Supreme Court of India (Division Bench (DB)- Two Judge)

Appeal (Civil), 10531 of 2014, Judgment Date: Nov 25, 2014

                                                                  REPORTABLE


                        IN THE SUPREME COURT OF INDIA


                        CIVIL APPELLATE JURISDICTION


                      CIVIL APPEAL NO.   10531 OF 2014

              (ARISING OUT OF SLP (CIVIL) NO.14767 OF 2012)




Associate Builders                                            ...Appellant

                                   Versus

Delhi Development Authority                                  ...Respondent



                               J U D G M E N T


R.F.Nariman,J.




1.    Leave granted.


2.    The appellant herein was awarded a certain construction work  contract

by the DDA vide a letter of award dated 14th May, 1992.  DDA was building  a

colony consisting of 7,000 houses in Trilok Puri in the  trans-Yamuna  area.

168 Middle Income Group houses and 56 Lower  Income  Group  houses,  Grade-A

Pocket-  B  (balance  work)  was  awarded  for  the   tendered   amount   of

Rs.87,66,678/-. The contract was to be completed in  9  months.  Admittedly,

it was ultimately completed only in 34  months,  the  contractor  completing

166 Middle Income Group houses and 36 Lower Income Group houses.  The  total

value of work that was done  amounted  to  Rs.62,84,845/-.  As  many  as  15

claims were made by the contractor and the High  Court  of  Delhi  appointed

one Shri K.D. Bali to arbitrate the present dispute.


3.    We are concerned here with claims 9, 10, 11 and 15, for  these  claims

have been allowed by the Arbitrator  and  the  DDA's  objections  have  been

dismissed by the learned Single Judge  of  the  High  Court  of  Delhi.  The

Division Bench in an appeal under Section 37 of the  Arbitration  Act,  1996

has stepped in to set aside the judgment of the Single  Judge  and  negative

these claims.  We are also concerned with claims 12 and 13 which  have  been

scaled down by the Division Bench.


4.    Claims 9, 10, 11 and 15 read as follows:


"Claim No.9: Claimants claim Rs. 20,950/- on  account  of  hire  charges  of

centering shuttering due to delay in laying of conduiting.


a) That the respondents had granted certain work of electrification but  the

said agency did not lay the conduit  resulting  in  delay  in  removing  the

shuttering  and  causing  hire  charges.  This  fact  was  reported  to  the

respondents vide claimant's letter dated 30.10.92 followed by reminders  and

also found place in hindrance register.


b) That this is the actual expenditure incurred and  thus  the  claimant  is

entitled for its refund.


c) That the detailed break-up of this claim has been appended separately.


Claim  No.10:  Claimants  claim  Rs.33,450/-  being  the  hire  charges   of

shuttering due to stoppage of work in block no. 100 and 101.


a) That the department had virtually stopped the work in block 100 & 101  on

20.7.93 and it continued up to 26.2.94.  During  this  period  no  work  was

allowed to be  executed  in  these  two  blocks  resulting  in  blockade  or

centering and shuttering in the said two blocks.


b) That by stoppage of work in these two blocks the claimants  had  suffered

hire charges of shuttering due to respondent's lapses and defaults.


c)  It is further stated that there was no  justification  for  stoppage  of

work and the action was arbitrary and totally unjust.


d) That the detail of this claim has been outlined and  appended  separately

and the same shall from part of the statement of facts.


Claim No. 11: Rs.2,00,000/- payable as damages on account  of  hire  charges

of tools & plants and scaffolding.


a) That due to prolongation of the contract on account  of  the  respondents

the claimants had to maintain tools & plants, scaffolding  etc,  during  the

prolongation of the contract resulting in expenditure for the same.


b)  That the said articles remained at site  beyond  the  stipulated  period

and the claimants suffered loss due to the said prolongation.


Claim  No.  15:  Claimants  claim  damages  Rs.6,25,979/-  on   account   of

establishment due to prolongation of the contract.


a) That the claimants had contemplated maintenance of  establishment  during

stipulated period of completion but the work was prolonged  due  to  various

delays and defaults on the part of the respondents.


b) It is further stated that the claimants  had  to  pay  the  establishment

payment during prolongation and the said expenditure  was  unproductive  and

un contemplated.


c) It is further stated that  the  claimants  had  maintained  establishment

beyond the stipulated completion due to the  respondent's  breach  and  thus

entitled for payment.


d) That the respondents were also aware that  the  claimant  has  maintained

regular establishment and thus, incurred expenditure and the  claimants  had

also made several representations."




Claims 12 and 13 read as follows:


"Claim No. 12: Claimants claim Rs.7,12,394/- as damages @20%  for  execution

of the work.


a) That the work was delayed because of the Respondents for the  reasons  as

set out in the letter indicating hindrances encountered during execution  of

the work resulting delay in execution  of  the  work  for  a  period  of  25

months.


b) It is further stated  that  the  claimants  incurred  unproductive  after

stipulated date of completion.


c)   It is further stated that during  prolongation  there  had  been  steep

rise in cost of material and labour.


d) That the claim of 20% is also lent support from the cost index as  issued

by the competent authority  and  only  applicable  on  the  work  which  was

executed during prolongation.


e) That as per cost index it comes to more than 30%  whereas  the  claimants

had claimed 20 & being highly rational and just.


f) That the claimants had appended the  details  of  this  claim  separately

based on cost index to show that the claimant  had  actually  incurred  this

additional expenditure due  to  the  respondents.  Copy  of  the  hindrances

encountered  during  the  execution  of  the  work  at  the  hands  of   the

respondents has been enclosed.


g) That the respondents had committed breach and thus liable for damages.


h) It is further stated that the cost of material issued by  the  department

has been deducted by assessing the cost.


Claim No. 13: Claimants claim Rs.97,5000/- being the extra at  35%  for  the

work executed in  block  100  &  101  effective  from  28.2.94  till  actual

completion.


a) It is further stated that due to delayed execution of the work  of  these

two blocks the claimants had to incur extra expenditure as the  stoppage  of

work was utterly arbitrary.


b) That the detailed break-up of this claim is appended with  the  statement

of facts."


5.    Though the challenge to claims 2, 3 and 4 were given up before the

Division Bench, they are also relevant and read as follows:


"Claim No.2:  Claimants  claim  Rs.1,62,387/-  being  the  reimbursement  of

statutory increase in labour under clause 10-C


a)  That the claimants submitted the tender on 6.2.92  and  said  offer  was

accepted on 14.5.92. The date  of  commencement  was  to  be  reckoned  from

24.5.92. The date of stipulated completion was 9  months  i.e.  23.2.93  but

the work could be completed on 28.3.95.


b) It is further stated that the claimants had submitted the  bill  for  the

value to the extent the work was executed till 4.10.94  for  a  sum  of  Rs.

l,12,067/- as per the formula applicable.


c) That the respondents however, did not make a single payment  though,  the

work was executed after submission of the said bill.


d) That however, a consolidated bill was furnished  the  respondents  for  a

sum of Rs. l,62,287/-. Even the said payment  has  not  been  liquidated  so

far.


e) That the claimants advised the statutory increase as  and  when  enforced

and the claimants also submitted the labour reports  indicating  the  nature

of the labour employed at site.


f) That the respondents had also certified  on  the  bill  that  the  labour

payment has been made as per the labour rate.


g) That it is further stated that since it  is  a  statutory  increase,  the

same is payable by the respondents. Copy of the  both  the  bills  attached.

And thus the claimants be awarded a sum of Rs. 1,62,287/- to the  claimants.



Claim No.3: Claimants claim Rs.l,49,862/- being  the  increase  in  cost  of

stone grit on account closure of the quarry by  the  order  of  the  Supreme

Court.


a)  That it is stated that the claimants had submitted  the  tender  on  the

basis of the rate prevailing but due to the Hon'ble Court's  directions  for

closure of the stone quarry resulting in shortage  of  stone  chips  in  the

market and consequently rates increased.


b) That the claimants informed the quantum of the increase  on  22.6.92  and

followed by reminders.


c) That the respondents had agreed in principle to pay  the  increase  which

was prevailing in the market.


d) That the detailed break-up of this claim has been appended separately.


e) It is further stated that the claimant was not instrumental for  increase

in cost but due to the interference of the Hon'ble Supreme  Court.  And  the

said increase has been taken into account  till  the  stipulated  completion

dated 23.2.93.


f)  That the claimant is entitled for recovery of the said increase.


Claim No. 4:  Claimants claim Rs.12,922/- payable by virtue of  clause  10-C

of the agreement and up to the stipulated period


a)    That there was steep rise in  cost  of  steel  and  the  claimant  was

exposed and the respondents were liable to pay the increase in steel.


b)    That the detailed  break-up  of  this  claim  has  been  prepared  and

appended.




6.    The Arbitrator by a reasoned award dated 23rd May, 2005 held that  the

entire delay of 25 months in the execution of the project was thanks to  the

DDA, none of this delay being attributable to the  contractor.  The  learned

Arbitrator found:


"That all the above four claims  are  inter  linked  being  related  to  the

overhead expenses and therefore dealt together.


That the date of commencement  of  work  was  24.5.92  and  the  period  for

completion was 9 months and therefore, the disputed date of  completion  was

23.2.93 but the work could be actually completed on 28.3.95.


That there was delay of 25 months in  completion  of  the  work  beyond  the

stipulated date of completion.


That the  Claimants  urged  that  there  had  been  various  delays  in  the

execution of work due to the lapses and defaults  of  the  Respondents  from

the very commencement of work. The progress was held up time and  again  and

the claimants therefore, as back as 17.2.93  advised  the  Respondents  (C-9

page 167) that the Claimants are not interested to execute the  work  beyond

the  stipulated  date  of  completion  and  therefore,  their  contract   be

finalized on the stipulated date of completion as the  Claimants   shall  be

exposed  to  incur  heavy   expenditure   in   overheads   for   maintaining

establishment watch and ward and  tools  and  plants  and  other  shuttering

material but the Respondents did not refute. The  chief  reasons  for  delay

are highlighted below:-


I)  Delay in supply of structural and architectural drawings.


II) That out of 9 Blocks 2 blocks are abnormally delayed as the site of  the

said 21 blocks was made available in piecemeal which stretched till  26.2.94

whereas the stipulated completion was 23.2.93.


III) Delay in laying the conduit  by  the  electrical  agency  resulting  in

delay in casting of RCC slab and plastering work besides  development  work.

The said hindrance was removed lastly on 28.3.95.


IV) Abnormal delay in  making  availability  of  the  alignment  sketch  for

electrical cables.


V) Inordinate delay in supply of stipulated material such as  cement,  steel

and pipes.


