on record to  say  that  unless
the buildings are in conformity with the sanctioned plan  and  the  building
regulations, no occupancy certificate will be  granted  to  Sadananda  Gowda
and Jeevaraj. The matter should rest at that.
29.    In our opinion, the  High  Court  was  in  error  in  coming  to  the
conclusion that the buildings constructed on  the  two  plots  were  not  in
accordance with the sanctioned plan. The buildings were and are still  under
construction and it is too early to say that there has been a  violation  of
the sanctioned plan. No doubt there are some deviations as  pointed  out  by
the BBMP but that  is  a  matter  that  can  certainly  be  attended  to  by
Sadananda Gowda and Jeevaraj on the one hand and  the  BBMP  on  the  other.
The mere existence of some deviations in the buildings does not lead to  any
definite conclusion that  there  is  either  a  breach  or  a  violation  of
condition No. 4  of  the  lease-cum-sale  agreement  or  the  building  plan
sanctioned by the BBMP.
30.    Another grievance of Nagalaxmi Bai is that the construction  is  such
that the building is capable of being used  as  a  commercial  complex.  For
instance, some photographs show that shutters  have  been  put  up  and  the
contention is that actually some shops have been constructed with  shutters.
As mentioned above, the building is not yet complete  and  we  cannot  guess
why shutters have been put up by Sadananda Gowda and Jeevaraj.  There  might
or might not be a good reason for it. Nothing can be assumed either way.  We
also cannot ignore the contention put forward that 20% of the  building  can
be permissibly used for a commercial purpose. If the putting up of  shutters
is suggestive of unlawful commercial use of a part of the building, the  BDA
and the BBMP will certainly consider the matter for whatever  it  is  worth,
including whether 20% of the building can be commercially exploited or  not.

31.    It is finally contended that what we are effectively required  to  do
is to lift the veil, so to speak, and appreciate that Sadananda Gowda is  an
influential  politician  and  can  muscle  his  way   with   the   statutory
authorities. The  contention  is  that  Sadananda  Gowda  was  (and  is)  an
influential politician in Karnataka and was also its Chief Minister  at  the
relevant time  and  that  made  it  impossible  for  any  of  the  statutory
authorities to come to any conclusion adverse to his interest despite an  ex
facie and egregious violation of  condition  No.  4  of  the  lease-cum-sale
agreement. It is difficult  to  accept  such  a  blanket  and  free-wheeling
submission, particularly in the absence of  any  material  on  record.  That
apart, it may be  recalled  that  even  when  Sadananda  Gowda  applied  for
amalgamation of his plot with  that  of  Jeevaraj,  he  was  an  influential
politician  in  Karnataka  being  the  Deputy  Leader  of  the   Opposition.
Notwithstanding this, the BDA rejected the request of amalgamating his  plot
with that Jeevaraj’s plot.  Additionally, even while  Nagalaxmi  Bai’s  writ
petition was pending in the High Court and Sadananda  Gowda  was  the  Chief
Minister of Karnataka, an inspection of the premises was carried out by  the
Assistant Director, Town Planning and the Assistant  Executive  Engineer  of
the BBMP.  They pointed out certain deviations in the construction  and  the
BBMP did state on affidavit that appropriate action would be taken  in  this
regard and that an occupancy certificate would  be  issued  only  after  the
BBMP is satisfied that the construction is in accordance  with  law.  It  is
difficult  to  assume,  under  these  circumstances,  that  Sadananda  Gowda
exercised his influence as the Chief Minister of Karnataka to arm-twist  the
BBMP since the inspection report was not entirely in his favour.
32.    This is not to say that in no circumstance can a statutory  body  not
be influenced by a politician who has considerable clout.  A lot depends  on
the facts of each case and the surrounding circumstances.   Insofar  as  the
present case is concerned, in spite of the clout that  Sadananda  Gowda  may
have wielded in Karnataka, his actions relating to the construction  of  the
building on his plot of land do not suggest any abuse, as  mentioned  above.
Undoubtedly, there are  some  deviations  in  the  construction  which  will
surely be taken care of by  the  BBMP  which  has  categorically  stated  on
affidavit that an occupancy certificate will be given only if  the  building
constructed conforms to the sanctioned plan and the building bye-laws.
33.    In view of the above, we find no good  reason  to  uphold  the  order
passed by the High Court allowing the writ petition and  it  is  accordingly
set aside.
Public interest litigation
34.    Learned counsel for the parties addressed us on the question  of  the
bona fides of Nagalaxmi Bai in  filing  a  public  interest  litigation.  We
leave this question open and do not express any opinion on  the  correctness
or otherwise of the decision of the High Court in this regard.
35.    However, we note that generally speaking,  procedural  technicalities
ought to take a back seat in public interest litigation. This Court held  in
Rural Litigation and Entitlement Kendra v. State of U.P.[5] to  this  effect
as follows:
“The writ petitions before us are not inter-partes disputes  and  have  been
raised by way of public interest litigation and the controversy  before  the
court is as to whether for social  safety  and  for  creating  a  hazardless
environment for the people  to  live  in,  mining  in  the  area  should  be
permitted or stopped. We may not be taken  to  have  said  that  for  public
interest litigations, procedural laws do not apply. At the same time it  has
to be remembered that every  technicality  in  the  procedural  law  is  not
available as a defence when a matter  of  grave  public  importance  is  for
consideration before the court.”

