Supreme Court of India (Division Bench (DB)- Two Judge)

Appeal (Civil), 2426 of 2015, Judgment Date: Feb 25, 2015

                                                          NON-REPORTABLE

                        IN THE SUPREME COURT OF INDIA
                        CIVIL APPELLATE JURISDICTION

                        CIVIL APPEAL NO. 2426 OF 2015
                 (Arising Out of SLP (C) No. 34955 of 2013)


   ANDHRA PRADESH INDL. INFRASTRUCTURAL
   CORPORATION LTD. & ANR.                               ......APPELLANTS

                                   VERSUS


M/S. SHIVANI ENGINEERING INDUSTRIES                      ......RESPONDENT


                               J U D G M E N T

V.GOPALA GOWDA, J.

Leave granted.
The appellant-Andhra Pradesh Industrial Corporation  Ltd.  (for  short  "the
Corporation") is aggrieved by the judgment and order dated 20.8.2013 of  the
High Court of Judicature of Andhra  Pradesh  at  Hyderabad  passed  in  Writ
Appeal No. 1273 of 2013 whereby the High Court  dismissed  the  writ  appeal
and affirmed the judgment and order dated 26.4.2013 of  the  learned  single
Judge passed in Writ Petition   No.11978 of 2012. This appeal  is  filed  by
the Corporation seeking for setting aside the impugned judgment  and  orders
passed in the writ appeal and writ petition by allowing this appeal,  urging
various facts and legal contentions.
The brief facts are stated in this judgment for the purpose of  appreciating
the rival legal contentions urged on behalf of the parties, with a  view  to
find out as to whether the impugned judgments and orders passed by both  the
Division Bench of the High Court and the learned single Judge  are  required
to be interfered with by this Court.
The  Corporation  (which  is  one  of  the  State  Undertaking  Corporations
established to promote the industrial growth and development  in  the  State
of Andhra Pradesh) on the  application  filed  by  M/s  Shivani  Engineering
Industries-the respondent herein for allotment of industrial plot  measuring
10,000 sq. mtrs., allotted plot No.181  of  Phase-III,  Industrial  Park  at
Pashamylaram to an extent of 12000 sq. mtrs. at a  price  of  Rs.72,00,000/-
in its favour and the said amount was to be paid by  the  respondent  within
90 days  of the  receipt  of  the  provisional  allotment  and  required  to
implement the project within 2 years from the  date  of  possession  of  the
allotted plot of land, failing which the plot was liable to be cancelled  by
the Corporation as per terms and conditions enumerated  in  the  provisional
allotment letter dated 20.6.2006. The relevant clauses from the  provisional
allotment order read thus:-
"2. You should pay the cost  of  land  which  works  out  to  Rs.72,00,000/-
within Ninety days from the date of receipt  of  the  allotment  order,  EMD
already paid.

        XXX  XXX       XXX

7.    If payment as stipulated in condition (2)above is not made  within  90
days of receipt of this allotment letter, this allotment letter shall  stand
cancelled and EMD paid shall remain forfeited.

      XXX      XXX     XXX

18.   You should implement the project envisaged within two years of  taking
possession of the  plot.  If  within  two  years  from  the  date  of  final
allotment and taking possession of the plot the project is not  implemented,
the allotment will be cancelled."