VI) Delay in decision of finishing work in kitchen and bath rooms.


VII) There was inordinate delay in making availability of colour scheme.


VIII) That the Respondents  also  abnormally  delayed  the  supply  of  door

shutters which were to  be  supplied  by  the  Respondents.  The  same  were

supplied as late as 8.11.94.


IX) Inordinate delay in writing in  the  electrical  conduits  resulting  in

delay in completion of finishing work.


X) Suspension of work by the Respondents for the period 17.1.94  to  25.2.94

and from 7.8.94 to 22.3.95 because of non-removal of hindrances.


XI) Delayed payment due  to  non-sanction  of  Administrative  Approval  and

Expenditure Sanction.


That all the delays as set out had been duly recorded 733 to 739 and  M.A.S.

register pages from  747  to  768  as  highlighted  by  the  Claimants.  The

Claimants also relied upon certain documents of  MAS  Register  supplied  by

the Respondents.


That the Claimants further stated that the Claimants had also filed  reasons

for delay and hold up of the work various defaults  of  the  Respondents  in

Annexure  pages  740  to   746.   The   Claimants   also   highlighted   the

correspondence made by the Claimants with Respondents.


That the Claimants further stated that the said  hindrances  were  avoidable

but the Respondents did not take timely steps.


That the Claimants also referred the contents of the  letter  dated  10.7.95

(page  885)  wherein  it  was  observed  that  the  Superintending  Engineer

appreciated the working of the Claimants and also observed  that  there  was

no fault of the contractor and they have successfully  completed  the  work.

The Claimants further stated that, they had incurred  heavy  expenditure  on

overheads of the lapses and default of the Respondents.


As against this the Respondents stated that there was poor planning  of  the

claimants and also contended that since the  compensation  has  been  levied

under Clause 2 of the agreement therefore, claim of the  claimants  deserves

to be rejected.


That on record it is conclusively  proved  that  the  Respondents  committed

breach of contract as they failed to discharge  their  obligations  in  time

resulting in prolongations did not deny the  deployment  of  the  tools  and

plants  and  machinery  at  site  besides  watch   and   ward   during   the

prolongation."




7.    It is important to note that before the Division  Bench,  the  learned

counsel for the DDA conceded that this being a  pure  finding  of  fact,  he

would not be challenging it before the Division Bench.


8.    Of the total claim of Rs.37.28 lakhs, the learned  Arbitrator  awarded

an  amount  of  Rs.23.39  lakhs.   Further,  the  learned   Arbitrator   has

laboriously gone through all the evidence and  answered  each  claim  giving

reasons for the same.


9.    By a judgment dated 3rd April, 2006, the learned Single Judge  of  the

High Court of Delhi dismissed the objections  of  the  DDA  and  upheld  the

award. In an appeal filed under Section 37 of the Arbitration Act, vide  the

impugned judgment dated 8th February, 2012, a Division  Bench  of  the  High

Court of Delhi set aside the judgment of the Single Judge on claims  9,  10,

11 and 15, and negatived these claims in toto.  Further, claims  12  and  13

were scaled down doing "rough and ready justice".  Resultantly, the  awarded

amount of Rs.7,20,000/- was scaled down to Rs. 5,57,137.50/-.


10.   We have heard learned counsel for  the  parties.  Shri  M.  L.  Verma,

learned Senior Advocate appearing on  behalf  of  the  appellant,  submitted

that the Division Bench has lost sight of the law laid down by this  Hon'ble

Court when it comes to challenges made to arbitral awards under  Section  34

of the Act. He has submitted that the Division Bench has acted  as  if  this

was a first appeal from  the  award  and  has  further  submitted  that  the

Division Bench has taken into account facts which were neither  pleaded  nor

proved before the learned Arbitrator in order to  negative  certain  claims.

He further submitted that  it  is  not  possible  for  a  Bench  hearing  an

objection against an arbitral award to do "rough and ready justice" - it  is

bound by the law laid down by this Hon'ble Court. In particular,  he  argued

that the conceded position is that 25  months  delay  was  due  to  the  DDA

alone.  The award read as a whole is  just,  fair  and  reasonable  as  only

certain claims have been granted and every claim granted has been  supported

with reasons. The Arbitrator is the sole judge of the quality  and  quantity

of evidence before him and he has decided on that evidence.   No  errors  of

law arise from the award and the award  has,  therefore,  been  wrongly  set

aside.


11.   Mr. Amarendra Sharan, learned Senior Advocate appearing on  behalf  of

the DDA has relied strongly on clause 10C  and  clause  22  to  support  the

judgment of the Division bench and has further argued that  there  has  been

duplication so far as certain claims are concerned. He argued that an  award

in the teeth of clause 10C and clause 22 would  be  a  jurisdictional  error

which would vitiate the award.


12.   In as much as serious objections  have  been  taken  to  the  Division

Bench judgment on the ground that it has ignored the  parameters  laid  down

in a series of judgments by this Court as to the limitations which  a  Judge

hearing objections to an arbitral award under Section 34 is subject  to,  we

deem it necessary to state the law on the subject.


Section 34 of the Arbitration and Conciliation Act reads as follows-


"Application for setting aside  arbitral  award.-(1)  Recourse  to  a  Court

against an arbitral award may be made only by  an  application  for  setting

aside such award in accordance with sub-section (2) and sub-section (3).


(2) An arbitral award may be set aside by the Court only if-


(a) the party making the application furnishes proof that-


(i) a party was under some incapacity; or


(ii) The arbitration agreement is not valid  under  the  law  to  which  the

parties have subjected it or, failing any indication thereon, under the  law

for the time being in force; or


(iii) the party making the application was not given proper  notice  of  the

appointment  of  an  arbitrator  or  of  the  arbitral  proceedings  or  was

otherwise unable to present his case; or


(iv) the arbitral award deals with a dispute  not  contemplated  by  or  not

falling within the terms of the submission to arbitration,  or  it  contains

decisions on matters beyond the scope of the submission to arbitration:


Provided that, if the decisions on matters submitted to arbitration  can  be

separated from those not so submitted, only that part of the arbitral  award

which contains decisions on matters not submitted to arbitration may be  set

aside; or


(v) the composition of the arbitral tribunal or the arbitral  procedure  was

not in accordance with the agreement of the parties, unless  such  agreement

was in conflict with a provision of this Part from which the parties  cannot

derogate, or, failing such agreement, was not in accordance with this  Part;

or


(b) the Court finds that-


(i) the subject-matter of the  dispute  is  not  capable  of  settlement  by

arbitration under the law for the time being in force, or


(ii) the arbitral award is in conflict with the public policy of India.


Explanation.-Without prejudice to the generality of sub-clause (ii),  it  is

hereby declared, for the avoidance  of  any  doubt,  that  an  award  is  in

conflict with the public policy of India if the  making  of  the  award  was

induced or affected by fraud or corruption or was in  violation  of  Section

75 or Section 81.


(3) An application for setting aside may not  be  made  after  three  months

have elapsed from the date on which the party making  that  application  had

received the arbitral award or, if a request had  been  made  under  Section

33, from the date on  which  that  request  had  been  disposed  of  by  the

arbitral tribunal:


Provided that if the Court is satisfied that the applicant was prevented  by

sufficient cause from making the  application  within  the  said  period  of

three months it may entertain the application within  a  further  period  of

thirty days, but not thereafter.


(4) On receipt of an application  under  sub-section  (1),  the  Court  may,

where it is appropriate and it is so  requested  by  a  party,  adjourn  the

proceedings for a period of time determined by  it  in  order  to  give  the

arbitral tribunal an opportunity to resume the arbitral  proceedings  or  to

take such  other  action  as  in  the  opinion  of  arbitral  tribunal  will

eliminate the grounds for setting aside the arbitral award."




           This Section in conjunction with Section 5 makes  it  clear  that

an arbitration award that is governed by  part  I  of  the  Arbitration  and

Conciliation Act, 1996 can be set aside  only  on  grounds  mentioned  under

Section 34 (2) and (3), and not otherwise. Section 5 reads as follows:


       "5.  Extent  of   judicial   intervention.-Notwithstanding   anything

contained in any other law for the time being in force, in matters  governed

by this  Part,  no  judicial  authority  shall  intervene  except  where  so

provided in this Part."




            It is important to  note  that  the  1996  Act  was  enacted  to

replace the 1940 Arbitration  Act  in  order  to  provide  for  an  arbitral

procedure which is fair, efficient and  capable  of  meeting  the  needs  of

arbitration; also  to  provide  that  the  tribunal  gives  reasons  for  an

arbitral award; to ensure that the tribunal remains  within  the  limits  of

its jurisdiction; and to minimize the supervisory roles  of  courts  in  the

arbitral process.


            It will be seen that none  of  the  grounds  contained  in  sub-

clause 2 (a) deal with the merits of the decision rendered  by  an  arbitral

award.  It is only when we come to the award  being  in  conflict  with  the

public policy of India that the merits  of  an  arbitral  award  are  to  be

looked into under certain specified circumstances.


            In Renusagar Power Co. Ltd.  v.  General  Electronic  Co.,  1994

Supp (1) SCC 644, the Supreme Court construed Section 7 (1)(b) (ii)  of  the

Foreign Award (Recognition and Enforcement) Act, 1961.


      "7. Conditions for enforcement of foreign awards.-(1) A foreign  award

may not be enforced under this Act-


      (b) if the Court dealing with the case is satisfied that-


       (ii) the enforcement of the award will  be  contrary  to  the  public

policy."




            In construing the expression "public policy" in the  context  of

a foreign award, the Court held that an award contrary to


      1.    The fundamental policy of Indian law


      2.    The interest of India


      3.    Justice or morality,


      would be set aside on the ground that it  would  be  contrary  to  the

public policy of India. It went on further to hold that a  contravention  of

the provisions of the Foreign Exchange Regulation Act would be  contrary  to

the public policy of India in that the statute is enacted for  the  national

economic interest to ensure that the nation does not lose  foreign  exchange

which is essential for the economic survival of the nation  (see  para  75).

Equally, disregarding orders passed by the superior courts  in  India  could

also be a contravention of the fundamental policy of  Indian  law,  but  the

recovery of compound interest on interest, being contrary to  statute  only,

would not contravene  any  fundamental  policy  of  Indian  law  (see  paras

85,95).