36.    A considerable amount has been said about public interest  litigation
in R & M Trust and it is not necessary for us to dwell any further  on  this
except to say that in issues  pertaining  to  good  governance,  the  courts
ought  to  be  somewhat  more  liberal  in  entertaining   public   interest
litigation.  However, in matters that may not be of moment or  a  litigation
essentially directed against one organization or  individual  (such  as  the
present litigation which was  directed  only  against  Sadananda  Gowda  and
later Jeevaraj was impleaded) ought not  to  be  entertained  or  should  be
rarely entertained. Other remedies are also  available  to  public  spirited
litigants and they should be encouraged to avail of such remedies.
37.    In such cases, that might  not  strictly  fall  in  the  category  of
public interest litigation and  for  which  other  remedies  are  available,
insofar as the issuance of a writ of mandamus is concerned, this Court  held
in Union of India v. S.B. Vohra[6] that:

“Mandamus literally means a command. The essence of mandamus in England  was
that it was a royal command issued by the King’s Bench (now  Queen’s  Bench)
directing performance of a public legal duty.

A writ of mandamus is issued in favour of a person who establishes  a  legal
right in himself. A writ of mandamus is issued against a person  who  has  a
legal duty to perform but has failed and/or  neglected  to  do  so.  Such  a
legal duty emanates from  either  in  discharge  of  a  public  duty  or  by
operation of law. The writ of mandamus  is  of  a  most  extensive  remedial
nature. The object of mandamus is to prevent  disorder  from  a  failure  of
justice  and  is  required  to  be  granted  in  all  cases  where  law  has
established no specific remedy and whether justice despite demanded has  not
been granted.”

38.    A salutary principle or a well recognized rule that needs to be  kept
in  mind  before  issuing  a  writ  of  mandamus  was  stated  in  Saraswati
Industrial Syndicate Ltd. v. Union of India[7] in the following words:

“The powers of the High Court under Article 226 are  not  strictly  confined
to the limits to which proceedings for  prerogative  writs  are  subject  in
English practice. Nevertheless, the well recognised rule  that  no  writ  or
order in the nature of a mandamus would issue when there is  no  failure  to
perform a mandatory duty applies in this country as well. Even in  cases  of
alleged breaches of mandatory duties, the salutary general  rule,  which  is
subject to certain exceptions, applied by us, as it is in  England,  when  a
writ of mandamus is asked for, could be stated as we  find  it  set  out  in
Halsbury’s Laws of England (3rd Edn.), Vol. 13, p. 106):
“As a  general  rule  the  order  will  not  be  granted  unless  the  party
complained of has known what it was he was required to do, so  that  he  had
the means of considering whether or not he should comply,  and  it  must  be
shown by evidence that there was a distinct demand of that which  the  party
seeking the mandamus desires to enforce, and that that demand was met  by  a
refusal.”
In the cases before us there was no such demand or refusal. Thus, no  ground
whatsoever is shown here for the issue of  any  writ,  order,  or  direction
under Article 226 of the Constitution.”