It is the case of the Corporation that the respondent has committed  default
in making said payment to it within stipulated time as payment  should  have
been made within 90 days from the date of receipt of  the  allotment  letter
which was not done by the respondent, but on the other  hand  on  18.9.2006,
the respondent sought for extension  of  time  for  making  payment  of  the
allotted industrial plot by 30.11.2006.
On 22.9.2006, it was found by  the  Corporation  that  the  industrial  plot
allotted in favour of the respondent was more than  the  area  mentioned  in
the provisional allotment, the area of the industrial land  was  revised  as
14046 sq. mtrs. and the cost payable  by  the  respondent  was  re-fixed  at
Rs.84,27,600/-. Despite having extended the  time  by  the  Corporation  for
making payment of land cost with interest @18%  p.a.  till  30.11.2006,  the
respondent again did not make the payment for the  plot  which  resulted  in
cancellation of the provisional allotment of industrial plot made in  favour
of the respondent by the Corporation vide its letter dated 16.12.2006.
Being aggrieved by the said action of the Corporation, the  respondent  made
representation on 3.2.2007 for restoration of the provisional  allotment  of
land in favour of the respondent. The Corporation  acceded  to  its  request
and it has  informed  on  21.2.2007  to  the  respondent  stating  that  the
restoration of allotment of plot of land will be done subject to payment  of
total cost of the  allotted  land  with  interest  on  belated  payment  and
penalty of 10% of the land cost at the prevailing rate and after making  the
payment the suit plot can be registered in favour of the respondent.
The respondent  made  the  payment  on  2.3.2007  for  the  industrial  plot
allotted in its favour and an agreement of sale was  executed  on  13.3.2007
between the Corporation and the respondent and possession of the  industrial
plot was given to the respondent on the same day. The relevant  clause  Nos.
'3 and 9c' of agreement of sale read thus :-
"3.   Only on the Party of the Second Part implementing the  scheme  in  the
allotted plot, the sale deed will be executed and registered.
    XXX        XXX        XXX
9c.The party of the Second Part  shall  implement  the  project  within  two
years of being put in possession of the said plot as detailed  at  clause  3
above."