            When it came to construing the expression "the public policy  of

India" contained in Section 34 (2) (b) (ii) of the  Arbitration  Act,  1996,

this Court in ONGC v. Saw Pipes, 2003 (5) SCC 705, held-


      "31. Therefore, in our view, the phrase "public policy of India"  used

in Section 34 in context is required to be given a wider meaning. It can  be

stated that  the  concept  of  public  policy  connotes  some  matter  which

concerns public good and the public interest. What is for public good or  in

public interest or what would be injurious or harmful to the public good  or

public interest has varied from time to time. However, the award  which  is,

on the face of it, patently in violation of statutory provisions  cannot  be

said to be in public interest. Such  award/judgment/decision  is  likely  to

adversely affect the administration  of  justice.  Hence,  in  our  view  in

addition to narrower meaning given to the term "public policy"  in Renusagar

case [1994 Supp (1) SCC 644] it is required to be held that the award  could

be set aside if it is patently illegal. The result would be  -  award  could

be set aside if it is contrary to:


      (a) Fundamental policy of Indian law; or


      (b) The interest of India; or


      (c) Justice or morality, or


      (d) in addition, if it is patently illegal.


      Illegality must go to the root of the matter and if the illegality  is

of trivial nature it cannot  be  held  that  award  is  against  the  public

policy. Award could also be set aside if it is so  unfair  and  unreasonable

that it shocks the conscience of the court. Such award is opposed to  public

policy and is required to be adjudged void.


      74. In the result, it is held that:


      (A) (1) The court can set  aside  the  arbitral  award  under  Section

34(2) of the Act if the party making the application furnishes proof that:


      (i) a party was under some incapacity, or


      (ii) the arbitration agreement is not valid under  the  law  to  which

the parties have subjected it or, failing any indication thereon, under  the

law for the time being in force; or


      (iii) the party making the application was not given proper notice  of

the appointment of an arbitrator or  of  the  arbitral  proceedings  or  was

otherwise unable to present his case; or


      (iv) the arbitral award deals with a dispute not  contemplated  by  or

not falling within the  terms  of  the  submission  to  arbitration,  or  it

contains decisions  on  matters  beyond  the  scope  of  the  submission  to

arbitration.


      (2) The court may set aside the award:


      (i)(a) if  the  composition  of  the  Arbitral  Tribunal  was  not  in

accordance with the agreement of the parties,


      (b) failing such agreement, the composition of the  Arbitral  Tribunal

was not in accordance with Part I of the Act.


      (ii) if the arbitral procedure was not in accordance with:


      (a) the agreement of the parties, or


      (b)  failing  such  agreement,  the  arbitral  procedure  was  not  in

accordance with Part I of the Act.


      However, exception for setting  aside  the  award  on  the  ground  of

composition of Arbitral Tribunal or  illegality  of  arbitral  procedure  is

that the agreement should not be in conflict with the provisions of  Part  I

of the Act from which parties cannot derogate.


      (c) If the award passed by the Arbitral Tribunal is  in  contravention

of the provisions of the Act or any  other  substantive  law  governing  the

parties or is against the terms of the contract.


      (3) The award could be set aside if it is against  the  public  policy

of India, that is to say, if it is contrary to:


      (a) fundamental policy of Indian law; or


      (b) the interest of India; or


      (c) justice or morality; or


      (d) if it is patently illegal.


      (4) It could be challenged:


      (a) as provided under Section 13(5); and


      (b) Section 16(6) of the Act.


      (B)(1) The impugned award requires to  be  set  aside  mainly  on  the

grounds:


      (i) there is specific stipulation in the agreement that the  time  and

date of delivery of the goods was of the essence of the contract;


      (ii) in case of failure to deliver the goods within the  period  fixed

for such delivery in the schedule, ONGC was entitled  to  recover  from  the

contractor liquidated damages as agreed;


      (iii) it was also explicitly understood  that  the  agreed  liquidated

damages were genuine pre-estimate of damages;


      (iv) on the request of the respondent to  extend  the  time-limit  for

supply of goods, ONGC informed  specifically  that  time  was  extended  but

stipulated liquidated damages as agreed would be recovered;


      (v) liquidated damages for  delay  in  supply  of  goods  were  to  be

recovered by paying authorities from  the  bills  for  payment  of  cost  of

material supplied by the contractor;


      (vi) there is nothing  on  record  to  suggest  that  stipulation  for

recovering liquidated damages was by way of penalty or  that  the  said  sum

was in any way unreasonable.


      (vii) In certain contracts, it is impossible to assess the damages  or

prove the same. Such situation is taken care of by Sections  73  and  74  of

the Contract  Act  and  in  the  present  case  by  specific  terms  of  the

contract."




            The  judgment  in  ONGC  v.  Saw  Pipes  has  been  consistently

followed till date.


            In Hindustan Zinc Ltd. v. Friends Coal Carbonisation,  (2006)  4

SCC 445, this Court held:                             


      "14. The High Court did not have the benefit of  the  principles  laid

down in Saw Pipes [(2003) 5 SCC 705] , and had proceeded on  the  assumption

that award cannot be interfered with even if it was contrary  to  the  terms

of the contract. It went to  the  extent  of  holding  that  contract  terms

cannot even be looked into for examining the correctness of the award.  This

Court in Saw Pipes [(2003) 5 SCC 705] has made it clear that it is  open  to

the court to consider whether the award is against  the  specific  terms  of

contract and if so, interfere with it on the  ground  that  it  is  patently

illegal and opposed to the public policy of India."




            In McDermott International  Inc.  v.  Burn  Standard  Co.  Ltd.,

(2006) 11 SCC 181, this Court held:        


 "58. In Renusagar Power Co. Ltd. v. General  Electric  Co. [1994  Supp  (1)

SCC 644] this Court laid down that the arbitral award can be  set  aside  if

it is contrary to (a) fundamental policy of Indian law;  (b)  the  interests

of India; or (c) justice or morality. A narrower meaning to  the  expression

"public policy" was given  therein  by  confining  judicial  review  of  the

arbitral award only on the aforementioned three grounds. An  apparent  shift

can, however, be noticed from the decision of this Court in ONGC  Ltd.v. Saw

Pipes Ltd. [(2003) 5  SCC  705]  (for  short  "ONGC").  This  Court  therein

referred to an earlier  decision  of  this  Court  in Central  Inland  Water

Transport Corpn. Ltd. v. Brojo Nath Ganguly [(1986) 3 SCC  156  :  1986  SCC

(L&S) 429 : (1986) 1 ATC 103] wherein the applicability  of  the  expression

"public policy" on the touchstone of Section 23 of the Indian  Contract  Act

and Article 14 of the Constitution of India  came  to  be  considered.  This

Court therein was dealing with unequal bargaining power of the  workmen  and

the employer and came to the conclusion  that  any  term  of  the  agreement

which is patently arbitrary and/or  otherwise  arrived  at  because  of  the

unequal bargaining power would not only be ultra vires  Article  14  of  the

Constitution of India but also hit by Section  23  of  the  Indian  Contract

Act. In ONGC [(2003) 5 SCC 705] this Court, apart  from  the  three  grounds

stated in Renusagar [1994 Supp (1) SCC 644] , added another  ground  thereto

for exercise of the court's jurisdiction in setting aside the  award  if  it

is patently arbitrary.


      59. Such patent illegality, however,  must  go  to  the  root  of  the

matter. The public policy violation, indisputably, should be so  unfair  and

unreasonable as to shock the conscience of the court. Where the  arbitrator,

however, has gone contrary to or beyond the expressed law  of  the  contract

or granted relief in the  matter  not  in  dispute  would  come  within  the

purview  of  Section  34  of  the  Act.  However,  we  would  consider   the

applicability of the aforementioned principles while noticing the merits  of

the matter.


      60. What would constitute public policy is  a  matter  dependent  upon

the nature of transaction and nature of statute. For the said  purpose,  the

pleadings of the parties and  the  materials  brought  on  record  would  be

relevant to enable the court to judge what  is  in  public  good  or  public

interest, and what would otherwise be injurious to the public  good  at  the

relevant point, as contradistinguished  from  the  policy  of  a  particular

Government. (See State of Rajasthan v. Basant Nahata [(2005) 12 SCC 77].)"




            In Centrotrade Minerals & Metals Inc. v. Hindustan Copper  Ltd.,

(2006) 11 SCC 245, Sinha, J., held:


      "103. Such patent illegality, however, must go  to  the  root  of  the

matter. The public policy, indisputably, should be unfair  and  unreasonable

so as to shock the conscience of the court. Where the  arbitrator,  however,

has gone contrary to or beyond the expressed law of the contract or  granted

relief in the matter not  in  dispute  would  come  within  the  purview  of

Section 34 of the Act."


      104. What would be a public policy  would  be  a  matter  which  would

again depend upon the nature of transaction and the nature of  statute.  For

the said purpose, the pleadings of the parties and the materials brought  on

record would be relevant so as to enable the court to judge the  concept  of

what was a public good  or  public  interest  or  what  would  otherwise  be

injurious to the public good at the relevant  point  as  contradistinguished

by the policy of  a  particular  government.  (See   State  of  Rajasthan v.

Basant Nahata [(2005) 12 SCC 77].)"




            In DDA v. R.S. Sharma and Co.,  (2008)  13  SCC  80,  the  Court

summarized the law thus:


       "21. From the above decisions, the following principles emerge:


(a) An award, which is


(i) contrary to substantive provisions of law; or


(ii) the provisions of the Arbitration and Conciliation Act, 1996; or


(iii) against the terms of the respective contract; or


(iv) patently illegal; or


(v) prejudicial to the rights of the parties;


is open to interference by the court under Section 34(2) of the Act.


(b) The award could be set aside if it is contrary to:


(a) fundamental policy of Indian law; or


(b) the interest of India; or


(c) justice or morality.


(c) The award could also be set aside if it is so  unfair  and  unreasonable

that it shocks the conscience of the court.


(d) It is open to the court to consider whether the  award  is  against  the

specific terms of contract and if so, interfere with it on the  ground  that

it is patently illegal and opposed to the public policy of India.


With these principles and statutory provisions, particularly, Section  34(2)

of the Act, let us consider whether the arbitrator as well as  the  Division

Bench of the High Court were justified in granting the award in  respect  of

Claims 1 to 3 and Additional Claims 1 to 3 of the claimant or the  appellant

DDA has made out a case for setting aside the  award  in  respect  of  those

claims with reference to the terms of the agreement duly  executed  by  both

parties."