39.    It  is  not  necessary  for  us  to  definitively  pronounce  on  the
contention of learned counsel for Sadananda  Gowda  and  Jeevaraj  that  the
litigation initiated by Nagalaxmi Bai was not a public  interest  litigation
or that no mandamus ought to have been issued by the  High  Court  since  no
demand was made nor was there any refusal to meet that  demand.  But  we  do
find it necessary to reaffirm the law should a litigant be  asked  to  avail
of remedies that are not within the purview of public interest litigation.
Exercise of discretion
40.    Learned counsel for Sadananda Gowda and Jeevaraj  also  addressed  us
on  the  issue  that  the  High  Court  had  exceeded  its  jurisdiction  in
questioning the sanctioning of the building plans by the  BBMP  and  further
mandating the BDA to take action against Sadananda  Gowda  and  Jeevaraj  in
terms of condition No. 4 of the lease-cum-sale agreement and  the  affidavit
undertaking given by them, thereby effectively requiring the BDA to  forfeit
the lease.
41.    This Court has repeatedly held that where discretion is  required  to
be exercised by a statutory authority, it must be permitted to do so. It  is
not for the courts to take over the  discretion  available  to  a  statutory
authority and render a decision. In the present case,  the  High  Court  has
virtually taken over the function of the BDA by requiring it to take  action
against Sadananda Gowda  and  Jeevaraj.  Clause  10  of  the  lease-cum-sale
agreement gives discretion to the BDA to take action against the  lessee  in
the event of a default in payment  of  rent  or  committing  breach  of  the
conditions of the lease-cum-sale agreement  or  the  provisions  of  law.[8]
This will, of course, require a notice being given to the alleged  defaulter
followed by a hearing and then a decision in the  matter.   By  taking  over
the functions of the BDA  in  this  regard,  the  High  Court  has  given  a
complete  go-bye  to  the  procedural  requirements  and  has   mandated   a
particular course of action to be taken by the BDA.  It  is  quite  possible
that  if  the  BDA  is  allowed  to  exercise  its  discretion  it  may  not
necessarily direct forfeiture of the lease but that was sought  to  be  pre-
empted by the direction given by the  High  Court  which,  in  our  opinion,
acted beyond its jurisdiction in this regard.
42.    In Mansukhlal Vithaldas Chauhan v. State  of  Gujarat[9]  this  Court
held that it is  primarily  the  responsibility  and  duty  of  a  statutory
authority to take a decision and  it  should  be  enabled  to  exercise  its
discretion independently. If  the  authority  does  not  exercise  its  mind
independently, the decision taken by the statutory authority can be  quashed
and a direction given to take an independent decision. It was said:
“Mandamus  which  is  a  discretionary  remedy  under  Article  226  of  the
Constitution is requested to be issued, inter alia,  to  compel  performance
of public duties which may be administrative, ministerial  or  statutory  in
nature. Statutory duty may  be  either  directory  or  mandatory.  Statutory
duties, if they are intended to be mandatory in character, are indicated  by
the use of the words “shall” or  “must”.  But  this  is  not  conclusive  as
“shall” and “must” have, sometimes,  been  interpreted  as  “may”.  What  is
determinative of the nature of duty, whether it is obligatory, mandatory  or
directory, is the scheme of the statute in which the  “duty”  has  been  set
out. Even if the “duty” is not set  out  clearly  and  specifically  in  the
statute, it may be implied as correlative to a “right”.

In the performance of this duty, if the authority in whom the discretion  is
vested under the statute, does not act independently  and  passes  an  order
under the instructions and orders of  another  authority,  the  Court  would
intervene in the matter, quash the  order  and  issue  a  mandamus  to  that
authority to exercise its own discretion.”