The respondent on 2.9.2008 has sought for change of manufacturing   activity
from mosquito coils to heavy engineering project and bus-body  manufacturing
unit. The respondent made an application for  loan  to  the  State  Bank  of
India for setting up the industry. On 23.9.2008, the  State  Bank  of  India
has asked the Corporation for issuing NOC for mortgaging the  plot  allotted
to the respondent for sanction of the loan in its favour. On  25.9.2008  the
Corporation approved the change of manufacturing  activity  after  receiving
requisite fees.
 On 21.1.2009 the Corporation was intimated by the respondent  that  it  has
completed the construction of a shed, office accommodation  and  stores  and
asked for registration of the allotted plot in its favour.
 On 12.3.2009, the period of two years stipulated for the completion of  the
project in the agreement was expired.  Further,  Andhra  Bank  also  sent  a
letter on 6.11.2009 to the Corporation requesting it  for  issuing  NOC  for
mortgage of the allotted plot of land for sanctioning the loan in favour  of
the respondent for setting up the project. According to the  respondent,  in
the month of November, 2010, there was installation of plant  and  machinery
and commencement of production on 1.12.2010.
 On 7.1.2011, a  Circular  Notice  was  issued  to  the  respondent  by  the
Corporation for charging fee @ 2% upto 1 year and 3% after 2  years  as  fee
for condonation of delay in implementation of the project for which  purpose
the plot was allotted in its favour. On 10.8.2011  the  respondent  wrote  a
letter to the Corporation asking them for registration of the  plot  in  its
favour. On 8.11.2011, the Corporation asked the respondent to pay an  amount
of Rs.8,42,760/- being 3% of the allotted plot cost towards condonation  fee
for delay in implementation of the project.
 Being aggrieved on the demand of condonation fee by  the  Corporation,  the
respondent filed writ petition No. 11978 of 2012 before the  High  Court  of
Judicature of Andhra Pradesh  at  Hyderabad,  challenging  the  validity  of
demand of condonation fee from the  respondent  and  prayed  for  issuing  a
direction to  the  Corporation  to  execute  registered  sale  deed  of  the
allotted plot in its favour. The said  writ  petition  was  opposed  by  the
Corporation by  filing  its  counter  affidavit  justifying  the  demand  of
condonation fee from the respondent for non-implementation of the project.
 The learned single Judge  of  the  High  Court  has  recorded  the  finding
holding that the plea of the respondent  that the  project  was  implemented
within a period of two years was not accepted, however it  has  allowed  the
writ petition on 26.4.2013 with a direction to the  Corporation  to  execute
the registered sale deed in favour of the  respondent   in  respect  of  the
allotted plot within two months without  charging  any  condonation  fee  of
Rs.8,42,760/- as demanded by the Corporation from  the  respondent  for  the
delay caused for implementation of the project.
 Aggrieved of the said judgment and order of the learned single Judge,  Writ
Appeal No. 1273 of 2013 was filed by the  Corporation  before  the  Division
Bench of the High Court seeking for setting  aside  the  said  judgment  and
order of the learned single Judge, urging various legal contentions.
 The Division Bench  of  High  Court  vide  its  judgment  and  order  dated
20.8.2013 dismissed the writ appeal of  the  Corporation  holding  that  the
penalties for restoration of allotment as well as the interest  has  already
been collected by the Corporation apart from the full cost of the land  from
the respondent. The allotment of plot made at       Rs.600/-  per  sq.  mtr.
was increased substantially on account of the  additional  amount  collected
from the respondent and therefore, it is  held  that  having  collected  the
entire cost of  land,  penalty,  interest  and  further  demand  of  fee  by
describing it as  delay  condonation  fee  from  the  respondent  is  wholly
unjustified  and  the  same  would  amount  to  unjust  enrichment  by   the
Corporation. As the respondent already  implemented  the  project  with  the
approval of the Corporation, it is not open for the  Corporation  to  demand
any additional amount now, in the name  of  delay  condonation  fee.  It  is
further held by the High Court  that  clauses  of  the  agreement  for  sale
relied upon by the learned senior counsel on behalf of  the  Corporation  do
not support its claim and as such the finding was recorded  by  the  learned
single Judge by allowing the  writ  petition  and  given  direction  to  the
Corporation as per para 15 of the judgment of the learned single Judge.  The
Division Bench of the High Court has dismissed the writ appeal by  affirming
the judgment and order of the learned single Judge. The correctness  of  the
judgment and order of the Division Bench of the High Court is challenged  in
this appeal, urging various legal contentions and prayed to set  aside  both
the judgments and orders of the learned single Judge and the Division  Bench
of the High Court.
 Mr. P.P. Rao, the  learned  senior  counsel  appearing  on  behalf  of  the
Corporation sought to justify the demand of condonation  delay  fee  of  the
allotted plot from the respondent for non-implementation of  project  within
two years as agreed by it which was impugned in  the  writ  petition  before
the learned single Judge urging untenable grounds.
It was further contended  by  the  learned  senior  counsel  that  both  the
learned single Judge as well as the Division Bench of High Court   have  set
aside  the  demand  of  condonation  of  delay  fee  for  delay  caused   in
implementation of the project as per the rates at 2% and  3%,  holding  that
the same is not permissible in law  without  noticing  the  clauses  in  the
provisional  allotment  letter  dated  20.6.2006.  The  clause  7   of   the
provisional allotment letter states that if  payment  of  Rs.72,00,000/-  as
stipulated in condition number two extracted above is  not  made  within  90
days  from  the  date  of  receipt  of  allotment  letter,  the  provisional
allotment of plot shall stand cancelled and EMD paid shall remain  forfeited
by the Corporation.  Clauses 18, 18A and 18B of  the  provisional  allotment
letter read thus :-
"18.        You should implement the project envisaged within two  years  of
taking possession of the plot. If within two years from the  date  of  final
allotment and taking possession of the plot the project is not  implemented,
the allotment will be cancelled.
IMPLEMENTATION MEANS:
18A.        You should have implemented the project in  full  as  envisaged.
Where for bonafide reason, there is some delay in implementation,  at  least
you should have implemented the project substantially.
SUBSTANTIAL IMPLEMENTATION MEANS;
18B.         You  shall  have  completed  Civil  Works  and  also  completed
erection of most of the plant and machinery(at  least  80%  of  the  Project
Cost)..."