      J.G. Engineers (P) Ltd. v. Union of India, (2011) 5 SCC 758, held:


"27. Interpreting the said provisions, this Court in ONGC Ltd. v. Saw  Pipes

Ltd.[(2003) 5 SCC 705] held that a  court  can  set  aside  an  award  under

Section 34(2)(b)(ii) of the Act,  as  being  in  conflict  with  the  public

policy of India, if it is (a) contrary to the fundamental policy  of  Indian

law; or (b) contrary to the interests of India; or (c) contrary  to  justice

or morality; or (d) patently illegal. This Court explained that to  hold  an

award to be opposed to public policy, the patent  illegality  should  go  to

the very root of the matter  and  not  a  trivial  illegality.  It  is  also

observed that  an  award  could  be  set  aside  if  it  is  so  unfair  and

unreasonable that it shocks the conscience of the court, as  then  it  would

be opposed to public policy."




      Union of India v. Col. L.S.N. Murthy, (2012) 1 SCC 718, held:


"22. In ONGC Ltd. v. Saw Pipes Ltd. [(2003) 5  SCC  705]  this  Court  after

examining the grounds on which an award of the arbitrator can be  set  aside

under Section 34 of the Act has said: (SCC p. 727, para 31)


"31. ... However, the award which  is,  on  the  face  of  it,  patently  in

violation of statutory provisions cannot be said to be in  public  interest.

Such   award/judgment/decision   is   likely   to   adversely   affect   the

administration of justice. Hence,  in  our  view  in  addition  to  narrower

meaning given to  the  term  'public  policy'  in Renusagar  case [Renusagar

Power Co. Ltd. v. General Electric  Co.,  1994  Supp  (1)  SCC  644]  it  is

required to be held that the award could be set  aside  if  it  is  patently

illegal".


Fundamental Policy of Indian Law


      Coming to each of the heads contained in the Saw  Pipes  judgment,  we

will first deal with the head "fundamental policy of  Indian  Law".  It  has

already been seen from the Renusagar judgment that violation of the  Foreign

Exchange Act and disregarding orders of superior courts in  India  would  be

regarded as being contrary to the fundamental policy of Indian law. To  this

it could be added that the binding effect of  the  judgment  of  a  superior

court being disregarded  would  be  equally  violative  of  the  fundamental

policy of Indian law.


      In a recent judgment, ONGC Ltd. v. Western  Geco  International  Ltd.,

2014 (9) SCC 263, this Court added  three  other  distinct  and  fundamental

juristic principles which must be understood as a part  and  parcel  of  the

fundamental policy of Indian law. The Court held-


"35. What then would constitute the "fundamental policy of  Indian  law"  is

the question. The decision in ONGC [ONGC Ltd. v. Saw Pipes  Ltd.,  (2003)  5

SCC 705] does not elaborate that aspect. Even so, the  expression  must,  in

our opinion, include all such fundamental principles as  providing  a  basis

for administration of justice  and  enforcement  of  law  in  this  country.

Without meaning to exhaustively enumerate  the  purport  of  the  expression

"fundamental policy of Indian law", we  may  refer  to  three  distinct  and

fundamental juristic principles that must necessarily  be  understood  as  a

part and parcel of the fundamental  policy  of  Indian  law.  The first  and

foremost is the principle that in every determination whether by a court  or

other authority that affects the rights of a citizen or leads to  any  civil

consequences, the court or authority concerned is bound to adopt what is  in

legal parlance called a "judicial approach"  in  the  matter.  The  duty  to

adopt a  judicial  approach  arises  from  the  very  nature  of  the  power

exercised by the court or the authority does not have to  be  separately  or

additionally enjoined upon the fora concerned. What must  be  remembered  is

that the importance of a judicial approach in  judicial  and  quasi-judicial

determination lies in the fact that so long as the court,  tribunal  or  the

authority exercising powers that affect the rights  or  obligations  of  the

parties before them shows fidelity to judicial approach, they cannot act  in

an arbitrary, capricious or  whimsical  manner.  Judicial  approach  ensures

that the authority acts bona fide and deals with  the  subject  in  a  fair,

reasonable and objective manner and that its decision  is  not  actuated  by

any extraneous consideration. Judicial approach in  that  sense  acts  as  a

check against flaws and faults that can render  the  decision  of  a  court,

tribunal or authority vulnerable to challenge.


38. Equally important and indeed fundamental to the policy of Indian law  is

the principle that a court and so  also  a  quasi-judicial  authority  must,

while determining the rights and obligations of parties before it, do so  in

accordance  with  the   principles   of   natural   justice.   Besides   the

celebrated audi alteram partem rule one of the facets of the  principles  of

natural justice is that the court/authority deciding the matter  must  apply

its mind to the attendant facts and circumstances while taking  a  view  one

way or the other. Non-application of mind is a defect that is fatal  to  any

adjudication. Application of mind is best demonstrated by disclosure of  the

mind and disclosure of mind is best done by recording reasons in support  of

the decision which the court or authority is taking.  The  requirement  that

an adjudicatory authority must apply its mind is, in that  view,  so  deeply

embedded in our jurisprudence that it can  be  described  as  a  fundamental

policy of Indian law.


39. No less  important  is  the  principle  now  recognised  as  a  salutary

juristic  fundamental  in  administrative  law  that  a  decision  which  is

perverse or so irrational that no reasonable person would  have  arrived  at

the  same  will  not  be  sustained  in  a  court  of  law.  Perversity   or

irrationality of  decisions  is  tested  on  the  touchstone  of  Wednesbury

principle [Associated Provincial Picture Houses  Ltd. v. Wednesbury  Corpn.,

(1948) 1 KB 223: (1947) 2 All ER  680  (CA)]  of  reasonableness.  Decisions

that fall short of the standards of reasonableness are open to challenge  in

a court of law often in writ jurisdiction of  the  superior  courts  but  no

less in statutory processes wherever the same are available.


40. It is neither necessary nor proper  for  us  to  attempt  an  exhaustive

enumeration of what would constitute the fundamental policy  of  Indian  law

nor is it possible  to  place  the  expression  in  the  straitjacket  of  a

definition. What is important in the context of the case at hand is that  if

on facts proved before them the arbitrators fail to draw an inference  which

ought to have been drawn or if they have drawn an inference which is on  the

face of it, untenable resulting in miscarriage of justice, the  adjudication

even when made by an Arbitral Tribunal  that  enjoys  considerable  latitude

and play at the joints in making awards will be open to  challenge  and  may

be cast away or modified depending upon whether the offending part is or  is

not severable from the rest."




      It is clear that the  juristic  principle  of  a  "judicial  approach"

demands that a decision be fair, reasonable and objective.  On  the  obverse

side,  anything  arbitrary  and  whimsical  would   obviously   not   be   a

determination which would either be fair, reasonable or objective.


            The  Audi  Alteram  Partem  principle  which  undoubtedly  is  a

fundamental juristic principle in Indian law is also contained  in  Sections

18 and 34 (2) (a) (iii) of  the  Arbitration  and  Conciliation  Act.  These

Sections read as follows:


"18. Equal  treatment  of  parties.-  The  parties  shall  be  treated  with

equality and each party shall be given a full  opportunity  to  present  his

case.


34. Application for setting aside arbitral award.-


      (2) An arbitral award may be set aside by the Court only if-


      (a) the party making the application furnishes proof that-


       (iii) the party making the application was not  given  proper  notice

of the appointment of an arbitrator or of the arbitral  proceedings  or  was

otherwise unable to present his case; "




      The third juristic principle is that a decision which is  perverse  or

so irrational that no reasonable person would have arrived at  the  same  is

important and requires some degree of explanation. It is  settled  law  that

where-


a finding is based on no evidence, or


an  arbitral  tribunal  takes  into  account  something  irrelevant  to  the

decision which it arrives at; or


ignores vital evidence in arriving at its decision,


such decision  would  necessarily  be  perverse.  A  good  working  test  of

perversity is contained  in  two  judgments.  In  H.B.  Gandhi,  Excise  and

Taxation Officer-cum-Assessing Authority v. Gopi Nath & Sons, 1992 Supp  (2)

SCC 312 at p. 317, it was held:

"7. ...................It is, no doubt, true that if a finding  of  fact  is

arrived at by ignoring or excluding relevant  material  or  by  taking  into

consideration irrelevant material or if the finding so  outrageously  defies

logic as to suffer from the vice of irrationality  incurring  the  blame  of

being perverse, then, the finding is rendered infirm in law."




In Kuldeep Singh v. Commr. of Police, (1999) 2 SCC 10 at  para  10,  it  was

held:


"10. A broad distinction  has,  therefore,  to  be  maintained  between  the

decisions which are perverse and those which  are  not.  If  a  decision  is

arrived at on no evidence or evidence which is thoroughly unreliable and  no

reasonable person would act upon it, the order would  be  perverse.  But  if

there is some evidence on record which is  acceptable  and  which  could  be

relied upon, howsoever compendious it may be, the conclusions would  not  be

treated as perverse and the findings would not be interfered with."




      It must clearly be understood  that  when  a  court  is  applying  the

"public policy" test to an arbitration award, it does not act as a court  of

appeal and consequently errors of fact cannot be corrected. A possible  view

by the arbitrator on facts has necessarily to pass muster as the  arbitrator

is the ultimate master of the quantity and quality of evidence to be  relied

upon when he delivers his arbitral award. Thus  an  award  based  on  little

evidence or on evidence which does not measure up in quality  to  a  trained

legal mind would not be held to be invalid on  this  score[1].  Once  it  is

found that the arbitrators approach is not arbitrary or capricious, then  he

is the last word on facts. In P.R. Shah, Shares & Stock Brokers (P) Ltd.  v.

B.H.H. Securities (P) Ltd., (2012) 1 SCC 594, this Court held:


"21. A court does not sit in appeal over the award of an  Arbitral  Tribunal

by reassessing or reappreciating the evidence. An award  can  be  challenged

only under the grounds mentioned in Section 34(2) of the Act.  The  Arbitral

Tribunal has examined the facts and held that  both  the  second  respondent

and the appellant  are  liable.  The  case  as  put  forward  by  the  first

respondent has been accepted. Even the minority view  was  that  the  second

respondent was liable as claimed by the first respondent, but the  appellant

was not liable only on the ground that  the  arbitrators  appointed  by  the

Stock Exchange under Bye-law 248, in a claim against a  non-member,  had  no

jurisdiction to decide a claim against another member. The  finding  of  the

majority is that the appellant did  the  transaction  in  the  name  of  the

second  respondent  and  is  therefore,  liable  along   with   the   second

respondent. Therefore, in the absence of any ground under Section  34(2)  of

the Act, it is not possible to re-examine the facts to find  out  whether  a

different decision can be arrived at."


      It is with  this  very  important  caveat  that  the  two  fundamental

principles which form part of the fundamental policy  of  Indian  law  (that

the arbitrator must have a judicial  approach  and  that  he  must  not  act

perversely) are to be understood.