43.    To this we may add  that  if  a  court  is  of  the  opinion  that  a
statutory authority cannot take an independent or impartial decision due  to
some external or internal pressure, it must give its reasons for  coming  to
that conclusion. The reasons given by the court for disabling the  statutory
authority from taking a decision can always be tested  and  if  the  reasons
are found to be inadequate,  the  decision  of  the  court  to  by-pass  the
statutory authority can always be set aside.  If  the  reasons  are  cogent,
then in an exceptional case, the court may take a decision  without  leaving
it to the statutory authority to do so. However, we  must  caution  that  if
the court were to take over the  decision  taking  power  of  the  statutory
authority it must  only  be  in  exceptional  circumstances  and  not  as  a
routine.  Insofar as the present case is concerned, the High Court  has  not
given any reason why it virtually took over the decision taking function  of
the authorities and for this reason alone the mandamus issued  by  the  High
Court deserves to be set aside, apart from the merits of the case  which  we
have already adverted to.
Conclusion
44.    Therefore, whichever way the decision of the  High  Court  is  looked
at, in our opinion, the conclusions arrived at and the directions given  are
not sustainable in law and are  set  aside.   The  appeals  are  accordingly
allowed.


                                                               ...…………………….J
                                                            (Madan B. Lokur)


New Delhi;                                                     ...…………………….J  
 November  27,  2015
                                                                (S.A. Bobde)


-----------------------
[1]  Learned counsel for Nagalaxmi  Bai  mentioned  that  the  discretionary
allotment was not warranted but that was not pressed  nor  is  it  an  issue
before us.

[2]  Section 310 - Completion certificate and permission to occupy or use
    (1) Every person shall, within one month after  the  completion  of  the
erection of a building or the execution of any such work,  deliver  or  send
or cause to be delivered or sent to the Commissioner at  his  office  notice
in writing of such completion, accompanied by  a  certificate  in  the  form
prescribed in the bye-laws signed and subscribed in  the  manner  prescribed
and shall  give  to  the  Commissioner  all  necessary  facilities  for  the
inspection of such buildings or of such work and shall apply for  permission
to occupy the building.
    (1A)  Notwithstanding  anything  contained  in  sub-section  (1),  where
permission is granted to any person for erection of a building  having  more
than one floor, such person shall, within  one  month  after  completion  of
execution of any of the floors of such building, deliver or  send  or  cause
to be delivered or sent to the Commissioner  at  his  office,  a  notice  in
writing of  such  completion  accompanied  by  a  certificate  in  the  form
prescribed in the bye-laws, signed and subscribed in the  manner  prescribed
and shall give to the Commissioner all necessary facilities  for  inspection
of such floor of the building and may apply for permission  to  occupy  such
floor of the building.
     (2)  No  person  shall  occupy  or  permit  to  be  occupied  any  such
building, or part of the building or use or permit to be used  the  building
or part thereof affected by any work, until,-
    (a) permission has been received from the Commissioner in  this  behalf,
or
    (b) The Commissioner has failed for thirty days  after  receipt  of  the
notice of completion to intimate his refusal of the said permission.
[3]  This is usually known as a ‘completion certificate’  or  an  ‘occupancy
certificate’
[4]  (2005) 3 SCC 91
[5]  1989 Supp (1) SCC 504
[6]  (2004) 2 SCC 150
[7]  (1974) 2 SCC 630
[8]  In the event of the Lessee/Purchaser committing default in the  payment
of rent or committing breach of any conditions  of  this  agreement  or  the
provisions of the Bangalore  Development  Authority,  (Allotment  of  Sites)
Rules, the Lessor/Vendor may determine the tenancy at any time after  giving
the Lessee/Purchaser fifteen days  notice  ending  with  the  month  of  the
tenancy, and take possession of the property.  The  Lessor/Vendor  may  also
forfeit twelve and a half per  cent  of  the  amounts  treated  as  security
deposit under clause of these presents.
[9]  (1997) 7 SCC 622