Despite  the  aforesaid  clauses,  the  Corporation  was  liberal   in   not
cancelling the provisional allotment  of plot made in favour  of  respondent
for non-compliance of  the  aforesaid  conditions  rather  it  extended  the
period upto 30.11.2006 for making cost of allotted plot in its  favour.  For
non-payment of the revised cost of Rs.84,27,600/- of the  allotted  plot  to
the Corporation and  the  non-compliance  of  the  said  conditions  by  the
respondent,  the  Corporation  on  16.12.2006  cancelled   the   provisional
allotment  of  plot  made  in  favour  of  the  respondent.   Further,   the
Corporation was also liberal in  giving  permission  to  the  respondent  to
change the manufacturing activity originally  proposed  with  further  terms
and conditions imposed upon the respondent, the  same  also  have  not  been
complied with by the respondent.
Further, the learned  senior  counsel  on  behalf  of  the  Corporation  has
contended that the learned  single  Judge  has  erroneously  set  aside  the
demand of 3% condonation fee for delay in implementation of the  project  by
the respondent. If the respondent was not willing  to  pay  the  condonation
delay fee for implementing the project, then  the  High  Court  should  have
seen that the Corporation had liberty to exercise its right and  resume  the
land after cancelling the allotment of plot made in favour of respondent  as
per terms and conditions of the provisional allotment  letter.  The  learned
single Judge without examining the above relevant aspects and the terms  and
conditions  incorporated  in  the  provisional  allotment  letter  and   the
agreement of sale  between  the  parties,  has  erroneously  held  that  the
Corporation is not empowered to collect the condonation of delay fee  at  3%
from the respondent as it has already collected  the  penalty  of  10%  with
interest on the belated payment made by the respondent and further  directed
the Corporation to execute  the  registered  sale  deed  in  favour  of  the
respondent in respect of the allotted plot. The said order  is  affirmed  by
the Division Bench without noticing that the  respondent  is  bound  by  the
terms and conditions of the provisional allotment letter, agreement  between
the parties and earlier cancellation order passed  by  the  Corporation  for
non-compliance of the condition i.e. not paying the amount  within  90  days
from  the  date  of  receipt  of  the  allotment  letter.  Even  after   the
restoration of allotment, further  period  was  extended  and  even  it  was
permitted to change its project, even though  it  has  not  implemented  the
original project within that period and the extended period, therefore,  the
Corporation keeping in view the extension of period granted, condonation  of
delay fee at  3%  was  demanded   for  non-implementation  of  the  required
project, if that was not acceptable to the respondent then  the  High  Court
should not have interfered with the demand made by the  Corporation  and  it
should have permitted the Corporation to invoke its right under  clauses  2,
7 and 18(A) and 18(B) of the provisional allotment letter and clauses 3  and
9(c)   of  the  Agreement  of  Sale  extracted  above  and   permitted   the
Corporation to  resume the land from the respondent.
 On the contrary Mr. Annam D.N. Rao, the learned counsel on  behalf  of  the
respondent sought to justify  the finding and reasons recorded by  the  High
Court in the judgment and order of the learned  single  Judge  holding  that
there is no justification on the  part  of  the  Corporation  to  demand  3%
condonation of delay fee from the respondent for non-implementation  of  the
required project within the stipulated time for the reason that the  delayed
payment with interest and 10% penalty has  already  been  collected  by  the
Corporation in respect of the allotted plot. The same has been  rightly  set
aside by the learned single Judge and the same is affirmed by  the  Division
Bench of High Court by assigning valid and cogent reasons  in  the  impugned
judgment and therefore, he submits that the impugned judgment does not  call
for interference by this Court.
Further, it is contended by the learned counsel for the respondent that  the
Corporation has extended time for similarly placed 150 allottees,  for  non-
implementation of project within two years and collected  interest  and  10%
penalty amount from them on the provisional allotment. Therefore,  there  is
no justification on the part of the Corporation  to  demand  penalty  of  3%