      Interest of India


            The next ground on which an award may be set aside  is  that  it

is contrary to the interest of India. Obviously, this concerns  itself  with

India as a member of the world  community  in  its  relations  with  foreign

powers. As at present advised, we need not dilate on  this  aspect  as  this

ground may need to evolve on a case by case basis.

      Justice

      The third ground of public policy is, if an award is  against  justice

or morality. These are two different concepts in law. An award can  be  said

to be against justice only when it shocks the conscience of  the  court.  An

illustration of this can be given. A claimant is  content  with  restricting

his claim, let us say to Rs. 30 lakhs in a statement  of  claim  before  the

arbitrator and at no  point  does  he  seek  to  claim  anything  more.  The

arbitral award ultimately awards him 45 lakhs without any acceptable  reason

or justification. Obviously, this would shock the conscience  of  the  court

and the arbitral award would be liable to be set aside on  the  ground  that

it is contrary to "justice".

      Morality


      The other ground is of "morality".  Just  as  the  expression  "public

policy" also occurs in Section 23 of the Indian Contract Act,  so  does  the

expression  "morality".  Two  illustrations  to   the   said   section   are

interesting for they explain to us the scope of the expression "morality".


"(j) A, who is B's Mukhtar, promises to exercise  his  influence,  as  such,

with B in  favour  of C,  and C promises  to  pay  1,000  rupees   to A. The

agreement is void, because it is immoral.


(k) A agrees  to  let  her  daughter  to  hire  to B for  concubinage.   The

agreement is void, because it is immoral, though  the  letting  may  not  be

punishable under the Indian Penal Code (XLV of 1860)."




      In Gherulal Parekh v. Mahadeo Dass Maiya, 1959 Supp (2) SCR 406,  this

Court explained the concept of "morality" thus-


"Re. Point 3 - Immorality: The argument under this head  is  rather  broadly

stated by the  learned  Counsel  for  the  appellant.  The  learned  counsel

attempts to draw an analogy from the Hindu Law relating to the  doctrine  of

pious obligation of sons to discharge  their  father's  debts  and  contends

that what the Hindu  Law  considers  to  be  immoral  in  that  context  may

appropriately be applied to a case under s. 23 of the Contract Act.  Neither

any authority is cited nor any legal basis is suggested  for  importing  the

doctrine of Hindu Law  into  the  domain  of  contracts.  Section 23 of  the

Contract Act is inspired by the common law of England and it would  be  more

useful to refer to the English Law than to the Hindu Law texts dealing  with

a different matter. Anson in his Law of Contracts states at p. 222 thus:


      "The only aspect of immorality with which Courts of Law have dealt  is

sexual immorality........... ."


      Halsbury in his Laws of England, 3rd Edn., Vol.  8,  makes  a  similar

statement, at p. 138 :


      "A contract which is made upon an  immoral  consideration  or  for  an

immoral purpose is unenforceable,  and  there  is  no  distinction  in  this

respect between immoral and illegal contracts. The immorality  here  alluded

to is sexual immorality."


      In the Law of Contract by Cheshire and Fifoot, 3rd Edn., it is  stated

at p. 279:


      "Although Lord Mansfield laid it down that  a  contract  contra  bonos

mores is illegal, the law in this connection gives no  extended  meaning  to

morality, but concerns itself only with what is sexually reprehensible."


      In the book on the Indian Contract Act by  Pollock  and  Mulla  it  is

stated at p. 157:


      "The epithet "immoral" points, in legal usage, to conduct or  purposes

which the State, though disapproving them, is unable,  or  not  advised,  to

visit with direct punishment."


       The  learned  authors  confined  its  operation  to  acts  which  are

considered to be immoral according to the standards of  immorality  approved

by Courts. The case law both in England and India confines the operation  of

the doctrine to sexual immorality. To cite only some instances:  settlements

in consideration of concubinage, contracts of sale or hire of things  to  be

used in a brothel  or  by  a  prostitute  for  purposes  incidental  to  her

profession,  agreements  to  pay  money  for  future  illicit  cohabitation,

promises in regard to marriage for consideration, or contracts  facilitating

divorce are all held to be void on the ground that the object is immoral.


      The word "immoral" is a very comprehensive word. Ordinarily  it  takes

in every aspect of personal conduct deviating from  the  standard  norms  of

life. It may also be said that what  is  repugnant  to  good  conscience  is

immoral. Its varying content depends upon  time,  place  and  the  stage  of

civilization of a particular society. In short, no  universal  standard  can

be laid down and any law  based  on  such  fluid  concept  defeats  its  own

purpose.  The  provisions  of  S. 23  of  the  Contract  Act  indicate   the

legislative intention to give it a  restricted  meaning.  Its  juxtaposition

with an equally illusive concept, public policy, indicates that it  is  used

in a restricted sense; otherwise there  would  be  overlapping  of  the  two

concepts. In its wide sense what is immoral may be  against  public  policy,

for  public  policy  covers  political,  social  and  economic   ground   of

objection. Decided cases and  authoritative  text-book  writers,  therefore,

confined it, with every justification, only to sexual immorality. The  other

limitation imposed on the word by the statute, namely,  "the  court  regards

it as immoral", brings out the idea that it is also a branch of  the  common

law like the doctrine of public policy, and, therefore, should  be  confined

to the principles recognized and settled by Courts. Precedents  confine  the

said concept only to sexual immorality and no case has been brought  to  our

notice where it has been applied to any head other than  sexual  immorality.

In the circumstances, we cannot evolve a new head so as to bring  in  wagers

within its fold."




      This Court has confined morality to sexual morality so far as  section

23 of the Contract Act is concerned, which in the  context  of  an  arbitral

award would mean the enforcement of an award say  for  specific  performance

of a contract involving prostitution. "Morality"  would,  if  it  is  to  go

beyond sexual morality necessarily cover such agreements as are not  illegal

but would not be enforced given the prevailing mores of the  day.   However,

interference on this ground would also  be  only  if  something  shocks  the

court's conscience.

      Patent Illegality

            We now come to the fourth head of public policy  namely,  patent

illegality. It must be remembered that under the explanation to  section  34

(2) (b), an award is said to be in conflict with the public policy of  India

if the making of the award was induced or affected by fraud  or  corruption.

This ground is perhaps the earliest ground on which courts  in  England  set

aside awards under English law. Added  to  this  ground  (in  1802)  is  the

ground that an arbitral award would be set aside if there were an  error  of

law by the arbitrator. This is explained by Lord Justice  Denning  in  R  v.

Northumberland Compensation Appeal Tribunal. Ex Parte Shaw., 1952 1  All  ER

122 at page 130:

"Leaving  now  the  statutory  tribunals,  I  turn  to  the  awards  of  the

arbitrators. The Court of King's Bench never interfered by  certiorari  with

the award of an arbitrator, because  it  was  a  private  tribunal  and  not

subject to the prerogative writs. If the  award  was  not  made  a  rule  of

court, the only course available to an aggrieved  party  was  to  resist  an

action on the award or to file a bill in equity. If the  award  was  made  a

rule of court, a motion could be made to the  court  to  set  it  aside  for

misconduct of  the  arbitrator  on  the  ground  that  it  was  procured  by

corruption or other undue means: see the statute 9 and 10 Will. III, c.  15.

At one time an award could not be upset on the ground of  error  of  law  by

the arbitrator because that could not be said  to  be  misconduct  or  undue

means, but ultimately it was held in Kent v.  Elstob,   (1802)  3  East  18,

that an award could be set aside for error of law on the face  of  it.  This

was regretted by Williams, J., in Hodgkinson v. Fernie,  (1857)  3  C.B.N.S.

189, but is now well established."




            This, in  turn,  led  to  the  famous  principle  laid  down  in

Champsey Bhara Company v. The Jivraj Balloo  Spinning  and  Weaving  Company

Ltd., AIR 1923 PC 66, where the Privy Council  referred  to  Hodgkinson  and

then laid down:


"The law on  the  subject  has  never  been  more  clearly  stated  than  by

Williams, J. in the case of Hodgkinson v. Fernie (1857) 3 C.B.N.S. 189.


"The law has for many years been settled, and remains so at this day,  that,

where a cause or matters in difference  are  referred  to  an  arbitrator  a

lawyer or a layman, he is constituted  the  sole  and  final  judge  of  all

questions both of law and of fact ...... The only exceptions  to  that  rule

are cases where the award is the result of  corruption  or  fraud,  and  one

other, which  though  it  is  to  be  regretted,  is  now,  I  think  firmly

established viz., where the question of law necessarily arises on  the  face

of the award or upon some paper accompanying and forming part of the  award.

 Though the propriety of this latter may very well be doubted,  I  think  it

may be considered as established."


"Now the regret expressed by Williams, J. in Hodgkinson v. Fernie  has  been

repeated by more than one learned Judge, and  it  is  certainly  not  to  be

desired that the exception should be in any way extended.  An error  in  law

on the face of the award means, in their Lordships' view, that you can  find

in the award or a document actually incorporated thereto, as  for  instance,

a note appended by the arbitrator stating  the  reasons  for  his  judgment,

some legal proposition which is the basis of the award  and  which  you  can

then say is erroneous.  It does not mean that if in a narrative a  reference

is made to a contention of one party that opens the  door  to  seeing  first

what that contention is, and  then  going  to  the  contract  on  which  the

parties' rights depend to see if that  contention  is  sound.   Here  it  is

impossible to say, from what is  shown  on  the  face  of  the  award,  what

mistake the arbitrators made.  The only way that  the  learned  judges  have

arrived at finding what the mistake was  is  by  saying:  "Inasmuch  as  the

Arbitrators awarded so and so, and inasmuch as the letter  shows  that  then

buyer rejected the cotton, the arbitrators can only  have  arrived  at  that

result by totally misinterpreting Cl.52." But they  were  entitled  to  give

their own interpretation to Cl. 52 or any other article, and the award  will

stand unless, on the face of it they  have  tied  themselves  down  to  some

special legal proposition which then, when examined, appears to be  unsound.

 Upon this point, therefore, their Lordships  think  that  the  judgment  of

Pratt, J was right and the conclusion of the learned Judges of the Court  of

Appeal erroneous."




      This judgment has been consistently followed in India to  test  awards

under Section 30 of the Arbitration Act, 1940.