from  the  respondent  towards  the  condonation  of  delay  fee  for   non-
implementation of the required project, which is unlawful  on  the  part  of
the Corporation and its action is actually arbitrary and  unreasonable,  and
the demand is not traceable to  any  legal  provisions  and  the  terms  and
conditions of the provisional allotment letter issued to the  respondent  by
further extending the period by the Corporation in its favour including  the
change of manufacturing activity by revising its earlier project.
We have very carefully examined the rival legal contentions urged on  behalf
of the parties with a view to find out as to whether the impugned  judgments
and order warrant interference of  this  Court.  We  have  to  consider  the
relevant clauses of the provisional allotment letter,  which  are  extracted
as above, particularly, the original allotment of plot was  made  in  favour
of the respondent on 20.6.2006 subject to payment of  Rs.72,00,000/-  within
90 days from the date of receipt of the allotment letter. Further, clause  7
of the said provisional allotment letter provides if  the  above  said  plot
cost is not made within 90 days of  receipt  of  the  allotment  letter  the
allotment of plot shall stand  cancelled  and  the  EMD  paid  shall  remain
forfeited by the Corporation. It is an undisputed  fact  that  on  22.9.2006
the allotted plot in favour of the respondent was found to be more than  the
area mentioned in the provisional allotment letter and the area was  revised
as 14046 sq. mtrs. as also the cost payable was  revised  at  Rs.84,27,600/-
and despite the  Corporation  extending  time  for  making  payment  by  the
respondent  till  30.11.2006,  the  same  was  not  paid.   Therefore,   the
provisional allotment was cancelled by the Corporation for  not  making  the
payment within stipulated time. The representation was given on 3.2.2007  by
the respondent for restoration of allotment of the plot  and  the  same  was
accepted  by  the  Corporation  by  informing  the   respondent   that   the
restoration of the provisional allotment of plot will  be  done  subject  to
the payment of total cost of plot  with  interest  on  belated  payment  and
penalty of 10% of the land cost at the prevailing  rate.  The  same  is  the
concession given by the Corporation to the respondent as it could  not  have
restored the provisional allotment of the plot as the  said  restoration  of
allotment was totally impermissible in  law.  The  concession  was  made  in
favour of the respondent by executing the agreement of sale of the  plot  on
13.3.2007 and the possession of the plot was also given on the same day  and
within two years from the date of possession of the said  plot  the  project
should have been implemented  by  the  respondent.  Despite  the  change  of
manufacturing activity from mosquito coil to heavy engineering  project  and
bus-body manufacturing  unit,   the  project  was  not  implemented  by  the
respondent within the said period. Therefore, the terms  and  conditions  of
the provisional allotment letter and  the  agreement  of  sale  executed  on
13.3.2007 are violated by it, therefore, the  Corporation  was  entitled  to
cancel the allotment of plot  and  resume  the  land  from  the  respondent,
instead of doing so, the Corporation has again made  concession  by  calling
upon the respondent to pay the  condonation  fee  at  3%  which  is  totally
impermissible in law. The same  was  challenged  by  the  respondent  taking
untenable stand that it is not liable to pay the same in view  of  the  fact
that the plot cost with interest on delayed plot cost and  10%  penalty  has
already been paid to the Corporation and the Corporation  is  not  empowered
to levy 3% of the land cost as condonation fee for delay  in  implementation
of the revised  project.  If  that  condition  was  not  acceptable  to  the
respondent, the only course left open for  Corporation  was  to  cancel  the
allotment and resume the land and allot the same in favour  of  an  eligible
applicant in accordance with the rules prevailing in law in this  regard  by
giving  advertisement  in  the  newspapers  and  inviting  applications  for
allotment of the project in public auction, as the property is  required  to
be sold in the above manner to get the market value of the  industrial  plot
in the absence of allotment Rules is the law laid  down  by  this  Court  in
catena of cases. Instead of doing so, the Corporation has proceeded with  to
issue the demand notice of 3% of the plot cost towards the  condonation  fee
for delay in implementation of the project. The same was not  acceptable  to
the respondent and therefore it has approached the  High  Court  seeking  to
quash the same contending that the Corporation has no right to  demand  such
fee and  therefore,  it  is  not  liable  to  pay  condonation  fee  to  the
Corporation. The High Court should not have  passed  the  impugned  judgment
and  order  quashing  the  demand  notice  and  giving  direction   to   the
Corporation to register the sale deed in respect of the plot  in  favour  of
the respondent, undisputedly the respondent has not implemented the  revised
project within 2 years from the date of  agreement  though  it  was  put  in
possession of the plot and granting permission to change  the  manufacturing
activity and extended the period. Hence, the impugned judgment and order  of
the single Judge which was affirmed by the Division Bench of the High  Court
is liable to be set aside. Liberty is also given to the Corporation to  take
necessary action to invoke the relevant clauses  of  agreement  of  sale  to
cancel the allotment of allotted plot and resume the same by issuing  notice
to the respondent. It is also brought to our notice by the  learned  counsel
Mr. Annam D.N. Rao on behalf of the  respondent  that  the  Corporation  has
extended time in favour of  nearly  more  than  150  similarly  placed  plot
allottees for not implementing the projects within  2  years  and  extending
period by collecting interest and 10% penalty amount on the  allotment  cost
on provisional allotment of land but no condonation of delay  fee  for  non-
implementation of the  project  was  levied  and  collected  from  them  and
therefore, the action of the Corporation is arbitrary and discriminatory.
In view of above submissions, we are of the view  that  the  Corporation  is
not diligent  in disposing  of  the  industrial  plots  acquired  by  it  in
accordance with law  in favour of the eligible applicants  keeping  in  view
after acquiring the land of the owners for the purpose  of  the  development
of industrial estate and allot the same in favour  of  eligible  persons  to
start industries on the allotted plots to  generate  employment  to  provide
employment to the unemployed youth in  the  State.   Having  regard  to  the
facts and circumstances of the case, the Corporation and  its  officers  are
very generous in extending time in favour of the allottees for  implementing
the  projects  on  the  allotted  plots  and  not  invoking  its  right  for
cancellation and resuming the plot for non-compliance  with  the  terms  and
conditions of allotment letter and agreement and     re-allot  the  same  in
public auction in favour of eligible persons. Therefore, it is  a  fit  case
for this Court to give direction to  the  CoD  of  the  Telangana  State  to
conduct a detailed investigation in the matter against all the officers  who
are involved in the cases of allotment of plots and extending the period  in
favour of the  allottees  for  implementation  of  the  projects  for  which
purpose the plots are allotted and not cancelling  the  allotments  made  by
the Corporation and resumed the plots and dispose of the same in  accordance
with law by taking steps. The CoD, Police must investigate the cases in  the
Corporation and  take  suitable  action  in  this  regard  against  officers
involved in such cases.
 With the aforesaid observation and direction to the  State  Government  and
CoD, Police, the appeal is allowed, the impugned  judgments  and  orders  of
both the learned single Judge and the Division Bench of the High  Court  are
set  aside.  The  Corporation  is  directed  to  withdraw  the   demand   of
condonation of delay fee issued to the respondent and  take  further  action
for resumption of the plot allotted to the respondent. The  CoD/CID  of  the
State Government of  Telangana  represented  by  its  Inspector  General  of
Police or Director General or whomsoever concerned, is directed  to  conduct
investigation and conclude  the  same  and  submit  the  report  before  the
jurisdictional court within four months from the  date  of  receipt  of  the
copy of this judgment. The Registry is directed to send the copies  to  them
and submit its compliance report for perusal of this Court.

  .....................................................................J.

                                              [V. GOPALA GOWDA]


    ..................................................................J.
                                                 [R. BANUMATHI]

New Delhi,
February 25, 2015

For the Latest Updates Join Now