      In the  1996  Act,  this  principle  is  substituted  by  the  'patent

illegality' principle which, in turn, contains three sub heads -


      (a) a contravention of the substantive law of India  would  result  in

the death knell of an arbitral award. This must be understood in  the  sense

that such illegality must go to the root of the matter and cannot  be  of  a

trivial nature. This again is a really a contravention of  Section  28(1)(a)

of the Act, which reads as under:


"28. Rules applicable to  substance  of  dispute.-(1)  Where  the  place  of

arbitration is situated in India,-


(a) in an arbitration other than an  international  commercial  arbitration,

the arbitral tribunal shall decide the dispute submitted to  arbitration  in

accordance with the substantive law for the time being in force in India;"


(b) a contravention of the Arbitration Act itself would  be  regarded  as  a

patent illegality- for example if an arbitrator  gives  no  reasons  for  an

award in contravention of section 31(3) of  the  Act,  such  award  will  be

liable to be set aside.


(c)  Equally,  the  third  sub-head  of  patent  illegality  is   really   a

contravention of Section 28 (3) of  the  Arbitration  Act,  which  reads  as

under:


"28. Rules applicable to substance  of  dispute.-  (3)  In  all  cases,  the

arbitral tribunal shall decide in accordance with the terms of the  contract

and shall take into account the  usages  of  the  trade  applicable  to  the

transaction."


      This last contravention must be understood with a caveat. An  arbitral

tribunal must decide in accordance with the terms of the  contract,  but  if

an arbitrator construes a term of the contract in a  reasonable  manner,  it

will not mean that the award can be set aside on this  ground.  Construction

of the terms of a contract is primarily for an arbitrator to  decide  unless

the arbitrator construes the contract in such a way that it  could  be  said

to be something that no fair minded or reasonable person could do.


            In McDermott International  Inc.  v.  Burn  Standard  Co.  Ltd.,

(2006) 11 SCC 181, this Court held as under:


"112. It is trite that the terms of the contract can be express or  implied.

The conduct of the parties would also be a relevant factor in the matter  of

construction of a contract. The construction of the  contract  agreement  is

within the jurisdiction  of  the  arbitrators  having  regard  to  the  wide

nature, scope and ambit of the arbitration  agreement  and  they  cannot  be

said to have misdirected themselves in passing  the  award  by  taking  into

consideration  the  conduct  of  the  parties.  It  is   also   trite   that

correspondences exchanged by the parties  are  required  to  be  taken  into

consideration for the purpose of construction of a contract.  Interpretation

of a contract is a matter for the arbitrator to determine, even if it  gives

rise to determination of a question  of  law.  (See Pure  Helium  India  (P)

Ltd. v. ONGC [(2003) 8 SCC 593] and D.D. Sharma v. Union of India [(2004)  5

SCC 325]).


113. Once, thus, it is held that the arbitrator  had  the  jurisdiction,  no

further question shall be  raised  and  the  court  will  not  exercise  its

jurisdiction unless it is found that there exists any bar  on  the  face  of

the award."




            In MSK Projects (I) (JV) Ltd. v. State of Rajasthan,  (2011)  10

SCC 573, the Court held:


"17. If  the  arbitrator  commits  an  error  in  the  construction  of  the

contract, that is an error  within  his  jurisdiction.  But  if  he  wanders

outside the contract and deals with matters not allotted to him, he  commits

a jurisdictional error. Extrinsic  evidence  is  admissible  in  such  cases

because the dispute is not something which arises under or  in  relation  to

the contract or dependent on the construction  of  the  contract  or  to  be

determined within the award. The ambiguity of the award can, in such  cases,

be resolved by admitting extrinsic evidence. The rationale of this  rule  is

that the nature of the dispute is  something  which  has  to  be  determined

outside and independent of what appears in the award. Such a  jurisdictional

error needs to be proved by evidence extrinsic to the award.  (See Gobardhan

Das v. Lachhmi  Ram [AIR  1954  SC  689],  Thawardas  Pherumal v. Union   of

India [AIR 1955 SC 468], Union of  India v. Kishorilal  Gupta  &  Bros. [AIR

1959 SC 1362], Alopi Parshad & Sons  Ltd. v. Union  of  India [AIR  1960  SC

588], Jivarajbhai Ujamshi Sheth v. Chintamanrao  Balaji [AIR  1965  SC  214]

and Renusagar Power Co. Ltd. v. General Electric Co. [(1984)  4  SCC  679  :

AIR 1985 SC 1156] )."




            In Rashtriya Ispat Nigam Ltd. v. Dewan Chand Ram  Saran,  (2012)

5 SCC 306, the Court held:


"43. In  any  case,  assuming  that  Clause   9.3   was   capable   of   two

interpretations, the view taken by the arbitrator was clearly a possible  if

not a plausible one. It is not possible  to  say  that  the  arbitrator  had

travelled outside his jurisdiction, or  that  the  view  taken  by  him  was

against the terms of contract. That being the position, the High  Court  had

no reason to interfere with the award and substitute its view  in  place  of

the interpretation accepted by the arbitrator.


44. The legal position in this behalf has been summarised in para 18 of  the

judgment of this Court in SAIL v. Gupta Brother Steel Tubes Ltd. [(2009)  10

SCC 63: (2009) 4 SCC (Civ)  16]  and  which  has  been  referred  to  above.

Similar view has been taken later in Sumitomo Heavy Industries  Ltd. v. ONGC

Ltd. [(2010) 11 SCC 296: (2010)  4  SCC  (Civ)  459]  to  which  one  of  us

(Gokhale, J.)  was  a  party.  The  observations  in  para  43  thereof  are

instructive in this behalf.


45. This para 43 reads as follows:  (Sumitomo  case [(2010)  11  SCC  296  :

(2010) 4 SCC (Civ) 459] , SCC p. 313)


"43. ...  The  umpire  has  considered  the  fact  situation  and  placed  a

construction on the clauses of the agreement which according to him was  the

correct one. One may at the  highest  say  that  one  would  have  preferred

another construction of Clause 17.3 but that cannot make the  award  in  any

way perverse. Nor can one substitute one's own view in such a situation,  in

place of the one taken by the umpire,  which  would  amount  to  sitting  in

appeal. As held by this Court in Kwality Mfg. Corpn. v. Central  Warehousing

Corpn. [(2009) 5 SCC  142  :  (2009)  2  SCC  (Civ)  406]  the  Court  while

considering challenge to arbitral award does not  sit  in  appeal  over  the

findings and decision of the arbitrator, which is what the  High  Court  has

practically done in this matter. The  umpire  is  legitimately  entitled  to

take the view which he holds to be the correct  one  after  considering  the

material before him and after interpreting the provisions of the  agreement.

If he does so, the decision of the umpire has to be accepted  as  final  and

binding."




13.   Applying the tests laid  down  by  this  Court,  we  have  to  examine

whether the Division Bench has exceeded its jurisdiction  in  setting  aside

the arbitral award impugned before it.


14.   A large part of the judgment is an extract from  the  arbitral  award.

It is important to note that the Division Bench held:


"9. A perusal of the award would reveal, from the portions extracted  herein

above,  that  with  reference  to  evidence  led  before  him  the   learned

Arbitrator has held delay attributable to DDA, a finding of  fact  which  is

based on evidence and rightly conceded to by Sh.  Bhupesh  Narula,  Advocate

who appears for DDA as being beyond judicial  review  power  of  this  Court

pertaining to a  reasoned  award.  But,  while  awarding  Rs.8,27,960/-  the

reasoning adopted by the learned  Arbitrator  is  questioned  as  being  the

result of ignoring the well-recognized  legal  principles  on  the  subject,

Learned counsel argued that the reasoning is the ipse dixit of  the  learned

Arbitrator."




15.   The Division Bench while considering claims 9, 10,  11  and  15  found

fault with the application of Hudson's formula which  was  set  out  by  the

learned Arbitrator in order to arrive at the claim made under  these  heads.

The Division Bench said that it  was  not  possible  for  an  Arbitrator  to

mechanically apply a certain formula however well understood in  the  trade.

This itself is going outside the jurisdiction to set aside  an  award  under

Section 34 in as much as in McDermott's case (supra), it was held:


"104. It is not in dispute that MII had  examined  one  Mr  D.J.  Parson  to

prove the said claim. The said witness calculated  the  increased  overheads

and loss of profit on the basis  of  the  formula  laid  down  in  a  manual

published by the Mechanical  Contractors  Association  of  America  entitled

"Change  Orders,  Overtime,  Productivity"  commonly  known  as  the   Emden

Formula. The said formula is said to  be  widely  accepted  in  construction

contracts for computing increased overheads and  loss  of  profit.  Mr  D.J.

Parson is said to have brought out the additional  project  management  cost

at US$ 1,109,500. We may at this  juncture  notice  the  different  formulas

applicable in this behalf.




(a) Hudson Formula: In Hudson's Building and Engineering  Contracts,  Hudson

Formula is stated in the following terms:


|"Contract head office      |        |      |Period of    |

|overhead and profit        |       |Contract period|       |delay"       |

|percentage                 |       |               |       |             |



In the Hudson Formula, the head office overhead  percentage  is  taken  from

the contract. Although the Hudson Formula has received judicial  support  in

many cases, it has been criticised principally because it  adopts  the  head

office overhead percentage from the contract as the factor  for  calculating

the costs, and this may bear little  or  no  relation  to  the  actual  head

office costs of the contractor.


(b) Emden Formula: In Emden's Building Contracts  and  Practice,  the  Emden

Formula is stated in the following terms:


|"Head office overhead and |      |Contract sum   |      |Period of     |

|profit                    |       |               |       |delay"        |

|100                       |       |Contract period|       |              |



Using the Emden Formula, the head office overhead percentage is  arrived  at

by  dividing  the  total  overhead  cost  and  profit  of  the  contractor's

organisation as a  whole  by  the  total  turnover.  This  formula  has  the

advantage of using the contractor's actual head office overhead  and  profit

percentage rather than those contained in the  contract.  This  formula  has

been widely applied and has received judicial support in a number  of  cases

including Norwest  Holst  Construction   Ltd. v. Coop.   Wholesale   Society

Ltd. [Decided  on  17-2-1998,   [1998]   EWHC   Technology   339], Beechwood

Development Co. (Scotland) Ltd. v. Mitchell [ Decided on  21-2-2001,  (2001)

CILL 1727] and Harvey Shopfitters Ltd. v. Adi Ltd. [  Decided  on  6-3-2003,

(2004) 2 All ER 982 : [2003] EWCA Civ 1757].


(c) Eichleay Formula: The  Eichleay  Formula  was  evolved  in  America  and

derives its name from a case heard by the Armed Services Board  of  Contract

Appeals, Eichleay Corporation. It is applied in the following manner:


Step 1


|Contract billings   |       |Total overhead |=      |Overhead allocable to|

|                    |        |for contract   |       |the contract         |

|                    |        |period         |       |                     |

|Total billings for  |        |               |                             |

|contract period     |        |               |                             |



     Step 2


|Allocable overhead                |=        |Daily overhead rate          |

|Total days of contract            |                                       |



      Step 3


|Daily contract    |      |Number of days|=      |Amount of unabsorbed   |

|overhead rate     |       |of delay      |       |overhead"              |



This formula is used where it is not possible to prove loss  of  opportunity

and the claim is based on actual cost. It can be seen from the formula  that

the  total  head  office  overhead  during  the  contract  period  is  first

determined by comparing the value  of  work  carried  out  in  the  contract

period for the project with the value of work carried out by the  contractor

as a whole for the contract period. A share of  head  office  overheads  for

the contractor is allocated in the same ratio and expressed as  a  lump  sum

to the particular contract. The amount of head office overhead allocated  to

the particular contract is then expressed as a weekly amount by dividing  it

by the contract period. The period  of  delay  is  then  multiplied  by  the

weekly amount to give  the  total  sum  claimed.  The  Eichleay  Formula  is

regarded by the Federal Circuit Courts of America  as  the  exclusive  means

for compensating a contractor for overhead expenses.


105. Before us several American decisions  have  been  referred  to  by  Mr.

Dipankar Gupta in aid of his submission that the  Emden  Formula  has  since

been widely accepted  by  the  American  courts  being Nicon  Inc. v. United

States [ Decided on 10-6-2003 (USCA Fed Cir),  331  F.  3d  878  (Fed.  Cir.

2003)], Gladwynne   Construction   Co. v. Mayor   and   City   Council    of

Baltimore [Decided on 25-9-2002, 807 A. 2d 1141 (2002) : 147 Md.  App.  149]

and Charles G. William Construction Inc. v. White [271 F 3d 1055 (Fed.  Cir.

2001)].


106. We do not intend to delve deep into the matter as  it  is  an  accepted

position that different formulae can be applied in  different  circumstances

and the question  as  to  whether  damages  should  be  computed  by  taking

recourse to one or the  other  formula,  having  regard  to  the  facts  and

circumstances of a particular case, would eminently fall within  the  domain

of the arbitrator."




16.   Obviously,  the  Division  Bench  has  exceeded  its  jurisdiction  in

interfering with a possible view of the Arbitrator on facts.


17.   The Division Bench then went on to hold:


"17.  There  is  admittedly  no  evidence  that  the  contractor  i.e.   the

respondent had a central establishment. It appears to be a  case  where  the

contractor is petty contractor and the only expenses  incurred  are  at  the

site.  The claim is towards hire charges paid for centering and  shuttering,

hiring tools, plants  and  scaffoldings  i.e.  the  claim  is  not  for  the

contractor's own equipment lying idle. There is just no  evidence  that  the

contractor paid charges as claimed by him. Not a single bill raised  by  the

alleged person who let on hire the equipment  to  the  contractor  has  been

filed nor any evidence adduced for the payment made. Except  for  listing  a

10 HP Water Pump, 4 number 1  HP  water  pump,  3  mixers,  250  scaffolding

bamboos, 150 ballis and 2  vibrators  in  Annexure-J  to  the  Statement  of

Claim, no document proving hiring the same and brought at the site has  been

led.  We highlight that the claim is on account of  hire  Charges  paid  and

there is no evidence of said payment. It does happen that where  a  work  is

stopped, the person who taken an equipment on hire returns the same and  re-

hires the same when work recommences. Thus, Claim No. 9, 10  and  11  cannot

be allowed because there is no evidence to support the claims.   Damages  on

account of  establishment  expenses  incurred  during  period  contract  got

prolonged have certainly to be recompensed, but we find no evidence  in  the

form of books of accounts, vouchers etc. to show payments to  the  staff  or

expenses incurred in maintaining an establishment at site in the form  of  a

site office. The wages register, photocopy  whereof  was  filed  before  the

Arbitrator, pertains to  wages  paid  to  the  unskilled,  semi-skilled  and

skilled labour deployed to execute the works. The  pleadings  pertaining  to

the claim would show  that  as  per  the  contractor  he  had  deployed  one

Executive  Officer,  one  Graduate  Engineer,  one  Junior   Engineer,   one

Accountant, one Storekeeper and Supervisor and one Mechanic at the site  and

had also deployed watch and ward. Details of the persons employed have  been

listed in Annexure-N to the Statement of Claim and the  documents  filed  to

establish the same would evidence that the contractor has filed  photocopies

of the salary register, which are available from pages No.1255 to 1322,  but

unfortunately for the contractor, the cat is out of the bag when we look  at

the documents.  They pertain to payments made for a site at Mayur Vihar.  We

highlight that the contract in question pertains  to  flats  and  houses  at

Trilokpuri and not Mayur Vihar. It  is  apparent  that  the  contractor  has

tried to pull the wool on the eyes of the primary adjudicator of the  claim.

It is not the case of the contractor that these persons were  simultaneously

supervising the work at two sites. Assuming this was the  case,  the  matter

would then have been adjudicated with reference to same  number  of  persons

supervising two sites and the time spent at each site by them.


18.  Thus, the award pertaining to Claim Nos. 9, 10, 11 and 15 is liable  to

be sent aside and it is so set aside. We need not therefore take  corrective

action on the apparent error i.e. the learned Arbitrator has worked out  the

claim on the original contract value  of   Rs.  87,66,678/-,  of  course  by

reducing it by 15%, but ignoring that final work executed was  only  in  sum

of Rs.62,84,845/-."




18.   Mr. Verma argued correctly that there is nothing  on  record  to  show

that the contractor is  a  petty  contractor  and  that  the  only  expenses

incurred are at the  site.   He  has  shown  us  that  the  contract  itself

required execution of the work by  a  Class-I  contractor  and  has  further

shown us  that  Class-I  contractors  require  to  have  certain  stipulated

numbers of works worth large amounts before they can apply  for  the  tender

and that their financial soundness  has  to  be  attested  too  by  banker's

certificate  showing  that  their  worth  is  over  10  crores  of   rupees.

Further, he has  pointed  out  from  the  statement  of  claims  before  the

Arbitrator that there was evidence for claims 9, 10 and 11 laid  before  the

Arbitrator which the Arbitrator has in fact  accepted.   Also  establishment

expenses were set out in great detail before the Arbitrator and it  is  only

on this evidence that the Arbitrator ultimately has  awarded  these  claims.

Mr. Verma is also right in saying that the  Division  Bench  was  completely

wrong in stating that the establishment expenses pertained to  payments  for

a site at Mayur Vihar as  opposed  to  Trilok  Puri  which  were  where  the

aforesaid houses were to  be  constructed.   He  pointed  out  that  in  the

completion certificate dated  30th  May,  1997  given  by  the  DDA  to  the

appellant,  it  is  clear  that  the  houses  that  were,  in  fact,  to  be

constructed were in Mayur Vihar, Phase-II, which is part of the Trilok  Puri

trans-Yamuna area.


It is most unfortunate that the  Division  Bench  did  not  advert  to  this

crucial document at all.  This document shows not  only  that  the  Division

Bench was wholly incorrect in its conclusion that the contractor  has  tried

to pull the wool over the  eyes  over  the  DDA  but  it  should  also  have

realized that the DDA itself has stated that the work has been  carried  out

generally to its satisfaction barring some  extremely  minor  defects  which

are capable of rectification. It is  clear,  therefore,  that  the  Division

Bench obviously  exceeded  its  jurisdiction  in  interfering  with  a  pure

finding of fact forgetting that the Arbitrator is  the  sole  Judge  of  the

quantity and quality of evidence before him and  unnecessarily  bringing  in

facts  which  were  neither  pleaded  nor  proved  and  ignoring  the  vital

completion certificate granted by the DDA itself. The  Division  Bench  also

went wrong in stating that as the work completed was only to the  extent  of

Rs. 62,84,845/-, Hudson's formula  should  have  been  applied  taking  this

figure into account and not the  entire  contract  value  of  Rs.87,66,678/-

into account.


19.   Here again, the Division Bench has committed a grave  error.  Hudson's

formula as is quoted in McDermott's case is as follows:


"(a) Hudson Formula: In Hudson's Building and Engineering Contracts,  Hudson

Formula is stated in the following terms:


|"Contract head office      |        |      |Period of    |

|overhead and profit        |       |Contract period|       |delay"       |

|percentage                 |       |               |       |             |



In the Hudson Formula, the head office overhead  percentage  is  taken  from

the contract. Although the Hudson Formula has received judicial  support  in

many cases, it has been criticised principally because it  adopts  the  head

office overhead percentage from the contract as the factor  for  calculating

the costs, and this may bear little  or  no  relation  to  the  actual  head

office costs of the contractor."




20.   It is clear that to apply this formula one has to  take  into  account

the contract value that is awarded and not  the  work  completed.   On  this

score again, the Division Bench is to be faulted.


21.   In dealing with claims 12 and 13, the Division Bench stated:


"19.  Pertaining  to  Claim  No.12  and  13,  the  learned  Arbitrator   has

recompensed the contractor 20% price  hike  in  the  cost  of  material  and

labour noting, that there was a steep hike in the period  in  question  when

the contract got prolonged by  25  months.  We  highlight  that  though  the

Arbitrator has found  the  delay  to  be  25  months,  recompense  has  been

restricted to only 20 months.


20. As noted herein above, partial recompense under  Clause  10C,  has  been

granted to the  contractor,  but  the  same  i.e.  the  Clause  in  question

requiring applicability during contract stipulated period,  it  is  apparent

that the contractor would be entitled to  full  recompense  for  price  hike

during the extended 25 months period and not the  20  months  to  which  the

learned Arbitrator has restricted the recompense to.


21.   But, for the benefit granted under Clause 10C wherein Rs.  1,62,387/-,

Rs.46,184/- and Rs.12,922/- have  been awarded under Claim Nos. 2, 3 and  4,

said amounts have to be adjusted, but not in  full,  for  the  reason  these

include the amounts payable during the contract stipulated period.


22.  The total of the three sums comes to Rs, 2, 21,493/-. We  have  another

problem. Neither counsel could help us identify the components thereof  i.e.

the component relatable to the 9 months during which  the  work  had  to  be

completed and the 25 months during which the contract got  prolonged.  Thus,

we apply the Rule of 'Rough and Ready Justice'. We divide the sum by  34  to

work out the proportionate increase per month.  Rs.  2,21,493/-  divided  by

34 = Rs.6,514.50 and multiplying  the  same  by  25,  the  figure  comes  to

Rs.1,62,862.50.


23. Adopting, for the reasons given by the Arbitrator, that 20% hike in  the

balance work done after the contract stipulated period i.e.  benefit  to  be

granted under  this  head  for  work  done  in  sum  of  Rs.37,02,066/-  and

accepting the sum of Rs.7,20,000/- being the resultant  figure,  subtracting

Rs.1,62,862.50, the figure arrived at is Rs.5,57,137.50."




22.   Here again,  the  Division  Bench  has  interfered  wrongly  with  the

arbitral award on several counts.  It had no business to enter into  a  pure

question of fact to set aside the Arbitrator for having  applied  a  formula

of 20 months instead of 25 months. Though this would inure in favour of  the

appellant, it is clear that the appellant did not file any  cross  objection

on this score.  Also, it is extremely curious that the Division Bench  found

that an adjustment would have to be made with claims  awarded  under  claims

2, 3 and 4 which are entirely  separate  and  independent  claims  and  have

nothing to do with claims 12 and  13.   The  formula  then  applied  by  the

Division Bench was that it would itself do "rough and  ready  justice".   We

are at a complete loss to understand how this  can  be  done  by  any  court

under the jurisdiction exercised under Section 34 of  the  Arbitration  Act.

As has been held above, the expression "justice" when it  comes  to  setting

aside an award under the public policy ground can only mean  that  an  award

shocks the conscience of the court.  It cannot  possibly  include  what  the

court thinks is unjust on the facts of a case for which  it  then  seeks  to

substitute its view for the Arbitrator's view and does what it considers  to

be "justice".  With great respect to the Division Bench, the whole  approach

to setting aside arbitral awards is incorrect. The Division Bench  has  lost

sight of the fact that  it  is  not  a  first  appellate  court  and  cannot

interfere with errors of fact.


23.   We come now to the arguments of Mr. Sharan in support of the  Division

Bench judgment. The learned  counsel  strongly  relied  on  clause  10C  and

clause 22.  These two clauses are set out as below:


Clause 10C of the agreement reads as follows:


"If  during  the  progress  of  the  works,  the  price  of   any   material

incorporated in the works, (not being a material supplied from the Engineer-

in-Charge's stores in accordance with  Clause  10  hereof  and/or  wages  of

labour increases as direct result of the coming  into  force  of  any  fresh

law, or statutory rule or order (but not due to any changes  in  sales  tax)

and such increase exceed ten per cent of the price and/or  wages  prevailing

at the time of receipt of the tender for the work, and contractor  thereupon

necessarily and properly pays in respect of the  material  (incorporated  in

the work) such increased price and/or in respect of labour  engaged  on  the

execution of the work such increased wages, then the amount of the  contract

shall accordingly be varied provided always that any increase so payable  is

not, in the opinion of the Superintending Engineer (whose decision shall  be

final and binding) attributable  to  delay  in  execution  of  the  contract

within the control of the contractor. Provided, however,  no  reimbursements

shall be made if the increase is not more than 10% of the said  prices/wages

and if so the reimbursements shall be made only on the excess over  10%  and

provided further that any  such  increase  shall  not  be  payable  if  such

increase has become  operative  after  the  contract  or  extended  date  of

completion of the work in question.


      If during the progress  of  the  works,  the  price  of  any  material

incorporated in the works (not being a material supplied from the  Engineer-

in-Charge's stores in accordance with Clause  10  hereof)  and/or  wages  of

labour is decreased as a direct result of  the  coming  into  force  of  any

fresh law or statutory rule or order (but not due to any  changes  in  sales

tax) and such decrease exceeds ten per  cent  of  the  prices  and/or  wages

prevailing at the time  of  receipt  of  the  tender  for  the  work,  Delhi

Development Authority shall in respect  of  materials  incorporated  in  the

work (not being materials supplied from the Engineer-in-Charge's  stores  in

accordance with Clause 10 hereof) and/or labour engaged on the execution  of

the work after the date of coming into force of such law, statutory rule  or

order be entitled to deduct from the dues of the contractor such  amount  as

shall be equivalent of difference between the prices of  materials  and/  or

wages as they prevailed at the time of receipt of tender for the work  minus

ten per cent thereof and the prices of materials and/ or wages of labour  on

the coming into force of such law, statutory rule or order.


The contractor shall for the purpose of this condition keep  such  books  of

account and other documents as are necessary  to  show  the  amount  of  any

increase claimed or reduction available and shall allow  inspection  of  the

same by a duly authorised representative of Delhi Development Authority  and

further shall, at the request of the  Engineer-in-Charge  furnish,  verified

in such a manner as the Engineer-in-Charge may  require.  Any  document,  so

kept and such other information as the Engineer-in-Charge may require.


The contractor shall, within a reasonable time of his becoming aware of  any

alteration in the prices of any such materials and/ or wages of labour  give

notice thereof to the Engineer-in- Charge stating that the same is given  in

pursuance to the condition together with all  information  relating  thereto

which he may be in a position to supply."


Clause 22 reads as follows:


"All sums payable by way of compensations  under  any  of  these  conditions

shall be, considered as reasonable compensation to be applied  to  this  use

of Delhi Development Authority without  reference  to  the  actual  loss  or

damage sustained, and whether or not any damage shall have been sustained.


Specifications and Conditions:


1. The contractor must get acquainted with the proposed site for  the  works

and study specifications and  conditions  carefully  before  tendering.  The

work shall be executed as per programme approved by the  Engineer-in-Charge.

If part of  site  is  not  available  for  any  reasons  or  there  is  some

unavoidable delay in supply of materials stipulated by the Departments,  the

programme of construction shall be modified accordingly and  the  contractor

shall have no claim for any extras or compensation on this account."




24.   Clause 10C concerns itself with the price of material incorporated  in

the works or wage or labour increases.  It has been seen that claims  9,  10

and 11 have nothing to  do  with  either  of  the  aforesaid  subjects.   In

seeking to apply this clause to claim 15, the simple  answer  is  that  this

clause will not apply when a  claim  for  damages  is  made.   Further,  the

Arbitrator considered this clause in detail and only awarded  amounts  under

this clause in excess of 10 percent as required by the clause when  it  came

to awarding amounts under claims 2, 3 and 4, which fell within the ambit  of

clause 10C.  The DDA in the appeal before the Division Bench correctly  gave

up any challenge to these claims as has been recorded in paragraph 4 of  the

order under appeal.


25.   The Arbitrator has dealt with this clause in detail and has  construed

and applied the same correctly while dealing with claims 2, 3 and 4 and  has

obviously not applied the said clause to claims 9,  10,  11  and  15  as  no

occasion for applying the same arose. The award cannot be  faulted  on  this

ground.


26.   Also, so far as clause 22 is concerned, the  DDA  did  not  raise  any

argument based on this clause before the  learned  Arbitrator.  However,  it

must in fairness be stated that it was  argued  before  the  learned  Single

Judge.  In para 15 of his judgment, the learned Judge sets  the  clause  out

and then  follows  a  judgment  of  the  High  Court  of  Delhi  in  Kochhar

Construction Works v. DDA & Anr.,  (1998) 2 Arb. LR  209.   Apart  from  the

fact that a learned Single Judge of the same court is bound  by  a  previous

judgment of a Single Judge, the conclusion of the learned Single Judge  that

if the  appellant  is  at  fault  and  the  contract  is  prolonged  for  an

inordinate period of time, it cannot be said that the respondents cannot  be

compensated for the same is correct.  Besides,  this  point  was  not  urged

before the Division Bench and must be taken to  be  given  up.   Mr.  Sharan

cited Harsha Constructions v. Union of India & Ors., (2014)  9  SCC  246  to

say that in respect of excepted matters, no  arbitration  is  possible,  and

that this being a jurisdictional point, he should be  allowed  to  raise  it

before us.   Unfortunately for Mr.  Sharan,  the  clause  does  not  operate

automatically. It only operates if an objection is taken stating  that  part

of the site is not available for any reason.  Nowhere  has  the  DDA  stated

which part of the site is  not  available  for  any  reason.   Further,  the

learned Single Judge's reason  for  rejecting  an  argument  based  on  this

clause also commends itself to us as the object of this clause  is  that  no

claim for extras should be granted only if there is  an  unavoidable  delay.

We have seen that the delay was entirely avoidable and caused solely by  the

DDA itself.


27.   One more point needs to be noted. An  argument  was  made  before  the

learned Single Judge that there has been a duplication  of  claims  awarded.

The learned Judge dealt with this argument as follows:


"18. Learned counsel for the petitioner in respect of ground P,  once  again

makes a reference to the issue that there is overlapping of the claim. I  am

unable  to  accept  the  submission  made  by  the  learned  counsel.    The

consequence of delay may have more  than  one  ramifications  including  the

cost of material the supervision required at the site, the inability of  the

contractor to utilise the manpower at some other  place,  the  inability  of

the contractor to make, profits from some other contract by  utilisation  of

the same resources. All these aspects  are  liable  to  be  considered.  The

Arbitrator has considered the claims separately and has dealt  with,  claims

9, 10, 11 & 15 together. Claims 12 & 13 have been thereafter dealt  with  on

the same principles since it was found that it was not the  respondent,  who

was responsible for  the  delay  for  a  period  of  25  months  beyond  the

stipulated condition of 9 months.


19. There is thus no question of overlapping  in  different  heads  and  the

grievance of the petitioner is rejected."




28.   The Single Judge is clearly right.  We have gone through  all  the  15

claims supplied to us and we find that none of  these  claims  are  in  fact

overlapping. They are all contained under separate  heads.   This  argument,

therefore, must also fail.


29.    The appeal is, therefore, allowed and the judgment  of  the  Division

Bench is set aside.   The  judgment  of  the  Single  Judge  is  upheld  and

consequently, the Arbitral award dated 23rd May, 2005 is as a whole  upheld.

 There will be no order as to costs.



                                   .......................................J.

                                                      (Ranjan Gogoi)




                                    ......................................J.

                                                      (R.F. Nariman)


New Delhi,

November 25, 2014

-----------------------

[1]


      [2]Very often an arbitrator is a lay person  not  necessarily  trained

in law. Lord  Mansfield,  a  famous  English  Judge,  once  advised  a  high

military officer in Jamaica who needed to act as a Judge as follows:

      "General, you have a sound head, and a good heart;  take  courage  and

you will do very well, in your occupation, in a court of equity.  My  advice

is, to make your decrees as your head and your heart dictate, to  hear  both

sides patiently, to decide with firmness in the best manner you can; but  be

careful not  to  assign  your  reasons,  since  your  determination  may  be

substantially right, although your reasons may be very bad,  or  essentially

wrong".

      It is very  important  to  bear  this  in  mind  when  awards  of  lay

arbitrators are challenged.